Clifford R. Gray, Inc. v. City School DistrictClifford R. Gray, Inc. v. City School District
Cross appeals from a judgment of the Supreme Court (Maney, J.), entered July 15, 1999 in Albany County, upon a decision of the court in favor of plaintiff.
The principal issue presented in this litigation between plaintiff, an electrical contractor, and defendant, the owner of a
It is well settled that, in spite of the inclusion in a construction contract of “[a] clause which exculpates a contractee from liability to a contractor for damages resulting from delays in the performance of the latter’s work * * * damages may be recovered for: (1) delays caused by the contractee’s bad faith or its willful, malicious, or grossly negligent conduct, (2) uncontemplated delays, (3) delays so unreasonable that they constitute an intentional abandonment of the contract by the contractee, and (4) delays resulting from the contractee’s breach of a fundamental obligation of the contract” (Corinno Civetta Constr. Corp. v City of New York,
Supreme Court credited the testimony of plaintiff’s president and an architectural engineer called as plaintiff’s expert witness who each detailed the causes of the delays that plagued
“Notwithstanding our broad scope of review in a nonjury trial, we accord great deference to the credibility determinations rendered by the trial court due to its ability to view the witnesses and the evidence firsthand [citations omitted]” (Auger v State of New York,
We disagree with defendant’s argument that plaintiffs request for damages should have been rejected in its entirety because the August 1995 correspondence was not sufficiently particularized to comply with the notice requirement. In contrast to the detailed contract specifications at issue in A.H.A. Gen. Constr. v New York City Hous. Auth. (
Arguing that the notice provision was inapplicable because it refers to requests for extensions and not claims for money damages, plaintiff maintains that Supreme Court erred in restricting its recovery in each of the six categories of damages awarded to expenses or losses incurred after August 1995. As plaintiffs notice of appeal challenges only so much of the judgment as denied its claim for damages for extended home office
Finally, we find plaintiff’s request to recover home office overhead expenses
We have considered the parties’ remaining contentions and find them to be unpersuasive.
Cardona, P. J., Peters, Carpinello and Rose, JJ., concur. Ordered that the judgment is affirmed, without costs.
Notes
. Section 6.06 of the “Terms and Conditions to Contract” provided, in pertinent part, as follows:
“(a) If Contractor shall be delayed in the commencement, prosecution or completion of the Work or shall be obstructed or hindered in the orderly progress of the Work by any act, neglect or default of Owner, Construction Manager, Architect, [or] Other Contractor * * * which preclude the continuation of the Project or the Work or portion thereof in a practicable manner then the time fixed for completion of the Work shall be extended for a period equivalent to the period of the delay incurred by Contractor as determined by Owner. No extension shall be granted unless a claim in writing therefore [sic] is presented to Construction Manager within seventy-two (72) hours of the start of such delay, obstruction or hindrance. Failure to give notice as provided herein constitutes a waiver of claim by Contractor. In the event of a continuing cause of delay, only one claim is necessary.
“(b) Contractor expressly agrees for itself, its Subcontractors and suppliers not to make, and hereby waives, any claim for damages on account of any delay, obstruction or hindrance. Contractor’s sole remedy for any delay, obstruction or hindrance shall be an extension of the time in which to complete the Work.”
. Plaintiff has not raised any issue concerning the warehouse worker and truck expenses in its brief on appeal.