39 Ga. App. 637 | Ga. Ct. App. | 1929
Rehearing
ON MOTION EOR REHEARING.
It is true (as pointed out in the motion for a rehearing) that in Town of Decatur v. Jaudon, 136 Ga. 854 (supra), there was no alteration of the plans and specifications submitted by Jaúdon and accepted by the Town of Decatur, and that in the instant case the original plans and specifications submitted by Bond, the contractor, and accepted by Cobb, the owner of the stores to be built by Bond, were so changed as to increase the cost of the buildings. In our opinion, however, that distinction between the facts of the two cases is immaterial for the following reason: The contract entered into between Bond and Cobb provided that Bond would furnish plans and specifications for the erection of two stores, and would build them; that the amount to be paid by Cobb to Bond was four hundred dollars, to be paid as follows: “Fifty dollars to be paid for the plans and specifications upon their delivery, and the balance to be paid as the work progresses in weekly amounts of twenty-five dollars per week until two hundred dollars has been paid, at which point the payments shall cease until the stores are fully completed and an inventory of total cost of same be made; and if such cost is found to exceed five thousand dollars, then the balance remaining due to the contractor
Rehearing denied.
Lead Opinion
The petition as amended was subject to general demurrer, and the trial judge of the municipal court of Atlanta properly so held. The reversal of that ruling by the appellate division of the court was error; and the judge of the superior court erred in sustaining the decision of the appellate division and in overruling the defendant’s petition for certiorari. See, in this connection, Town of Decatur v. Jaudon, 136 Ga. 854 (72 S. E. 351).
Judgment reversed.