700 N.E.2d 54 | Ohio Ct. App. | 1997
[EDITORS' NOTE: THIS PAGE CONTAINS HEADNOTES. HEADNOTES ARE NOT AN OFFICIAL PRODUCT OF THE COURT, THEREFORE THEY ARE NOT DISPLAYED.] *375
[EDITORS' NOTE: THIS PAGE CONTAINS HEADNOTES. HEADNOTES ARE NOT AN OFFICIAL PRODUCT OF THE COURT, THEREFORE THEY ARE NOT DISPLAYED.] *376
[EDITORS' NOTE: THIS PAGE CONTAINS HEADNOTES. HEADNOTES ARE NOT AN OFFICIAL PRODUCT OF THE COURT, THEREFORE THEY ARE NOT DISPLAYED.] *377 This matter is before this court upon the appeal of Cleveland Construction, Inc. ("Cleveland"), appellant, from the May 7, 1996 judgment entry of the Franklin County Court of Common Pleas. The history of this case is as follows: Cleveland is an Ohio corporation that submitted a bid to complete Phase I of a public works project known as the Max M. Fisher College of Business.("Fisher Project") at the Ohio State University. The Department of Administrative Services ("DAS") is an agency for the state of Ohio that acts as the contracting authority for the state on public construction projects. The Ohio State University ("OSU") is the agency that will occupy the project once it is completed.
In February 1996, DAS sought to procure bids for the Fisher Project. As part of the contract documents which potential bidders received, DAS included its "Standard Conditions of Contract for Construction," which further contained "Instructions to Bidders." Sections 3.5.3 and 3.5.4 of the Instructions to Bidders provide information pertinent to the determination of whether a bidder is a "responsible" bidder and lists the factors set forth in R.C.
Cleveland submitted a base bid for the "general trades" portion of the project in the amount of $22,898,000. Cleveland further submitted bids for alternates one through fourteen, bringing the total base bid, plus alternates, to $24,421,000. The other apparent low bidders on the project were appellee Danis Building Construction Company ("Danis") and Dick Construction ("Dick"). The base bid submitted by Danis for the general trades portion of the project was $23,278,000, and the base bid for the general trades portion of the project submitted by Dick was $22,987,000. *379
At the February 21, 1996 bid opening, both Jill Morelli and Chuck Hamilton, who represented the OSU Architect's Office at the bid opening, raised concerns about prior work that Cleveland had performed on OSU's campus. Morelli's concern stemmed from the work Cleveland performed as the interior packages contractor on the building which is currently occupied by Morelli and the OSU Architect's Office. The parties dispute whether Cleveland failed to complete several punch list items. Hamilton's concern stemmed from the fact that he understood Cleveland to be an interior packages construction company, and did not know whether Cleveland had ever performed as the lead contractor on a public works project of the scope and complexity of the Fisher Project. At trial, Tom Poulton, the Project Administrator for the Office of Construction Management of DAS, expressed a similar concern.
Subsequent to the submission of the bids, Morelli recommended to DAS that two apparent low bidders be announced, namely Cleveland and Dick, because the decision as to which alternates to accept had not yet been determined. Thereafter, OSU made its decision to accept all of the general trades contract alternatives. Thus, Cleveland was the apparent low bidder and Danis was the second low bidder.
On or about March 4, 1996, Morelli met with counsel for DAS to discuss conducting a responsibility investigation as contemplated under R.C.
On March 5, 1996, the deputy director for DAS, George Kaitsa, sent a letter to nine contractors requesting that they submit information on the following criteria:
"(1) experience of the bidder, including a list of recent public projects completed of a similar nature. Mr. Kaitsa asked the contractors to indicate the scope and value of their contracts and the name of an owner representative for a reference;
"(2) financial condition of the bidder, including a certified financial statement;
"(3) conduct and performance of the bidder on previous contracts, including any prevailing wage complaints, EEOC regulation issues or citations from EPA, OSHA or other regulating entities;
"(4) facilities of the bidder; and,
"(5) management skills of the bidder." *380
Kaitsa indicated that as to numbers four and five, the bidders could submit any information they deemed relevant to these factors. Cleveland received Kaitsa's March 5 letter and responded accordingly. Prior to its response, Cleveland did not contact DAS to request any direction or assistance in responding to this letter.
