This action was commenced January 29, 1904, under Act March 3, 1887, c. 359, 24 Stat. 505 (U. S. Comp. St. 1904, p. 752). This act gives the Circuit Court of the United States concurrent jurisdiction with the Court of Claims of suits against the United States where the amount of the claim exceeds $1,000 and does not exceed $10,000. The action is based upon the claim of an implied contract for compensation for the value of a stream of water diverted from petitioner’s premises by the United States in the improvement of Oakland Harbor.
The act of Congress approved March 3, 1873 (17 Stat. 566, c. 234), contained a provision for the survey and examination of San Antonio creek or estuary by the engineers of the army, under the direction of the Secretary of War, with a view to the improvement of Oakland Harbor. Under this authority the Board of Engineers made an examination and survey and reported a plan of improvement, which included the excavation of a tidal canal in Alameda county from the upper end of the estuary of San Antonio to San Leandro Bay, a distance of about 8,400 feet. The object of the canal was to carry a tidal current from San Leandro Bay into the estuary of San Antonio, and thus increase the tidal prism of the Oakland Harbor. The plan was approved, by the proper authority, and the United States proceeded to condemn and acquire the land on the line of the proposed tidal canal. The improvement included also a subsidiary canal along a part of the northern or upper side of the main canal. The purpose of the subsidiary canal was to divert flood water that would otherwise empty into the canal from Sausal creek, a small unnavigable stream coming down from the hills to the north of, and from a direction at a right angle to, the canal, but which at the line of the canal turns to the east and empties into Brickyard slough, an arm of San Leandro Bay, navigable waters in which the tide ebbs and flows. The creek has about four or five square miles of watershed, and is a winter stream, carrying the rainfall in the immediate vicinity of its origin and course for a period of seven months in the year. During the remaining five months the bed of the creek is dry.
The work on the main canal was commenced by the United States in January, 1891, and was completed in March, 1903. The subsidiary canal was commenced in March, 1900, and finished in October, 1900. The main canal is a channel of 400 feet in width at the top and 300 feet at the bottom. It is 8 feet deep at low water and 14 feet deep at high water. The petitioner in this case is the owner of a tract of
The petitioner claims that by the diversion of Sausal creek she has been deprived of the use and benefit of 1,500 tons of gravel for each of the three years preceding the commencement of this action, making a total of 4,500 tons of gravel, of the value of $6,750; that but for the diversion mentioned the creek would have continued to deposit at least the same amount of gravel upon petitioner’s land for all time, and that such deposit -would, in the ordinary course of nature, have increased each and every year, and petitioner would have derived an annual benefit and revenue therefrom of $2,250; that but for the diversion mentioned the creek would have brought down and deposited upon the lands of petitioner, adjacent to and through which said creek ran, large quantities of silt and alluvial earth; which would have been of great benefit to the lands of petitioner, as it would have enriched the same and made.them more fertile, and the overflow of said water would have been of great benefit to said lands, for the reason that it was a natural irrigation, which caused the same to produce green feed during.the summer months' for petitioner’s horses, cattle, and other domestic animals; that the value of said deposits upon said lands is at least $5,000; that the value of the water of said Sausal creek so taken and appropriated by the United States is the sum of $5,000. Petitioner claims that the detriment to her property caused by the diversion of Sausal creek, as alleged, amounts to the sum of $24,000; but petitioner waives the excess over $10,000, and claims
In Gibson v. United States,
“The damage of which Mrs. Gibson complained was not the result of the taking of any part of her property, whether upland or submerged, or a direct invasion thereof, but the incidental consequences of the lawful and proper exercise of the governmental power.”
The judgment of the Court of Claims that the petitioner was not entitled to recover, and dismissing the petition, was affirmed.
In Scranton v. Wheeler,
In Mills v. United States (D. C.)
