This сase presents the question whether, in a breach of contract action, a circuit court has subject matter jurisdiction to review the validity of agency rules that the parties have incorporated as contract terms. The Court of Appeals assumed without discussion that the circuit court has such jurisdiction.
Coats v. ODOT,
Plaintiff is a contractor who constructs and repairs public highways in Oregon. On March 21,1997, plaintiff contracted with the Oregon Department of Transportation (ODOT) to pave a portion of State Highway 20 in Deschutes County (the highway project). The pаrties’ contract was subject to Oregon’s prevailing wage statute, ORS 279.350(1), which provides:
“The hourly rate of wage to be paid by any contractor or subcontractor to workers upon all public works shall be not less than the prevailing rate of wage for an hour’s work in the same trade or occupation in the locality where such labor is performed. * * *”
The parties do not dispute that the highway project was a “public work” 1 or that ORS 279.350(1) applied here.
The Oregon Burеau of Labor and Industries (BOLI) had promulgated administrative rules construing ORS 279.350(1) to apply to all workers at the “site of work.” 2 See OAR 839-016-0004(19). 3 Plaintiff and ODOT agreed to incorporate those rules as terms of their contract. 4 As explained below, central to the parties’ contract dispute in this case are two subsections of a BOLI rule that identified the circumstances under which rock quarries, or so-called “borrow pits,” would be considered part of the “site of wоrk.” 5 First, subsection (b) of OAR 839-016-0004(19) provided:
“* * * [B]orrow pits * * * are part of the site of work provided they are dedicated exclusively, or nearly so, to the performance of the contract or project, and are so located in proximity to the actual construction location that it would be reasonable to include them. Such facilities which are established by a supplier of materials for the project after the opening of bids shall be deemed to be dedicated exclusively to the performance of the contract or project.”
(Emphasis added.) Subsection (c) of the same rule provided the following exception:
“* * * [B]orrow pits * * * which are established by a supplier of materials for the project before opening of bids and not on the project site, are not included in the site of work. Such permanent, previously established facilities are not part of the site of work, even wherе the operations for a period of time may be dedicated exclusively, or nearly so, to the performance of a contract or project.”
(Emphasis added.)
In 1995, plaintiff had obtained a permit from the Oregon Department of Geology and Mineral Industries
(DOGMI) to mine bentonite on a specified portion of real property that he owned. That property is about 10 miles from the site of the highway project. Two years later, after ODOT had opened bids on the contract for the highway project,
Plaintiff proceeded with work on the highway project, using his newly established hard rock quarry to supply the aggregate required for the project. During construction, plaintiff did not pay prevailing wages to quarry workers who produced rock for the project or to truck drivers who transported rock from the quarry to the construction site.
On May 9, 1997, BOLI sent plaintiff a letter notifying him that, if he failed to pay prevailing wages to the workers producing and hauling rock for the highway project, the agency would consider placing him on a “List of Ineligibles” that would bar him from bidding on public works projects in the future. 6 BOLI based that actiоn on its conclusion under OAR 839-016-0004(19)(b) that plaintiff had established his hard rock quarry after the opening of bids on the highway project and, therefore, that the quarry was “deemed to be dedicated exclusively to the performance of the contract” and part of the “site of work” subject to the prevailing wage requirements of ORS 279.350(1). 7
PROCEEDINGS BELOW
Upon receipt of BOLI’s letter, plaintiff filed a complaint against the state, by and through ODOT and BOLI, seeking a declaratory judgment that BOLI’s rules requiring him to pay prevailing wages to the quarry workers and truck drivers were, among other things, invalid. More specifically, plaintiff asserted that BOLI’s rules incorrectly interpreted ORS 279.350(1), which requires that he pay prevailing wages to only those workers “upon [the] public work[ ].” In plaintiff’s view, the word “upon,” as used in that statute, connotes direct geographic proximity to the work site, and BOLI had exceeded its authority by promulgating rules that construed ORS 279.350(1) to cover workers producing and hauling rock from a borrow pit located 10 miles from the highway project. Plaintiff also sought a restraining order to enjoin BOLI from “following through on its threat” to prevent plaintiff from bidding on future public works projects.