Morelli also formed a committee to review the information submitted in response to Kaitsa's March 5 letter. The members of the committee were as follows: Greg Honzo, a representative of Gilbane Building Company, the construction manager for the Fisher Project; Dick Carpenter, a representative of Karlsberger Company, the associate architect for the project; and Hamilton.
Between March 5 and March 18, 1996, the committee conducted an analysis of the bidders that submitted bids for the project using the information submitted by the bidders in response to Kaitsa's March 5 letter. The committee developed a series of standardized questions to ask the bidders about their experience, financial condition, conduct and performance on prior contracts, facilities and management skills. The committee also conducted a series of reference checks using projects submitted by the various bidders. Honzo performed reference checks for those contractors that bid to serve as the lead contractor on the Fisher Project. It should be noted that reference checks were also performed for some of the other contractors on the project, even though they would not serve as the lead contractor.
Honzo contacted representatives of the RTA Bus Garage Project in Cleveland, Ohio, and the Design Architecture and Art Planning Project ("DAAP") at the University of Cincinnati. Honzo testified that he chose not to contact Cleveland's private references, simply because those projects were retail in nature and were in no way comparable in scope and complexity to the Fisher Project. It should be noted that several of the references for these private projects were contacted later by Kaitsa when he conducted his independent investigation, after the protest meeting.
As a result of their investigation, the committee and OSU ultimately made a recommendation to DAS that Cleveland be found not responsible and that Danis be awarded the contract. The results of the committees investigation are contained in the March 19, 1996 letter to Deputy Director George Kaitsa, which, although signed by Morelli, was drafted by the committee members. On or about March 20, 1996, Morelli and Kaitsa met to discuss the results of the committees investigation. Kaitsa reviewed the committees results and further reviewed a spreadsheet prepared by the committee.
Kaitsa testified that at that time he did not conduct an independent investigation but, rather, relied on the findings of the committee. At that time, Kaitsa simply reviewed the process undertaken by the committee in conducting its *381 responsibility investigation. Kaitsa testified that he did not see any problem with the process and, for that reason, made his recommendation to the director of DAS, Sandra Drabik, that Cleveland be found not responsible. Drabik concurred with Kaitsa's recommendation that Cleveland be found not responsible for the Fisher Project, and further agreed that the general trades contract be awarded to Danis as the next low bidder. On March 22, 1996, DAS notified Cleveland of its decision.
Thereafter, on or about March 27, 1996, Cleveland requested a protest meeting pursuant to R.C.
Following the April 2 meeting, Kaitsa conducted his own independent investigation. He investigated Cleveland's financial status, experience on similar projects, management skills, and overall ability to execute the contract properly. Kaitsa further testified that he reviewed all of the information provided by Cleveland at the April 2 meeting, the results of the investigation performed by the committee, and his own reference checks, which included several of the private reference checks that Cleveland had submitted. After performing this independent investigation, Kaitsa recommended to Drabik that Cleveland be found responsible with respect to its financial condition, but not responsible with respect to experience, management skill, past performance on other contracts, and an overall ability to execute the contract properly. On April 5, 1996, Drabik informed Cleveland that DAS was affirming its earlier decision insofar as DAS found that Cleveland was not a responsible bidder for the Fisher Project. It should be noted that the prior determination that Cleveland was not financially responsible was reversed after Kaitsa's independent investigation.
On April 12, 1996, DAS issued its notice of award to Danis. On or about April 18, 1996, Danis received its notice to proceed and began mobilizing equipment and moving forward with construction. Danis also acquired performance bonds and liability insurance and made commitments to various subcontractors and suppliers, all at an estimated cost of $500,000 prior to the conclusion of the trial. Construction on the Fisher Project has been proceeding since the time Danis received its notice to proceed.
