97 P. 1079 | Or. | 1908
Opinion by
Several important questions have been raised and presented to this court, but it will be necessary to refer to and consider but one of them, viz. whether the claim for a lien was filed within the time required by the statute.
After the substantial completion of his contract on or about August 13, plaintiff should not be permitted, by unreasonable delay in the performance of trfling matters, which could and should have been done at an earlier time, postpone the date from which the time allowed by the statute begins to run: Cooley v. Holcolmb, 68 Conn. 35 (35 Atl. 765) ; Cole v. Uhl, 46 Conn. 296; Dayton v. Minn. R. & I. Co. 63 Minn. 48 (65 N. W. 133) ; Burleigh Bld. Co. v. Building Co. 13 Colo. App. 455 (59 Pac. 83). If, when inspected August 13, the work was
At the argument a theory was advanced by plaintiff’s counsel to the effect that as defendants had averred in their answer that the work was to be done to the satisfaction of the plumbing inspector of the City of Portland, the contract could not be considered as completed until such officer had issued his certificate to that effect, which was not done until December 2, and that plaintiff’s time to file a lien would run from that date, but by the alleged contract the inspector was arbiter, at most, only of the quality of the work, and any act of his in inspecting or delaying the issuance of his certificate would not extend the time allowed by law to the plaintiff after the completion of the contract in which to file his lien: Beatty v. Mills, 113 Cal. 312 (45 Pac. 468).
From these considerations, it follows that plaintiff’s alleged lien was not filed within time, and is therefore invalid, and the decree should be reversed and the complaint dismissed. Reversed.