The state moved to dismiss the complaint for lack of subject matter jurisdiction, citing
Alto v. State Fire Marshal,
In his summary judgment motion, plaintiff asserted that ODOT could not bind him to contract terms that consisted of invalid BOLI rules. In the alternative, plaintiff argued that he had complied with the contract because BOLI’s rules, properly interpreted, excludеd the workers at issue from the prevailing wage requirement. In that regard, plaintiff argued that, contrary to BOLI’s conclusions, he had not established his borrow pit after the opening of bids on the highway project, for purposes of OAR 839-016-0004(19)(b). As noted, under OAR 839-016-0004(19)(c), borrow pits that were “previously
The state responded that BOLI’s rules were valid and that, even if they were not, plaintiff was bound by them because they were terms of his contract with ODOT. Furthеr, the state argued that plaintiff was well aware of BOLFs rules and the manner in which that agency interpreted them when he signed the contract and that plaintiff, after signing the contract, could not challenge the facial validity of BOLFs rules, or that agency’s interpretation that the rules applied to the workers involved here, in a claim for breach of contract.
The circuit court granted plaintiffs motion for summary judgment and denied the state’s motiоn. That court declined to address plaintiffs rule challenge, accepting instead plaintiffs alternative argument that the hard rock quarry was part of a “permanent, previously established [facility]” under OAR 839-016-0004(19)(c) and, therefore, that it was not included as part of the “site of work.” Accordingly, the circuit court held that plaintiff had complied with the terms of his contract with ODOT and that he was not required to pay his quarry workers or truck drivers prevailing wages. 8
The state appealed. The Court of Appeals affirmed the judgment of the circuit court, although that court decided instead to address plaintiffs rule challenge. Applying principles of administrative law, the Court of Appeals agreed with plaintiffs assertion that the phrase “upon all public works,” as used in ORS 279.350(1), requires contractors to pay prevailing wages to only those who are working in “close proximity” to the actual construction site.
Coats,
DISCUSSION
On review, the parties continue their disagreement over the validity of BOLI’s rules, and the state argues that the Court of Appeals erred in concluding that BOLI had applied its rules improperly. However, after reviewing the record and procedural history of this case, we conclude that the case presents problems of subject matter jurisdiction that limit our consideration of the issues that the parties have argued and that the Court of Appeals decided. When a question of subject matter jurisdiction presents itself at any stage of a proceeding, whether on the motion of a party or on the court’s own motion, it is the court’s duty to address it.
See City of Lake Oswego v. Mylander,
As noted above, although plaintiff named ODOT in his amended complaint for breach of contract and asserted that he had complied with the contract’s prevailing wage requirements, his complaint also challenged the validity of BOLI’s rules interpreting the prevailing
Statutes, and decisions of this court, identify several ways in which a plaintiff may seek judicial review of an administrative rule. The Administrative Procedure Act (APA), ORS 183.310 to 183.500, provides that the validity of an agency rulе is subject to judicial review either “upon a petition by any person to the Court of Appeals,” ORS 183.400(1), or by a court “upon review of an order in any manner provided by law or pursuant to ORS 183.480 or upon enforcement of such rule or order in the manner provided by law,” ORS 183.400(2).
See Hay,
This court also has recognized that a circuit court has jurisdiction to consider a challenge to an administrative rule when the rule’s validity is “at issue” in a “separate civil action” properly before the circuit court.
Hay,
The plaintiffs in
Hay
were owners of a beachfrоnt hotel who filed nuisance and trespass claims in circuit court against ODOT for authorizing parking in front of their hotel.
Plaintiff argued in circuit court that the
Hay
exceрtion applies here because he has placed the validity of BOLFs rules “at issue” in a separate civil action for breach of contract. In other words, plaintiff claimed that judicial review of the validity of BOLFs rules is necessary to resolve whether plaintiff or ODOT breached the parties’ contract. Plaintiff, however, is mistaken. He seeks to challenge the validity of state agency rules that, earlier, he had agreed to as contract terms.
10
Even if plaintiff could not be forced to comply with those rules by operation of law, he nonetheless could bind himself to do so by contract, as he did here.
See Vulcan Arbor Hill Corp. v.
Reich,
Because the validity of BOLI’s rules is not relevant to resolving whether ODOT is liable for breach of contract—
i.e.,
because the validity of the rules is not “at issue” — plaintiffs rule challenge does not satisfy the exception to the jurisdictional requirements of ORS 183.400 that this court identified in
Hay,
The circuit court did not, however, lack jurisdiction to hear other aspects of plaintiffs breach of contract action. The issue remains whether the circuit court correctly concluded, with respect to plaintiffs alternative claim, that the exception to prevailing wage coverage contained in OAR 839-016-0004(19)(c) applied to the quarry workers and truck drivers at issue as a matter of contract. As we рreviously noted, the text of that rule provided:
“* * * [B]orrow pits * * * which are established by a supplier of materials for the project before opening of bids and not on the project site, are not included in the site of work. Such permanent, previously established facilities are not part of the site of work, even where the operations for a period of time may be dedicated exclusively, or nearly so, to the performance of a contract or project.”