Before Danis received its notice to proceed, Cleveland filed its verified complaint seeking injunctive and declaratory relief. Cleveland sought to enjoin DAS from awarding, executing, or beginning performance of the contract for the *382 general trades portion of Phase I of the Fisher Project. Cleveland also moved for a temporary restraining order, which was subsequently denied. The trial court consolidated the hearing on the preliminary injunction with the trial on the merits. The trial was held from April 25 to April 30, 1996. On May 7, 1996, the trial court issued its findings of fact and conclusions of law, along with its judgment entry. The court dismissed the complaint and denied Cleveland's request for declaratory and injunctive relief. Cleveland timely appealed and on appeal asserts the following assignments of error:
"1. The trial court erred when it denied Appellant's request for declaratory relief.
"2. The trial court erred when it denied Appellant's request for injunctive and/or declaratory relief on the grounds that Appellee Ohio Department of Administrative Services (`ODAS') had abused its discretion.
"3. The trial court erred when it denied Appellant's request for injunctive and/or declaratory relief on the grounds that ODAS had failed to legally promulgate rules and/or regulations to govern its determination of Appellant's responsibility as a bidder.
"4. The trial court erred when it denied Appellant's request for injunctive and/or declaratory relief on the grounds that ODAS utilized illegal rules, not legally promulgated, to find that Appellant was not a responsible bidder.
"5. The trial court erred when it denied Appellant's request for injunctive and/or declaratory relief on the grounds that Ohio Revised Code Section
"6. The trial court erred when it utilized the wrong standard for `abuse of discretion' in the context of public competitive bidding in making its determination that Appellant was not entitled to the relief requested.
"7. The trial court erred when it held that R.C.
"8. The trial court erred when it failed to find that ODAS's use of its `frontend documents' to establish rights and obligations of parties who contract with the State of Ohio are rules which must be duly promulgated in accordance with law.
"9. The trial court erred in finding that the `Committee' who undertook the non-responsibility investigation of Appellant was doing so for and on behalf of ODAS.
"10. The trial court erred in finding that the protest meeting contemplated by R.C.
"11. The trial court erred in finding that the criteria set forth in R.C.
"12. The trial court erred in finding that the procedures applied in determining `responsibility' under R.C.
"13. The trial court erred in finding that ODAS fully complied with R.C.
"14. The trial court erred in finding that the process used by ODAS in evaluating bidders pursuant to the criteria set forth in R.C.
"15. The trial court erred in finding that ODAS and Intervenor-Appelle The Ohio State University had the unbridled discretion to accept another bid or reject all bids when either party determined it would not be in the best interest of the State to award to the lowest responsive bidder pursuant to ยง 3.4.4 of the Instructions to Bidders and R.C.
"16. The trial court erred in finding that the contract entered into between ODAS and Intervenor-Appelle Danis Building Construction Company is not void, ab initio.
"17. The trial court erred in allowing Intervenor-Appellees The Ohio State University and Danis Building Construction Company to intervene."
In the instant action, Cleveland seeks review of two types of claims in this matter: claims for declaratory judgment and claims for injunctive relief. The granting of declaratory relief and the issuance of an injunction are matters of judicial discretion that will not be disturbed on appeal absent an abuse of discretion by the trial court. Control Data Corp. v. Controlling Bd.
