Cnf Constructors, Incorporated v. Donohoe Construction Company, a Division of the Donohoe Companies, IncorporatedCnf Constructors, Incorporated v. Donohoe Construction Company, a Division of the Donohoe Companies, Incorporated
Affirmed by published per curiam opinion.
OPINION
Donohoe Construction Company (Donohoe) appeals from a district court ruling that arbitration of a construction contract dispute between Donohoe and CNF Constructors, Inc., (CNF), must take place pursuant to the rules and procedures of the American Arbitration Association (AAA). For the reasons that follow, we conclude that Donohoe’s motion for clarification, upon which the district court ruled and Donohoe appeals, is best characterized as a motion for reconsideration of a final judgment under
I.
This lawsuit centers around the construction of a new Human Studies facility at the University of North Carolina at Chapel Hill. The State of North Carolina, the owner of the facility to be constructed, hired Donohoe as the primary contractor for the site. Do-nohoe, in turn, entered into a subcontract with CNF, under which CNF would perform the mechanical work on the project, such as plumbing and process piping. As the project proceeded, the construction crews encountered unexpected site conditions and problems with installation of the building’s caissons, which substantially delayed the project schedule. The parties essentially dispute who should be held financially responsible for the increased costs arising from the construction delays.
On March 22, 1993, CNF instigated this action in federal court by filing a motion to compel arbitration under the Federal Arbitration Act pursuant to
The district court issued two orders that are relevant to this appeal. In the first
On January 20, 1994, over two months after the district court issued the order compelling arbitration, Donohoe filed a “Motion for Clarification of Judge Boyle’s Order Granting CNF’s Motion to Compel Arbitration.” According to the motion, the American Arbitration Association interpreted the district court’s November 4th order as providing the organization with the authority to conduct the arbitration and, more specifically, to compel Donohoe to attend AAA hearings in Atlanta, Georgia. In its motion for clarification, Donohoe requested that the district court (1) direct CNF to dismiss the action pending before AAA, (2) find that the arbitration was to take place at or near Raleigh, North Carolina, and (3) appoint an arbitrator pursuant to
In its second order, entered on April 6, 1994, the district court addressed the issues raised in Donohoe’s motion for clarification. Without touching upon the jurisdictional basis for addressing the motion, the district court essentially ruled that it had already decided in its first order that the parties were bound under their contract to arbitrate their dispute and that the arbitration was to proceed according to the rules of AAA. The district court concluded its order not by denying the motion for clarification, but instead by stating that “the court orders that its November 4, 1993, order be enforced and arbitration [ ] continue pursuant to the AAA.” (J.A. 240.)
Donohoe timely appealed to this Court from the district court’s second order.
II.
On appeal, Donohoe asks this Court to reverse the district court’s second order, entered April 6, 1994, disposing of Donohoe’s motion for clarification. Specifically, Dono-hoe asks that we (1) order CNF to dismiss the arbitration proceedings before AAA, (2) order that the arbitration take place within the Eastern District of North Carolina, and (3) appoint an arbitrator to resolve the arbitration. Donohoe’s appeal raises interesting and difficult questions as to the procedural intricacies surrounding the arbitration process, as well as to the jurisdictional powers of the district court and this Court to resolve those intricacies.
Before we can consider Donohoe’s requests on their merits, however, we must determine the extent of our own appellate jurisdiction to review the district court’s two orders in this case.
1
Although the lack of
Second, because we conclude that the first order was a final order susceptible to appeal, we look to whether Donohoe’s motion for clarification, from which the second order was issued, was a proper postjudgment motion over which the district court had jurisdiction. As to this portion of the appeal, we conclude that the district court did not abuse its discretion in ruling on the motion for clarification, although we resolve this issue, in large part, upon different grounds than those offered by the district court.
A.
The Federal Arbitration Act (the FAA) specifically explains the circumstances under which a party may appeal a district court order compelling arbitration.
In recent years, we have repeatedly considered what types of orders are “final” for the purposes of
In
Stedor Enterprises,
two textile companies entered into a series of contracts for the sale of textile piece goods. The contracts contained clauses providing for arbitration of any controversies or claims relating to the purchase of the goods. A dispute arose over a shipment of fabric under one of the contracts. However, the purchaser of the fabric never signed or returned the confirmation in which the arbitration clause was contained. The seller served the purchaser with a notice of intent to arbitrate the dispute. The purchaser responded by filing suit, and subsequently removed the case to federal court, seeking temporary and permanent injunctive relief from having to proceed with arbitration. The seller responded by seeking an order compelling arbitration pursuant to
We find that the circumstances underlying the
Stedor
decision are closely analogous to this case, and conclude that the district court’s November 4th order constitutes an appealable final order for the pur
Donohoe argues, however, that the otherwise final order rendered by the district court is not appealable because the district court failed to rule on CNF’s motion to appoint an arbitrator. Although the district court’s November 4th order was not as clear as it could have been, we find that it did resolve the issue of appointing a mediator. A review of the manner in which the district court addressed the issue of compelling arbitration reveals that the district court, at least implicitly, ruled on (and denied) the motion to appoint an arbitrator.
The district court described the negotiation process by which the parties determined whether to arbitrate disputes over contract performance. The process consisted of three exchanges of proposed contracts between the parties. First, Donohoe submitted its form contract for construction projects, including the following portion concerning arbitration:
5.21 Any disputes arising hereunder as to the respective rights or obligations of the parties (excluding matters committed to the sole judgment of the Contractor under subparagraph 5.6) hereto shall be referred to the Architect and his decision shall be binding on both parties.