(Emphasis added.) The circuit court concluded that plaintiffs quarry workers and
“Based on the uncontroverted facts from the affidavits and the exhibits, the mining site owned by [plaintiff] was established prior to the opening of bids. The fact that a different kind of material was taken from the actual hole or a diffеrent kind of material other than the rock, is irrelevant. It was taken from the mining site. I think these are all facts that are uncontroverted.”
The circuit court’s interpretation of OAR 839-016-0004(19)(c) as a term of the contract provided the basis for its subsequent conclusion that plaintiff had complied with that contractual provision, had not breached the contract, and was entitled to summary judgment. That contract interpretation, rather than the administrative lаw issue that the circuit court did not (and could not) reach, also is the legal issue that the Court of Appeals should have considered on review. We remand to give that court the opportunity to do so.
The decision of the Court of Appeals is vacated, and the case is remanded to the Court of Appeals for further proceedings.
Notes
ORS 279.348(3) provides:
“ ‘Public works’ includes, but is not limited to, roads, highways, buildings, structures and improvements of all types, the construction, rеconstruction, major renovation or painting of which is carried on or contracted for by any public agency to serve the public interest but does not include the reconstruction or renovation of privately owned property which is leased by a public agency.”
BOLI administers and enforces the prevailing wage laws, ORS 279.348 to 279.380, and has statutory authority to adopt rules necessary to do so, ORS 651.060(4).
All references to the Oregon Administrative Rulеs refer to the 1997 compilation, which applied when the contract at issue was formed. BOLI’s definition of “site of work” is now found at OAR 839-016-0004(23).
The contract expressly incorporated ODOT’s “Standard Specifications,” which require compliance with state labor rules. See Oregon Department of Transportation, Standard Specifications for Highway Construction § 00170.00,54 (1996) (contractors of public works must “[cjomply with all laws, ordinances, codes, regulations and rules * * * that relate to the work or to those engaged in the work”). As noted, the parties agreе that this contract was subject to prevailing wage requirements; the dispute concerns what the prevailing wage statute and regulations require.
The parties do not distinguish among the terms “mine,” “quarry,” “borrow pit,” and “pit,” or among the terms “rock,” “hard rock,” “gravel,” and “aggregate,” notwithstanding the different meanings, in some contexts, of those words. Because no party argues that any differences in meaning are relevant to the issues in this case, we ignore any such differences in this opinion.
ORS 279.361(1) provides that “[t]he commissioner [of BOLI] shall maintain a written list of the names of those contractors and subcontractors determined to be ineligible under this section and the period of time for which they are ineligible.”
Other than the warning letter of May 9,1997, there is no evidence in the record that BOLI took any enforcement action against plaintiff.
At oral argument on the motions for summary judgment, the trial judge stated, “As far as I’m cоncerned, if this site had not been opened prior to the opening of the bids, then I would have ruled the other way.”
Under ORS 279.355(4), the commissioner of BOLI may “initiate legal proceedings against employers to enjoin future failures to pay required prevailing wages * * ORS 279.365(1) further authorizes the commissioner to bring a civil action
“to require a public agency under a public contract with a contractor to withhold twice the wages in dispute if it is shown that the cоntractor or subcontractor on the contract has intentionally failed or refused to pay the prevailing rate of wage to workers employed on that contract and to require the contractor to pay the prevailing rate of wage and any deficiencies that can be shown to exist because of improper wage payments already made. In addition to other relief, the court may also enjoin any suсh contractor or subcontractor from committing future violations.”
The commissioner also has available other means of enforcing the prevailing wage requirements. ORS 279.361; ORS 279.370; ORS 652.332.
Plaintiff does so even though, as reflected in his affidavit, he appears to have been aware of the manner in which ODOT intended BOLI’s rules to apply. He stated that he had “several lawsuits pending against [ODOT and BOLI]” in which he had raised similar issues. He identified two other contract disputеs, both of which apparently arose before he signed the contract at issue here.
We note that there might be circumstances in a breach of contract action in which the validity of an agency rule that the parties had incorporated as a contract term is “at issue.” For example, contracting parties might agree that rules later determined to be invalid will not be binding as contract terms. There is no evidence of such an agreement in this case.