(1983),
Moreover, the proof necessary to support the granting of an injunction must be clear and convincing, and the right thereto must be clear and established by the strength of Cleveland's own case and not by the weakness of appellees' case. SeeW.C.I./Waltek v. Ohio Bldg. Auth. (Aug. 4, 1994), Franklin App. No. 93APE1-1583, unreported, 1994 WL 409780, citingWhite v. Long (1967), *384
However, to prevail on a complaint seeking injunctive relief with respect to the award of a public contract, Cleveland must prove by clear and convincing evidence that the award constituted an abuse of discretion and resulted in some tangible harm to the public in general, or to Cleveland individually. In this context, abuse of discretion has been defined as an unreasonable, arbitrary or unconscionable attitude. Cedar Bay Constr., Inc.v. Fremont (1990),
In its second, thirteenth, and fourteenth assignments of error, Cleveland argues that it is entitled to injunctive relief because of the arbitrary nature of DAS's use of unannounced and unlawful criteria to determine responsibility. We disagree. R.C.
"The factors that the state agency or political subdivision shall consider in determining whether a bidder on the contract is responsible include the experience of the bidder, his financial condition, his conduct and performance on previous contracts, his facilities, his management skills, and his ability to execute the contract properly."
R.C.
Secondly, Cleveland takes issue with the fact that Honzo only checked references pertaining to public projects when it checked references for Cleveland, *385
but checked references for private projects for Danis. References regarding recent public projects pertain to the prior experience of the bidder as well as his conduct and performance on previous contracts. R.C.
Cleveland further argues that the committee and DAS improperly considered the fact that the second phase of the Fisher Project would be ongoing during Phase I, that the Fisher Project was of architectural significance, and that it was a legacy project. Initially this court notes that Honzo testified that he would still recommend that Cleveland be found not responsible, even if there were no second phase to the project.
This court finds that such factors go to the ability of Cleveland to execute the contract properly. R.C.
Cleveland further objects to the fact that Honzo did not put as much emphasis on written recommendations as he did on telephone conversations. Cleveland points to Morelli's March 19 letter, which indicated that Cleveland's reference checks indicated that they would not have Cleveland on another job, without giving the reasons why Cleveland would not be on some of these jobs. A review of the transcript reveals that Cleveland had the opportunity to explain why RTA would not have Cleveland on another job, namely, that Cleveland did not wish to work on another RTA job. All of this evidence was before the trial court to weigh and consider. It is not this courts function to make those credibility determinations.
Honzo testified as to his reasons for why he did not give much credence or weight to a written recommendation. There was also testimony in the record to *386 reflect why Honzo preferred to hear from an owner as opposed to a construction manager, and why he would give an owners opinion more weight. Again, the trial court was free to accept or reject Honzo's testimony. It was free to decide if Honzo's approach was reasonable. Such credibility determinations belong to the trier of fact, not this court.
For all of the above reasons, this court rejects Cleveland's argument that the above constitute "unannounced" criteria. Clearly the information sought by Kaitsa and the committee was collected in an effort to address the factors set forth in R.C.
"To have that effect, the variations from the instructions or specifications must be substantial, and to be substantial, it must affect the amount of the bid and must give the bidder an advantage or benefit not allowed to other bidders." Id.
at 819,
As previously noted, all of these factors were considered by the committee in reviewing Danis, Dick, and Cleveland. This court cannot find that Danis was given an advantage or benefit not allowed to Cleveland. For those reasons, appellants second, thirteenth and fourteenth assignments of error are overruled.
Cleveland also argues that the committee and DAS improperly collected this information for purposes of R.C.
This court is cognizant of R.C.
"After investigation, which shall be completed withinthirty days, the contract shall be awarded by such owner to the lowest responsive and responsible bidder in accordance with section
Given the time constraints of R.C.
In Cleveland's sixth assignment of error, Cleveland argues that the court erred when it utilized the wrong standard for abuse of discretion in the context of public competitive bidding, in making its determination that Cleveland was not entitled to the relief requested. The Supreme Court's decision in DanisClarkco Landfill Co. v. Clark Cty. Solid Waste Mgt. Dist.