In United States v. Lynah,
The present case is distinguished from .the foregoing cases in the fact that Sausal creek is not a navigable stream and the construction of the canal by the government was not for the benefit or improvement of that stream, but for the improvement of navigable waters in another and different locality,/and it is claimed by the petitioner that the injury she suffered was the taking of her private property (the waters of Sausal creek) for a public use, and that for the taking she is entitled to just compensation. This distinction between acts of the government damaging private property on a navigable stream in the work of improving its navigability and the taking of private property connected with an unnavigable stream for public use in improving navigable waters elsewhere was recognized when the court disposed of the demurrer to the complaint, and is now referred to in considering the case on its merits, for the purpose of making clear the precise character and scope of petitioner’s cause of action.
The government has diverted the waters of Sausal creek at the point where it enters the subsidiary canal, and in effect has taken and appropriated the stream below that point, and the petitioner has been deprived of its flow adjacent to and upon her premises. This is a taking, within the constitutional provision. But the question remains to be determined, what was the value of the waters of this creek at the time of their diversion, for which the petitioner is entitled to just compensation ?
The petitioner’s cause of action is based upon the claim of riparian ownership and appropriation of the waters of Sausal. creek. This
Testimony on behalf of the United States was that this overflow water was of no benefit to petitioner’s land. The weight of evidence was that this flood water came at the wrong season of the year. It came in the winter, when it had no value for irrigation, and did not come in the summer, when it would have been of value. When the water did come, the land needed drainage, and not irrigation; furthermore, that petitioner’s land has suffered no depreciation in value by reason of the diversion of the creek. From this evidence I am unable to find that the water of Sausal creek had any value to the petitioner at the time of the diversion, either for irrigation or for domestic purposes, or for the enrichment of the soil by deposit of silt. With respect to that phase of petitioner’s cause of action there must, therefore, be a finding in favor of the defendant.
The next element in petitioner’s cause of action is the habit of the water of Sausal creek to carry and deposit gravel during the rainy season in the bed of the creek adjacent to petitioner’s premises. This gravel appears to have been washed from the banks of the creek; but, as the land along the creek has become occupied by residences, the banks have been bulkheaded at a number of places, and the evidence shows that at the time of the construction of the canal this wash of
The riparian owner has no vested right in future accretions. Western Pac. Ry. Co. v. Southern Pac. Co.,
“The lawful appropriation of the land by the Rock Island Railroad Company cut off accretions to defendants’ land and established a line beyond which no right by accretions can be acquired.”
In Lyons v. United States,
“This plaintiff asks damages because the government has limited the effects of a freshet; and this on the ground that, while freshets are generally injurious and their prevention a benelit, in his case the reverse is true, as they cover his land with sand washed away from some one else's property higher up on the stream, and from the sale of this sand he derives a profit. * * * The projected Rock Creek Park and Zoological Gardens are to be laid out at no great distance above plaintiff’s property. It is not impirobable that in the course of the preparation of these improvements for public use the stream may be walled in or otherwise confined more strictly to its bed, and that the banks will be so protected as, if possible, to prevent washing. Would a riparian owner below find in such work a valid ground for claiming damages because deposits of sand were no longer made upon his land in time of freshet? So the deepening of the stream below plaintiff by a neighbor desirous of protecting his own land would tend to quicken the current above and carry the sand by plaintiff while held in suspension. There are many elements of uncertainty in a claim of this description. Its value depends upon the- accidents*371 of nature, upon the legitimate and proper use of the stream both above and below plaintiff, and the natural use of their land by riparian owners above him, and we are of opinion that the use by the government of the stream does not injure plaintiff in any tangible property right.”
It follows from these authorities that the riparian owner, having no-vested right in future accretions, cannot maintain an action for damages against one who lawfully obstructs or diverts the stream carrying such accretions, so that such deposits are no longer formed adjacent to her premises.
It is contended, however, on behalf of petitioner, that she is not seeking compensation for the loss of gravel brought down by Sausal creek, but for the value of the stream for which use this is an element,
1 that the habit of the stream to bring gravel to her premises was evidence of such value. But this habit, as we have seen, was not fixed' or stable. It depended upon conditions that were so uncertain that no value can be attached to the habit.
In my opinion Sausal creek had no value in this respect at the time of the diversion, either present or prospective, for which petitioner-is entitled to recover compensation. Bet the findings be prepared in accordance with this opinion, and a judgment entered accordingly.