Lead Opinion
OPINION
This is a suit under the Texas Deceptive Trade Practices Act wherein appellees sued appellant for defects in the home appellees purchased from appellant. The jury returned the verdict in favor of appellees. Damages were trebled pursuant to the 1977 version of this law. We affirm.
The facts of this case are essentially undisputed. On or about August 22, 1979, appellees and appellant executed an Earnest Money Contract for the purchase of a home which at that time was under construction. At the time of the execution of the Earnest Money Contract, the structure and exterior of the home were complete. The interior finishing was in progress. After the Earnest Money Contract was executed, the construction of the home continued. Appellees prepared a list of items needing correction or completion, but the list did not include the defects complained of in this ease. Several inspections were made by the appellees. The listed corrections were not complete at the time of closing, October 26, 1979. On that date, appellees and appellant agreed to place $1,500.00 of the purchase price into an escrow account to pay for the remaining items to be corrected. Subsequent to the closing of the house, work continued on the items needing repair. Later, the appellees discovered several additional defects (the fireplace, roof, rearyard drainage and the improper placement of a rear wall basep-late) which caused leaks, water pooling and water damage to the house.
This lawsuit was filed in 1982. While this suit was pending, the parties entered into a settlement and compromise agreement during May of 1983. Under the terms of this agreement, appellant was to pay the expenses of litigation and to deposit a letter of credit in the amount $30,-000.00 to secure the payment of the repairs. The letter of credit was valid for a period of ninety days from the date of issue. An architect was named to act as an arbitrator and to determine how the defects were to be repaired. That architect refused to serve. A lengthy discussion then ensued between the attorneys regarding the selection of an alternate architect. Apparently, there were communication difficulties between the parties and the architect who was ultimately selected. By the time an agreement was reached, the letter of credit had expired. Despite a number of requests, appellant did not renew the letter of credit, and no work could proceed.
The case was set for trial in February of 1984. At that time, appellant amended his pleadings. In those pleadings, which were the same pleadings upon which trial was had in this cause, the defense of compromise and settlement was not raised.
The case was again set for trial on May 21, 1984, and, at that time, the appellant orally urged the court to abate or to bar the case from going to trial on the grounds that the compromise and settlement agreement barred a trial. This plea in abatement was denied by the trial court, and the case went to trial before a jury. After appellees rested, appellant submitted a trial amendment raising the defense of compromise and settlement which was denied by the trial court. The jury returned a verdict in favor of appellees on the issues of im
By his first through third points of error, appellant complains of the trial court’s action in refusing to permit appellant to raise the compromise and settlement agreement as a bar to the lawsuit by plea in abatement. We will assume without deciding that the settlement complied with TEX.R.CIV.P. 11 and is binding upon the parties. See Burnaman v. Heaton,
Appellant, by his fourth and fifth points of error, complains of the trial court’s action in refusing to allow the defendant leave to file his first trial amendment alleging the affirmative defense of compromise and settlement because there was no showing of surprise or prejudice to the plaintiff and in refusing to allow appellant to put on evidence of the compromise and settlement agreement during the trial.
After appellees had rested, appellant filed a motion for leave to file a trial amendment. Trial amendments are governed by TEX.R.CIV.P. 66, which reads in pertinent part:
[I]f during the trial, any defect, fault or omission in a pleading, either of form or substance, is called to the attention of the court, the court may allow the pleadings to be amended and shall do so freely when the presentation of the merits of the action will be subserved thereby and the objecting party fails to satisfy the court that the allowance of such an amendment would prejudice him in maintaining his action or defense upon the merits. The court may grant a postponement to enable the objecting party to meet such evidence.
A trial amendment may be filed only by leave of court, and the request for leave to file is addressed to the trial court’s discretion; the trial court’s ruling is reversible only by a showing of abuse of discretion. Victory v. State,
In the absence of this trial amendment, there is no pleading upon which to base the admission of the evidence regarding the compromise and settlement agreement. It is not proper to admit evidence unless such evidence is addressed to or bears upon some issue raised by the pleading. Erisman v. Thompson,
Appellant, by his sixth and seventh points of error, complains that the trial court erred in ruling that the pre-1979 amendments to the Texas Deceptive Trade Practices Act applied and trebling the damages found by the jury as a matter of law.