(1995),
"It is true that Danis presented evidence that one District board member had indicated he would `help lead the fight against Danis,' and that prior to the date set for submission of proposals another board member had written a handwritten note indicating that the District `must follow the procedures
preserve [the District's] ability to oppose Danis in the future.' * * * It is clear that the members of the District's boardmay have been influenced by citizens opposed to the selection of Danis's proposal, and may well have held apredisposition against accepting its proposal. However, such areluctance under the circumstances of this case does notnecessarily demonstrate bad faith or abuse of discretion."
(Emphasis added.) Id. at 604-605,
The Supreme Court found that this did not necessarily demonstrate bad faith or an abuse of discretion.
Likewise, even though Jill Morelli had heard negative comments from Ron Kull, the architect at the University of Cincinnati, regarding the DAAP project, or had a "predisposition" against Cleveland, such factors would not necessarily rise to the level of bad faith and/or an abuse of discretion.
Cleveland cites the Supreme Court's decision in Dayton exrel. Scandrick v. McGee (1981),
Cleveland argues that the above definition of "abuse of discretion" should have been utilized by the trial court. This court notes that in both the Danis and theScandrick cases, the court defined "abuse of discretion" as an unreasonable, arbitrary or unconscionable attitude.Danis, Scandrick, supra; see, also, Cedar BayConstruction, supra,
Moreover, in the Wilson Bennett case, the court citedScandrick for the proposition that one was not required to award the contract to the lowest bidder; but was rather empowered to make a qualitative determination as to which bid was both lowest and best. In this case, DAS had the discretion to determine which bid was the lowest, responsive, and responsible bid. R.C.
In its ninth assignment of error, Cleveland objects to the trial courts finding that the committee that undertook the responsibility investigation was doing so for and on behalf of DAS. Testimony at trial revealed that two of the committee members, Honzo and Carpenter, worked for companies that had contracts with DAS for the Fisher Project. DAS contracted with Karlsberger to act as its associate architect on the Fisher Project. Carpenter is Karlsberger's project manager on the Fisher Project. DAS also contracted with the Gilbane Building Company to act as the construction manager, and Honzo was serving as Gilbane's project manager for the Fisher Project. Both Kaitsa and Drabik testified that they understood that the committee performing the investigation contained two DAS representatives, namely Honzo and Carpenter.
Moreover, Kaitsa was free to accept and/or reject the recommendations of the committee. Both Morelli and Hamilton testified that they understood that DAS would review the investigation and recommendation made by the committee, and that DAS had the ultimate authority in determining responsibility. The record reflects that the ultimate determination was left to Kaitsa and the director of DAS, Sandra Drabik. In fact, after the protest meeting, Kaitsa did recommend that a finding of the committee be changed and that Cleveland be found to be financially responsible.
Cleveland apparently takes the position that Kaitsa must conduct every responsibility determination personally. This court cannot find that the statute *389 prohibits Kaitsa from delegating this duty. It should be noted that Cleveland correctly points out that there is testimony in the record to reflect that Kaitsa and/or the director of DAS did not delegate this authority up front. However, the fact remains that after the investigation was complete, and once DAS discovered that this investigation had been completed, DAS was free to use that information in order to determine whether Cleveland should be deemed not responsible for this particular project. For those reasons, this court finds that the trial court did not err in finding that the committee undertook its responsibility investigation on behalf of DAS, insofar as DAS utilized that investigation in making its final determination. Appellants ninth assignment of error is overruled.
In its fifteenth assignment of error, Cleveland argues that the trial court erred in finding that DAS and OSU had unbridled discretion to accept another bid or reject all bids when either party determined it would not be in the best interest of the state to award to the lowest responsive bidder. Initially it should be noted that the statute in question discusses the lowest responsive and responsible bidder. R.C.
R.C.
"If in the opinion of the owner referred to in section
Section 3.4.4 of the Instructions to Bidders provides:
"If in the opinion of the Owner, the award of the contract to the lowest Bidder is not in the best interest of the State, with the written consent of the Director, the Owner may accept, in its discretion, another bid so opened or reject all bids, and advertise for other bids, pursuant to Section
In this assignment of error, Cleveland objects to conclusion of law No. 25, wherein the trial court stated that DAS had no legal duty to award the contract for the general trades portion of the project to Cleveland in that DAS and OSU always had the right to accept another bid or to reject all bids when not *390
in the best interest of the state, pursuant to Section 3.4.4 of the Instructions to Bidders and R.C.
