4 Conn. Cir. Ct. 333 | Conn. App. Ct. | 1966
The plaintiff brought suit to recover damages for breach of contract by the defendants. Before trial, the action against the defendant Irene Noonan was withdrawn, leaving only the named defendant, hereinafter called the defendant.
The finding discloses that on November 7, 1961, the plaintiff and the defendant entered into a written contract for the plaintiff to construct a garage on the defendant’s premises in Wilton at a price of $1679. The contract provided that it was the plaintiff’s duty to take care of the building permit and the variance required for the construction. The plaintiff was to complete the garage “three weeks after the permit is gotten,” and in addition there appeared a provision that the garage be completed as “soon as possible.” On the same date, the plaintiff also filled out and signed a “property improvement loan application” on a form provided by the bank for financing the construction, which the bank approved November 13, 1961. When no representative of the plaintiff appeared at the defendant’s home on November 10 or 11, as previ
The court concluded that a valid contract existed between the parties, that the plaintiff was willing to complete the contract, that the plaintiff offered to perform within the time provisions of the contract, that the defendant broke the contract, and that the plaintiff was entitled to recover $600 as damages. The defendant assigns error in the court’s refusal to correct the finding and in the conclusions stated therein.
This court may correct the finding only if “relevant and material facts have been found without evidence, or . . . such facts were admitted or undisputed and have not been found, or . . . facts have been found in language of doubtful meaning.” Practice Book § 985. A fact is not admitted or undis
The remaining assignment of error attacks the court’s conclusions with regard to its finding of $600 damages, claiming that there was no evidence on which to base such an award and that the court erred in using gross profit or markup on this contract, rather than the net profit percentage of the plaintiff’s yearly operations, as the measure of damages. The measure of damages for nonaeceptance or repudiation of contract is set forth in § 42a-2-708 of the General Statutes.
The court found as a fact that the plaintiff’s profit, including the salesman’s commission on the
There is no error.
In this opinion Kosicki and Dearington, Js., concurred.
“See. 42a-2-708. seller’s damages for non-acceptance or repudiation. (1) Subject to subsection (2) and to the provisions of section 42a-2-723 with respect to proof of market price, the measure of damages for non-acceptance or repudiation by the buyer is the difference between the market price at the time and place for tender and the unpaid contract price together with any incidental damages provided in section 42a-2-710, but less expenses saved in consequence of the buyer’s breach. (2) If the measure of damages