191 A.D. 396 | N.Y. App. Div. | 1920
The order recites that the motion was denied for laches and on the ground that the defendant failed to satisfy the court that the additional defense and counterclaim sought to be pleaded are meritorious. The action was commenced on the 23d of August, 1918, and issue was joined by the service of an answer on the thirtieth of September of that year. The action is brought to recover damages for breaches of two contracts. The breaches alleged are that the defendant failed to deliver to the plaintiff all of the goods he agreed to deliver. By the original answer, the defendant admitted that he made the contracts with the plaintiff and he pleaded modifications thereof. The proposed answer with respect to the defenses is wholly inconsistent with the original, for thereby defendant proposes to plead that the contracts were not his and that he was acting as agent for a disclosed principal. The order, therefore, in so far as it denies the motion to allow the service of an amended answer with respect to the new defenses was proper; but the defendant should be permitted to plead the proposed counterclaim, which is for the difference between the original contract purchase price of the goods delivered to the plaintiff and the alleged purchase price thereof under a modification of the contracts, which amount, it is alleged, plaintiff agreed to pay to L. F. Dommerich & Co., the guarantors of the accounts. It is alleged that that claim was
The order is, therefore, modified by allowing the defendant to serve an amended answer consisting of the provisions of the original answer with the counterclaim added thereto as aforesaid upon payment of ten dollars costs of the motion, the date of issue to remain the same and without prejudice to the position of the cause on the calendar, and, as so modified, the order is affirmed, without costs.
Clarke, P. J., Dowling and Merrell, JJ., concur.
Order modified as directed in opinion and, as so modified, affirmed, without costs. Settle order on notice.