Cleveland has not presented any argument to this court to explain why the trial court should not have abided by R.C.
Moreover, the record supports Das's finding that awarding the contract to a nonresponsible bidder was not in the best interest of the state. The record is replete with testimony regarding dissatisfaction on the part of owners with Cleveland's performance in the past. John Childress, who is the owners representative on the DAAP project, testified at length regarding the difficulties that had been encountered in working with Cleveland on the DAAP project at the University of Cincinnati. On appeal, Cleveland adamantly challenges and attempts to undermine Childerss's testimony, but the issues of Childerss's credibility and what weight ought to be given his testimony belong to the trier of fact, not to this court. For all of the above reasons, appellants fifteenth assignment of error is overruled.
In its sixteenth assignment of error, Cleveland argues that the trial court erred in finding that the contract entered into between DAS and Danis is not void ab initio. It is Cleveland's contention that R.C.
The trial court found that the contract entered into between DAS and Danis complied with R.C.
Next, Cleveland argues that several sections of the front-end documents, specifically the Instructions to Bidders, are invalid and unlawful insofar as *391
they were not promulgated in accordance with R.C. Chapters
"`Agency' means, except as limited by this division, any official, board, or commission having authority to promulgate rules or make adjudications in the bureau of employment services, the civil service commission, the department of industrial relations, the department of liquor control, the department of taxation, the industrial commission, the bureau of workers compensation, the functions of any administrative or executive officer, department, division, bureau, board, or commission of the government of the state specifically made subject to sections
As noted by this court in Stanfield v. Ohio Dept. of Admin.Servs. (June 27, 1985), Franklin App. No. 84AP-1050, unreported, 1985 WL 10356, R.C.
Thus, the issue was whether or not the first category, which consisted of agencies enumerated in the statute, applied to DAS. In Stanfield, the issue was whether DAS constituted a civil service commission for purposes of R.C.
R.C.
"Notwithstanding any other provisions of the Revised Code, the procedure described in this division is not subject to Chapter
Cleveland argues that this language pertains only to the protest meeting that is described and set forth in R.C.
However, the fact that the legislature chose to specifically state that such a protest meeting would not be subject to R.C. Chapter
"(A) The director of administrative services shall establishpolicy and procedure guidelines for contract documents in conjunction with the administration of public works contracts that the state or any institution supported in whole or in part by the state enters into for any project subject to sections
The fact that the legislature chose the words "policy and procedure guidelines" rather than "rule" and failed to otherwise specify that rules shall be promulgated pursuant to R.C. Chapter
Cleveland cites several cases wherein agencies themselves have designated items as "policies," "position papers" or "guidelines" when, in fact, such items were subject to R.C. Chapter
These cases are easily distinguishable from the instant action. In the case before us, this court is not reviewing a "policy" or a "guideline" labeled as such *393
by a state agency. Rather, this court is reviewing the statutory language chosen by the legislature. This court can only presume that the legislature chose to use the statutory language set forth in R.C.
For all the above reasons, this court cannot find that the trial court erred or abused its discretion in determining that Cleveland was not entitled to declaratory relief and/or that DAS had utilized illegal rules and had failed to legally promulgate rules and/or regulations to govern the determination of responsibility. Thus, we affirm the trial courts finding that R.C.
Cleveland also argues that R.C.
