Proceeding pursuant to CPLR article 78 (initiated in this Court pursuant to Labor Law §§ 220 and 220-b) to review a determination of respondent which found that petitioner failed to pay prevailing wages and supplements.
The Department of Labor’s Bureau of Public Work conducted a lengthy investigation into whether petitioner complied with the requirements of Labor Law § 220 in the performance of
A main focus of the hearing was whether petitioner properly classified particular tasks of work under each contract. On this issue, the Hearing Officer determined that certain work classified as “building laborer” by petitioner should have been classified as “plumber,” thus resulting in underpayments since the plumber rate is higher than the laborer rate. The Hearing Officer specifically found, however, that these underpayments were not willful and thus refused to impose a civil penalty. Ultimately, respondent issued a final determination and order adopting the Hearing Officer’s report and recommendation and finding petitioner liable for $43,710 in underpayments, plus 16% interest annually. This CPLR article 78 proceeding challenging the determination ensued.
Petitioner argues that respondent’s determination classifying the disputed work as that of a plumber, as opposed to a building laborer, was arbitrary and capricious, contrary to statute and unsupported by substantial evidence. Specifically, petitioner claims that, because it relied upon respondent’s published prevailing rate schedule to pay its workers on each of the seven projects and the disputed work fit within the general description of building laborer, respondent cannot make “retroactive changes” to such wage schedule in the course of a compliance proceeding. We are unpersuaded.
First, we disagree with petitioner’s characterization of respondent’s determination as an “ex post facto” and/or retroactive change of a classification. In short, we find no support for petitioner’s claim that the prevailing rate schedule is meant to be determinative on the issue of disputed classifications (see generally Matter of Twin State CCS Corp. v Roberts,
As noted by the Court of Appeals, “while [Labor Law § 220] provides a specific process for calculating the ‘prevailing rate of wage,’ it does not require a specific procedure for [respondent] to use in evaluating the appropriate trade or occupation to assign to particular work” (Matter of Lantry v State of New York,
The record reveals that the Department considered a number of factors in classifying a particular task into the appropriate trade or occupation, including the specific nature of the work, pertinent collective bargaining agreements, jurisdictional agreements, historical practice and past Department recognition. At the hearing in this matter, senior public work wage investigators established that the Department has for some time classified work on plumbing contracts, with a few exceptions not relevant here, as plumbing work.
Notably, this five-foot distinction was employed in both plumbing and site work contracts on the subject projects. Moreover, certain collective bargaining agreements of both trades in the locality of the projects (i.e., plumbers and laborers) recognized this distinction and assigned the disputed work to laborers only if it took place outside the five-foot perimeter of a building. Given this evidence, we cannot say that respondent’s determination that the subject work constituted plumber’s work was irrational or unsupported by substantial evidence (see e.g. Matter of Consolidated Masonry Contrs. v Angello,
Petitioner also argues that the award of interest at the rate of 16% per year was arbitrary and capricious. We are persuaded. First, while a former version of the statutory scheme would have permitted us to reduce the rate of interest applied to the award (see e.g. Matter of NAB Constr. Corp. v Goldin,
However, while respondent most appropriately refused to charge petitioner interest for the time period between the completion of the first set of audits and the commencement of the hearing, we find that all interest prior to the commencement of the hearing should be eliminated (see Matter of M. Passucci Gen. Constr. Co. v Hudacs,
Petitioner’s remaining contentions have been reviewed and found to be without merit.
Cardona, P.J., Mercure, Peters and Spain, JJ., concur. Adjudged that the determination is modified, without costs, by eliminating interest for the period of February 2000 to January 7, 2002, and, as so modified, confirmed.
Notes
To the extent that petitioner’s president testified that he was told otherwise by one particular wage investigator, it was for respondent to weigh this contradictory evidence and resolve credibility questions (see e.g. Matter of Consolidated Masonry Contrs. v Angello,
