34 Wash. 238 | Wash. | 1904
This action was commenced in the superior court of King county by C. D. Cochran and A. J. Webb, as plaintiffs, against-J. F. Yoho and Mary Yoho, his wife, as defendants. Plaintiffs allege in their amended complaint that, on or about the 14th day of December, 1900, they and one C. L. Huggins entered into a written' contract with J. K. Yoho, for the construction of four certain two-story frame buildings upon lot 4 in block 54 of the Second Addition to the city of Seattle. This contract is referred to as an exhibit, and is as follows:
“Seattle, Wash., Dec. 17th, 1901.
“We, the parties of the first part, C. L. Huggins, A. J. Webb and C. D. Cochran, and J. P. Yoho of the second part, do enter into a contract for the construction of four, four part tenement houses to be erected on lot 4, block 54, Sarah A. Bell’s 2nd addition to Seattle, Wash. The parties of the first part agree to furnish all material and labor for construction and completion of said buildings according to plans and specifications for the sum of forty four hundred dollars ($4400). Said buildings are to be commenced at once and completed as soon as possible. The party of the second part agrees to furnish a sufficient amount of money for the parties of the first part to get the material for said buildings, but at no time to pay any in advance. All bills to be receipted and turned into party of second part before final payment” [Signed, etc.]
The complaint further alleges that, immediately after the execution of this contract, O. L. Huggins abandoned said contract, and so notified these plaintiffs (Cochran and Webb), verbally, without giving any reasons therefor. That on the 17th day of December, 1900, these plaintiffs commenced to perform labor and furnish materials to be used in the construction of such buildings, the contract price
*‘(2) That in accordance with the term's of said contract the said Cochran, Webb, and Huggins were to- construct the said buildings in accordance with certain plans and specifications furnished, and that it was also provided that the lumber furnished was to be of good quality, and that the said houses were to be completed as soon as pos*241 sible. (3) That contrary to the terms of said agreement the said lumber furnished was of an inferior quality and was not suitable for the use to which it was put, the buildings were not and are not constructed in accordance with the plans and specifications provided, and the work was performed in a careless, indifferent, and unworkmanlike manner. (4) That contrary to the terms of said contract after partially constructing said buildings and before the completion thereof and while the same were in an exposed and unfinished condition, these plaintiffs wilfully abandoned said labor, on or about March 9th, 1901, and then refused, and at subsequent times when notified by the said J. F. Yoho to complete the said buildings, refused to further perform labor or to further furnish material. (5) That up to and including the 9th day of March, 1901, when these plaintiffs abandoned said contract as above alleged, the said J. F. Yoho had paid these plaintiffs for use in the said houses the sum of four thousand twenty two dollars and twelve cents ($4022.12). (6) That the defendant J. F. Yoho was compelled to and did actually expend the further sum of five hundred sixty six dollars sixty nine cents ($566.69) for the completion of said houses in accordance with the terms of said contract.”
The defendants further allege damages in the sum of $1,500, and ask judgment against plaintiffs for $1,688.73 on their counterclaim. Plaintiffs in their reply deny each and all the material allegations of new matter contained in the answer.
The cause was tried to the court without a jury on the 6th day of January, 1902, and thereupon the following findings of fact, among others, were made by the trial court:
“(5) That on or about the 6th day of March, 1901, the defendant J. F. Yoho forcibly ejected the plaintiffs from said premises, and refused to allow them to further perform said contract, or to carry the same out or complete the same, and that thereupon the plaintiffs ceased to perform any further labor, or to furnish any further materials,*242 upon said houses; that all of said labor and materials under said contract were performed and furnished between the 17th day of December, 1900, and the 9th day of March, 1901. (6) That at the time when said defendant J. F. Yoho refused to allow the plaintiffs to further perform said contract, one hundred and fifty dollars would have completed said buildings, including all necessary material therefor. (7) That during the construction of said buildings, it had been agreed between the plaintiffs and the defendant, J. F. Yoho, that four chimneys might be omitted from said houses, for which the plaintiffs agreed to allow the defendants their reasonable cost. (8) That the reasonable costs of said chimneys would have amounted to eighty dollars. (9) That the labor performed and materials furnished, as aforesaid, to be used in and which were used in the construction of said buildings, were furnished to the said J. F. Yoho in accordance with the terms and conditions of said contract, except as in paragraph seven hereof stated.....(14) And the court further finds that it was agreed upon the trial of this cause between the plaintiffs and defendants and stipulated therein that, in case said lien was foreclosed and a decree rendered in favor of the plaintiffs, $150 was a reasonable attorney’s fee to be allowed the plaintiff in this cause.”