Initially this court notes that all legislative enactments enjoy a strong presumption of constitutionality. See State v.Collier (1991),
As previously noted, Cleveland never requested any further information from DAS once it received Kaitsa's March 5, 1996 letter. Had Cleveland found that the criteria listed therein were vague, or difficult to understand, one would expect Cleveland to have contacted DAS to specifically ask what it was that DAS was looking for. To the contrary, the transcript demonstrates that John Zeller, Cleveland's vice-president, who was responsible for submitting information to DAS in response to Kaitsa's March 5, 1996 letter, testified that he understood what type of information was being considered in determining responsibility. Nor was there any other evidence presented that any other bidder had difficulty understanding the criteria that were being utilized to determine responsibility. *394
Given the above testimony, and given the fact that Cleveland had the burden of proving, by clear and convincing evidence, that it was entitled to injunctive and/or declaratory relief because R.C.
In its tenth assignment of error, Cleveland argues that the trial court erred in finding that the protest meeting contemplated by R.C.
Initially this court notes that R.C.
To have a property interest in a benefit, such as a public works contract, a person clearly must have more than an abstract need or desire for it. One must have more than a unilateral expectation; rather, one must instead have a legitimate claim of entitlement to such a contract. See Dixon v. Brown (May 16, 1996), Cuyahoga App. No. 66931, unreported, 1996 WL 257443;Depas v. Highland Local School Dist. Bd. of Edn. (1977),
Clearly, contracts with state entities may give rise to a property right which is protected under the
If a charging party fails to demonstrate either of these, there is no property right to which due process rights attach. This court has previously stated that the trial court did not abuse its discretion in finding that Cleveland was not the lowest responsive and responsible bidder. A party that is a second- or third-place finisher in a determination of lowest and best bidder does not acquire a constitutionally protected property right. SeeMiami Valley Contrs., Inc. v. Oak Hill (1996),
Moreover, given the fact that OSU and/or DAS retained the right to reject all bids, this court is further persuaded that Cleveland did not have a property interest in the contract for the Fisher Project. Thus, even if the "protest meeting" language set forth in R.C.
Finally, Cleveland argues that the trial court erred in allowing intervenors-appellees OSU and Danis to intervene. Cleveland essentially argues that OSU and Danis did not have an interest in this action that was not already represented by DAS or that required representation by intervention of the parties. Cleveland argues that OSU and DAS are one and the same entity, and that OSU has no interest that is not already protected by DAS. This argument is rather interesting given the fact that Cleveland strongly objected to OSU's investigation of bidders on behalf of DAS. In any event, as the owner of the construction project and the entity that would use this project, OSU has an interest in this case. Courts consistently apply an abuse-of-discretion standard when reviewing trial courts rulings on motions to intervene, pursuant to Civ. R. 24. See Kourounis v. Raleigh (1993),
As to Danis, Cleveland argues that the issue in this case is whether Das's conduct, with respect to Cleveland, was arbitrary, capricious, and unreasonable so as to constitute an abuse of discretion. Therefore, Cleveland argues *396 that Danis has no issue before the court to be resolved. Cleveland argues that Danis has no standing to intervene because, in order for a party to have standing, there must be a justiciable controversy and the party seeking standing must have a sufficient stake in the outcome.
This court finds that Danis has a sufficient stake in the outcome of this case. Cleveland seeks the following relief: to be declared the lowest responsive and responsible bidder, and to be declared the recipient of this contract; and to have an injunction issued that would prohibit further execution of the general trades portion of the Fisher Project, which is currently being executed by Danis. Were this court to grant Cleveland the relief it seeks, Danis would obviously be affected. Given that Danis clearly has a stake in the outcome of this case, this court cannot find that the trial court erred or abused its discretion in permitting Danis to intervene in this action.
Moreover, this court cannot find that Cleveland has asserted any prejudice because OSU and Danis were added as parties to this action. Thus, any error that may have taken place by the addition of these parties would not be sufficient to constitute reversal in this case. Accordingly, appellants seventeenth assignment of error is overruled.
For all of the above reasons, appellants assignments of error are hereby overruled, and the judgment of the Franklin County Court of Common Pleas is hereby affirmed.
Judgment affirmed.
TYACK, P.J., and CLOSE, J., concur.