The question for our decision is whether the appeal was applied for within the three months’ period provided by law. 28 U. S. C. § 350. The suit was dismissed on the merits by the Superior Court of Suffolk County, Massachusetts, and appealed to the Supreme Judicial Court of Massachusetts, which on December 4, 1942, decided that the case had become moot.
Applications for the allowance of an appeal to this Court, presented within three months after December 4th, were denied by the Chief Justice of the Superior Court of Massachusetts and by an Associate Justice of this Court. An application presented to another Associate Justice on March 6th was allowed. But this last application was not timely if the time to take an appeal ran from December 4th.
Matton Steamboat Co.
v.
Murphy,
Massachusetts local practice regards the decree entered by the Superior Court on the rescript, rather than the order of the Supreme Judicial Court contained in the rescript, as the “final decree” in the case. See
Boston
v.
Santosuosso,
Dismissed.