OPINION
This case comes before the Court on the motion of the defendant Mabro Construction, Inc., to stay proceedings pending arbitration and to compel arbitration.
Suit was filed by plaintiff Mаyhew, Inc., a subcontractor, against Mabro Construction, Inc., a general contractor, for monies due for labor and materials furnished. The parties had signed a contract in Novembеr, 1972, whereby the plaintiff agreed to paint and cover the walls of the Foxhall Apartments which the defendant was building. The contract contained a clause providing that:
“Any dispute arising under this contract shall be submitted to arbitration in accordance with the provisions, then obtaining, of the Standard Form of Arbitration Procedure of the American Institute of Architects. The Subcontractor agrees that he will not take any legal action or institute proceedings of any kind for the enforcement of what he may deem to be his rights in connection with the subject matter of аny dispute between himself and the Contractor until the Contractor either shall have refused to submit the same to arbitration, or . shall have rejected *193 or refused to comply with the decisiоn of the Arbitrators. . . .”
A dispute arose between the parties concerning payments and concerning the schedule of performance. A meeting was held about November 27, 1973, by the parties at which time they discussed cancelling or suspending or terminating the contract, and an agreement (now disputed) was made. Thereafter, plaintiff did no more work for defendant. Defendant bought from plaintiff his remaining inventory of paint and wall covering, but did not pay for the work plaintiff had done. Instead, on February 14, 1974, Mabro filed a demand for arbitration, claiming that Mayhew owed the defendant $138,478.10, the cost of completing the painting and wall covering.
On March 8, 1974, Mayhew filed this suit for monies due for labor and materials, claiming $39,894.67 is owed by defendant for the reasonable worth of work and materials furnished. On March 28, 1974, the defendant filed the instant motion to stay proceedings pending arbitration (9 U.S.C. § 3) and to compel plaintiff to submit to arbitration (9 U.S.C. § 4).
Title 9 of the U.S. Code, Section Threе, provides that “upon being satisfied that the issue involved in such suit or proceeding is referable to arbitration” a federal court shall stay court proceedings until after arbitration has bеen had.
Section Four provides that if one party to an arbitration agreement fails to arbitrate, a federal court shall, “upon being satisfied that the making of the agreement for arbitration or the failure to comply therewith is not in issue,” order the refusing party to proceed with arbitration. But if either of these points is in issue, a hearing must be held on that issue by the Court, and the party alleged to be in default can demand jury trial.
In this case the plaintiff raises as a defense to the motion the claim that the contract which contained the arbitration clause wаs canceled by mutual agreement of the parties at the November 27, 1973 meeting.
The issue, then, is whether a dispute arising out of a contract containing an arbitration clause is referаble to arbitration if it is claimed that the parties mutually canceled the contract; or does the claim of mutual cancellation put “the making of the agreement for arbitratiоn in issue,” necessitating a trial on that point?
In favor of referring the entire dispute to arbitration is the general principle that questions of arbitrability are initially for arbitrators.
“[A]ny doubts as to the construction of the [Arbitration] Act ought to be resolved in line with its liberal policy of promoting arbitration both to accord with the original intention of the parties and to help ease thе current congestion of court calendars.” Robert Lawrence Co. v. Devonshire Fabrics, Inc.,271 F.2d 402 , 410 (2d Cir. 1959) cert. dismissed364 U.S. 801 ,81 S.Ct. 27 ,5 L.Ed.2d 37 (1960).
In Petition of Ropner Shipping Co., Ltd.,
In World Brilliance Corp. v. Bethlehem Steel Co.,
Numerоus federal cases have held that even though a contract is terminated or expires, that does not erase the continu
*194
ing effectiveness of the arbitration agreement, and have entered Orders compelling arbitration even though the contract in which the arbitration clause was written expired before the demand for arbitration was filed. See, e. g., Zenol, Inc. v. Carblox, Inc.,
In 1967 the Supreme Court, in Prima Paint Corp. v. Flood & Conklin Mfg. Co.,
“This case presents the question whether the federal court or an arbitrator is to resolve a claim of ‘fraud in the inducement,’ under a contract governed by the United States Arbitration Act of 1925 . . . ." Id. at 396,87 S.Ct. at 1802 .
The Court observed that there was a split among the Circuits over whether questions about the validity of the whole contract should always be referred to arbitrators. Reviewing the various positions, the Court adopted the viеw of the Second Circuit that disputes concerning the validity of the whole contract must be separated from disputes relating specifically to the arbitration agreement, and only the latter should be considered by the courts before being referred to arbitrators.
“We hold, therefore, that in passing upon a § 3 application for a stay while the parties arbitrate, a federal court may consider only issues relating to the making and performance of the agreement to arbitrate. In so concluding, we not only honor the plain meaning of the statute but also the unmistakably clear congressional purpose that arbitration procedure, when selected by the parties to a contract, be speedy and not subject to delay and obstruction in the courts.” Id. at 404,87 S.Ct. at 1806 . (emphasis added).
Since this decision, a few circuit courts have given
Prima Paint
a narrow reading.
*
In General Guaranty Insurance Co. v. New Orleans General Agency, Inc.,
The Seventh Circuit in Halcon International, Inc. v. Monsanto Australia, Ltd.,
On the other hand, the Second Circuit has continued to support the federal policy favoring arbitration and has more liberally interpreted
Prima Paint.
See, e. g., Hamilton Life Insurance Co. of New
*195
York v. Republic National Life Insurance Co.,
It seems beyond dispute that the parties are entitled to agree, should they so desire, that one of the questions referable to arbitration is the question of whether the contract has been terminated, abandoned, or canceled. See Robert Lawrence Co. v. Devonshire Fabrics Inc.,
supra,
The parties here apparently did so agree when they approvеd the broad arbitration agreement involved. As set forth above, that agreement bound the plaintiff to
“not take any legal action or institute proceedings of any kind for the enforcement of what he may deem to be his rights in connection with the subject mаtter of any dispute between himself and the Contractor . . .”
(emphasis added)
until he tried arbitration. See R. Coulson, Prima Paint: An Arbitration Milestone, 23 BUS.LAWYER 241, 246 (1967): “When a businessman uses a broad arbitration clause, he indicates that he wants ALL issues to be arbitrated.”
It is also true that parties can agree to terminate or cancel an arbitration agreement; and if such were alleged to have occurred in this сase, there would still have to be a trial on that issue and a determination that the arbitration agreement were still in effect before this Court could issue a stay of proceedings or an order to arbitrate.
However, the procedure is not the same when a party alleges that the entire contract was canceled. The holding of the Supreme Court in Prima Paint indicatеs that such issues are for arbitrators and not for federal courts to decide.
The defendant’s motion to stay proceedings and to compel arbitration will be granted.
Counsel for the defendant will prepare an appropriate Order.
Notes
It appears that Prima Paint has not yet been applied by the Courts of Appeals for this Circuit.
