53 So. 313 | Ala. | 1910
The courts of the land have experienced no- little difficulty in construing contracts stipulating for a payment of a specific sum of money on a contingency, and in determining whether the sum so mentioned should be regarded as a penalty or as liquidated damages. The primary rules for interpretation are laid down in the case of Keeble v. Keeble, 85 Ala. 552, 5 South. 149; and, applying those rules to the contract in question, it was the manifest intention of the .parties thereto to fix the sum named as liquidated damages to compensate the defendant for losses in the operation of its plant caused hv a delay in the shipment of the cranes, which, while constituting but a part of the defendant’s works or plant, were essential to the manufacture of its products and the successful operation of same. The damages accruing could not be easily .estimated or ascertained in an action at law, and it was but natural for the parties to agree upon a fixed and certain sum as liquidated damages, and which was not intended as a penalty. Such is not only the wording of the contract, but said wording is substantiated by the surrounding facts and circumstances, which evince an intent and purpose of the contracting parties to provide for liquidated damages rather than a penalty; and we think that the trial court properly construed the contract, and properly overruled the plaintiff’s demurrers to the defendant’s special pleas of set-off and recoupment.
Replications 3 and 4 were subject to the demurers interposed to same, and which were properly sustained by the trial court.
The trial court committed no reversible error in ruling upon the evidence.
The judgment of the circuit court is affirmed.
Affirmed.