The court thereupon stated the following conclusions of law:
“(1)’ That the defendants are indebted to the plaintiffs in the sum of $482.10, together with interest thereon from the 9th day of March, 1901, at the legal rate, aggregating $510.20, together with an attorney’s fee of $150, and their costs herein, and that the plaintiffs are entitled to a judgment against the defendants for said sums. (2) That the lien, mentioned and described in the findings of fact herein, is a good, first, and valid and subsisting lien upon the premises therein described, and that the plaintiffs are entitled to have said lien foreclosed, and the premises therein described sold by the sheriff of this county, and that the proceeds of such sale- be applied in payment of such judgment, attorney’s fees, interest, and costs, together with the costs and increased costs of such sale.”
Appellants assign errors as follows: (1) That the trial court erred in not sustaining the demurrer to the amended complaint; (2) in making the findings of fact and conclusions of law to which appellants excepted as above noted; (3) in not making certain findings and conclusions of law proposed by appellants.
The main contention of appellants, in support of their demurrer to the above complaint, is based upon the proposition that it appears from such pleading that the original contract for the construction of these buildings was entered into between respondents and one Huggins, as parties of the first part, and J. D. Yoho, appellant, as party of the second part, and that said Huggins withdrew from' the work, and that there is no allegation in the complaint of knowledge or consent to such withdrawal on the part of the owner, J. D. Yoho. Respondents, in their amended complaint, among other things, allege that, immediately after the execution of the contract, the said O. L. Huggins abandoned said contract, that respondents commenced to perform labor and furnish materials for the erection of these structures from December 17, 1900, and continued in so doing up to and including March 9, 1901, and before that time had completed two of said buildings and delivered the same to appellant, Yoho, who accepted the same. Dor the purposes of this demurrer, these allegations must be taken as true. Giving these averments a reasonable and liberal
Appellants contend there was no evidence to justify the finding of the trial court that “defendant Yoho forcibly ejected plaintiffs from said premises.” Respondent Cochran testified that, “on Monday, about the 4th or 5th of March, 1901, when we arrived at the premises, Yoho hadn’t got there, we found our tools were locked up and we waited a few minutes for Yoho-. I asked him if he wanted us to go to work on the coal shed; he said, ‘Ho,’ he would not let us go to work at all; he said he would not let us have anything to do with it, he would not have anything to do with us any more, especially me; said he would not allow me around there; and we came around to see Mr. Bronson, and Mr. Bronson was not in his office, and when we came back he had our tools there on the back porch, and would not let us in at all.” Respondent Webb substanti
It further appears from Yoho’s evidence that, at and prior to the time respondents quit working on these buildings, he was very much dissatisfied with the quality of the work thereon, and that disagreements between him and Cochran were frequent; that, within a day or two after the alleged ejectment of respondents, appellant Yoho served a written notice upon Webb, Cochran, and Huggins that, unless they proceeded at once with the construction of these four buildings, he would consider that they had abandoned the work, and look to them for whatever damages he might sustain thereby. Respondents admit the receipt and service of this notice upon them.
Treating the above finding as a verity for the purposes of this controversy, we are constrained to hold, as a matter of law, that appellants, by wrongfully stopping the work on these buildings, rendered themselves liable to respondents in damages. We are of the opinion that the fact of appellants having given notice to respondents and Huggins to proceed with the work does not affect respondents’ right to recover in the case at bar; that the latter, by the acts of J. P. Yoho, had a right to treat the contract as rescinded, and they could not legally be required to go back to work on those structures, under the original contract; that J. P. Yoho, being the party at fault, under the findings of the trial court, in causing respondents to quit work, must bear the consequences of his own acts. “Where one of the parties to a contract, either before the time for performance or in the course of performance, makes performance or further performance by him impossible, the other party is discharged and may sue at once for the breach.” 9 Cyc. 639, and authorities cited.
It is admitted that, during the progress of the above work, appellants advanced $3,687.92 under the contract. The trial court found that, when respondents quit work, $150 would have completed said buildings, including all necessary materials therefor. We think that, on the respondents’ evidence, appellants should have been allowed an additional credit of $25, making the sum total of $175 to be deducted from the contract price for labor and material necessary to complete the buildings. Under the testimony the cost of the erection of eight chimneys should have been deducted from the contract price for the completion of the buildings. The trial court allowed
Do costs shall be taxed in favor of either respondents or appellants on this appeal. This cause is therefore remandéd with directions to enter judgment in conformity with this opinion.