Appellant argues that appellees tried the case on the theory that appellant breached the implied warranty of good workmanship. Appellant further argues “[ujntil the construction of the house was completed, there could be no such implied warranty in favor of the Whites because Cocke was at liberty to change, repair, replace, redesign and complete the construction as he chose so that, when the closing took place and the possession of the house was given over to the Whites, he would be prepared to have the Whites (and himself) rely upon such implied warranty so that any latent defects discovered subsequent to the closing and taking of the possession by the Whites would, if appropriate, constitute breaches of such implied warranty.” The gravaman of appellant’s argument is that the warranty of habitability can only arise at the time of closing and transfer of possession. We disagree.
The applicable version of the DTPA is the one in effect on the date of the acts which give rise to the cause of the action under the DTPA. McAllen State Bank v. Linbeck Construction Corp.,
This case was brought under the implied warranty that a dwelling should be constructed in a good and workmanlike manner. This warranty was added to the common law of Texas in Humber v. Morton,
It is clear from the record that the defects complained of, that is, the roof, the fireplace, the baseplate of the rear wall and
Appellant, by his eighth point of error, complained that the trial court erred in failing to submit definitions of “warranty,” “implied warranty,” the “implied warranty of workmanlike manner and suitable for habitation,” “mitigation” and “knowingly” in its charge to the jury. We have examined the charge to the jury, and we find that these terms were not used in the issues submitted to the jury, and, therefore, the trial court properly excluded any definition of these terms. Brandon v. Cooper,
Appellant, by his ninth point of error, complains that the trial court erred in the submission of Special Issue No. 1 of its charge because such special issue failed to instruct or define “implied warranty of construction in a good workmanlike manner and suitable for human habitation” in connection with Special Issue No. 1, and such issue submitted to the jury failed to include the term “suitable for human habitation.” As noted above, in Point of Error No. 8, the term “implied warranty of construction and a good workmanlike manner and suitable for human habitation” was not used in the charge to the jury. Rather, Special Issue No. 1 read:
Do you find from a preponderance of the evidence that the house which is the subject of this suit was constructed in a good and workmanlike manner?
We therefore find that no definition need by submitted.
Appellant, by his tenth point of error, complains that the trial court erred in its submission of Special Issue No. 4 of its charge because it failed to include an instruction on mitigation of damages. We find that the trial court properly excluded an instruction on mitigation of damages because the defendant claiming mitigation of damages has the burden not only to prove lack of diligence on the part of the plaintiff but also to prove the amount by which the damages were increased by such failure to mitigate damages. R.A. Corbett Transport, Inc. v. Oden,
The judgment of the trial court is affirmed.
Notes
. The sale occurs at the time the contract for sale (Earnest Money Contract) is entered into. Lefevere v. Sears,
. This case is distinguishable from the recent case decided by this Court, McAllen State Bank v. Linbeck Construction Corp., No. 84-085,
. It should be pointed out that this term, “constructed in a good and workmanlike manner,” is different from the term addressed in the eighth point of error, "implied warranty of workmanlike manner and suitable for human habitation,” in that the latter addresses the warranty and the former only requires that the jury apply the standard provided by the expert witnesses.
Lead Opinion
OPINION ON APPELLANT’S MOTION FOR REHEARING
In his motion for rehearing, appellant complains that the pre-1979 Amendments to the Texas Deceptive Trade Practices Act do not apply and therefore it was error to treble the damages in this case. Appellee did not discover the defects in the house until after the effective date of the 1979 amendments.
Although appellant correctly states the rule derived from Jim Walter Homes, Inc. v. Castillo,
The case at hand does not involve the statute of limitations, but rather which version of the DTPA controls. Therefore, it is necessary to take notice of the savings clause included in the 1979 amendment which provides:
“This act shall be applied prospectively only. Nothing in this Act affects either procedurally or substantively a cause of action that arose either in whole or in part prior to the effective date of this Act.” (emphasis added).
Act of June 13, 1979, 66th Leg., p. 1327, ch. 603, Sec. 9, Tex.Gen.Laws 1332, eff. August 27, 1979. McAllen State Bank v. Linbeck Construction Corp.,
The implied warranty arises from the sale, which occurred on August 22, 1979. Humber v. Morton,
Appellant’s motion for rehearing is overruled.