(J.A 11.) Then, on September 18, 1991, CNF responded to this with the following proposal:
Article 5.21, modify to read as follows:
Any disputes arising hereunder as to the respective rights or obligations of the parties (excluding matters committed to the reasonable judgment of the Contractor under subparagraph 5.6) hereto shall be determined by arbitration pursuant to the Construction Industry Arbitration Rules of the American Arbitration Association.
(J.A. 169.) Finally, on September 20, 1991, Donohoe provided a final proposal:
Article 5.21, delete in entirety.
The following comments are related to ATTACHMENT “A” of the Subcontractor. Relative plans & spec first to Architect. Performance or other contractual items first to Arbitration.
(J.A. 169.) After reciting the proposals, the district court found that CNF accepted the final Donohoe proposal and Donohoe prepared the revised contract between the parties. (J.A. 169.)
The district court, however, further discussed its interpretation of the negotiation process. In particular, the district court reasoned:
After reviewing the contested facts regarding the formation of the subcontract, this court finds that Donohoe and CNF had agreed upon an arbitration clause within their contract. Donohoe made the initial offer when it presented CNF with Article 5.12 of its standard form for CNF’s consideration. CNF modified this when it proposed an arbitration clause.
[On September 20, 1991,] Donohoe then countered with a composite proposal that incorporated both a referral of some disputes to the architect and others to arbitration. Disputes having to do with the plans and specifications were to go first to the architect, as originally proposed in the standard form agreement. Disputes having to do with contract performance and other contract matters were to be sent directly to arbitration as provided by the arbitration clause originally submitted by CNF as Article 5.21, in reply to the proposed standard subcontract form.
(J.A. 170.) (emphases added). The district court reiterated this final point when it stated that the parties reached agreement on the resolution of contract performance disputes and that the agreement included the “counteroffer-modification proposal including the arbitration clause.” (J.A. 171.)
The extended interpretation of the negotiation process offered by the district court
Accordingly, having rejected Donohoe’s argument that the district court failed to address all the issues presented in the parties’ initial motions, we return to the fundamental point that the district court’s November 4th order was final for the purposes of the FAA As a final order, Donohoe could have taken a direct appeal of that order to this Court, as provided by
[I]n a civil case in which an appeal is permitted by law as of right from a district court to a court of appeals the notice of appeal required by Rule 3 [Fed.RApp.P.] must be filed with the clerk of the district court within 30 days after the date of entry of the judgment or order appealed from
Fed.RApp.P. 4(a)(1) . Donohoe chose not to appeal that first order from the district court. Therefore, we move to the district court’s second order on Donohoe’s motion for clarification.
B.
Our conclusion that the district court’s first order was final for the purposes of the FAA directly affects the manner in which we consider the appealability of the district court’s second order. Once a final judgment has been rendered by a district court, we have stated that “[i]n cases where a party [subsequently] submits a motion ... which is unnamed and does not refer to a specific Federal Rule of Civil Procedure, the courts have considered that motion either a
“To the extent that the post-judgment motion sought to have the district court reconsider its ruling with respect to the [issues addressed in the district court’s original order], it [is] clearly improper, because
We agree with CNF, in large part, and conclude that a substantial portion of Dono-hoe’s motion simply reiterates legal arguments already addressed in the district court’s first order. On appeal, Donohoe requests, in part, that we reverse and remand to the district court, with orders to (1) direct CNF to dismiss the action before AAA and (2) appoint an arbitrator pursuant to
Our conclusion that Donohoe simply asked the district court to reconsider what it had already resolved raises an interesting question concerning the standard of review we are to apply under
Although we decline to review those issues that the district court addressed in its first order, there remains one argument in Donohoe’s motion for clarification that was not a simple re-argument of matters directly decided by the district court: Donohoe’s request that the district court order the arbitration proceedings to proceed in the Eastern District of North Carolina. At some level of abstraction, the venue issue flows from the district court’s holding that AAA
III.
For the reasons stated above, the district court’s order of April 6, 1994, refusing to alter its earlier order compelling arbitration is affirmed. 3
AFFIRMED.
Notes
. As an initial matter,
Donohoe
argues that this Court is estopped from considering the jurisdictional issues in this case because a panel of this Court previously denied a motion to dismiss the appeal for lack of jurisdiction. We disagree and hold, in accordance with all other Circuits that have considered the issue, that the doctrine of “law of the case” does not prevent this Court from revisiting a prior ruling of a motion panel on the Court’s jurisdiction.
Johnson v. Burken,
. Functionally, the
Williams
decision renders reconsideration of legal arguments under
While this rationale has intuitive appeal as a manner in which to resolve the issue under the abuse of discretion standard, we note that at least one Court of Appeals has taken a similar route in analyzing the problem but disposed of the issue by dismissal instead of by affirmance. In
Smith v. Evans,
The effect of dismissing the appeal as to any issues raised under
We also pause to consider the implications of
In re Burnley,
. Subsequent to oral argument, Donohoe filed a motion to dismiss this appeal. Donohoe argues that dismissal is appropriate because the arbitration panel issued an order resolving the underlying claims and Donohoe fears increased costs that might result now from a reversal of the district court's order. An arbitration panel's resolution of a submitted claim does not necessarily render an appeal moot.
Dollar Rent a Car of Washington v. Travelers Indem.,