CNY Mechanical Associates v. Fidelity & Guaranty InsuranceCNY Mechanical Associates v. Fidelity & Guaranty Insurance
—Order unanimously affirmed without costs. Memorandum: McKinley Mechanical, Inc. (McKinley) was hired as a heating, ventilation and air conditioning subcontractor in connection with construction of a building on the Syracuse University campus. Defendant, Fidelity & Guaranty Insurance Company (F&G), issued a Labor and Material Payment Bond (Bond) in the sum of $1,193,908 for McKinley’s performance on that contract. McKinley hired CNY Mechanical Associates, Inc. (CNY Mechanical) to perform certain work on its behalf. Upon completion of performance, CNY Mechanical made a claim upon the Bond, asserting that McKinley refused to pay $225,000 that was owing to CNY Mechanical for its work. F&G refused to pay, and CNY Mechanical commenced this action to recover on the Bond.
CNY Mechanical moved for summary judgment, and F&G cross-moved pursuant to CPLR 3211 to dismiss the complaint
On appeal, F&G contends that qualifying as a claimant and satisfying the contractual Statute of Limitations pursuant to the terms of the Bond are conditions precedent to recovery and that CNY Mechanical was required to allege compliance with those conditions precedent in its complaint. We disagree.
A party is not required to plead the performance or occurrence of a condition precedent contained in a contract (CPLR 3015 [a]). If a plaintiff fails to allege the performance or occurrence of such a condition precedent, the defendant must deny compliance with the condition precedent specifically and with particularity (CPLR 3015 [a]), and the defendant’s failure to assert a specific denial constitutes a waiver of that defense (see, Igbara Realty Corp. v New York Prop. Ins. Underwriting Assn.,