-Plaintiff seeks damages for alleged breach of a contract for construction of the second stage of the six-stage Fishtrap Reservoir Project on the Big Sandy River in Pike County, Kentucky. Completion of plaintiffs portion was set for June 29, 1968, performance to occur during four construction seasons. The first-stage contract awarded to another was for building a tunnel through an adjoining hillside, foundations of the intake structure to the tunnel allowing controlled flow of water to bypass the dam, and the tunnel outlet. The first-stage work was scheduled to be completed prior to July 1, 1965, and it was intended that the river should then be diverted by a cofferdam to pass through the tunnel while the dam was being built across the original channel. Plaintiffs contract related to the construction of the intake structure with hydraulically operated slide