ORDER
This matter is before the Court on Defendant’s Motion for Summary Judgment [D.I. 44], Plaintiffs Response [D.I. 47] and Defendant’s Reply [D.I. 49], Oral arguments were held on the Motion on March 21, 2011. For the reasons laid out below, the Defendant’s Motion is GRANTED IN PART and DENIED IN PART.
I. Background
Cleveland Construction Company (“Plaintiff’) filed suit against Fireman’s Fund Insurance Company (“Defendant”) on April 15, 2009 in the Superior Court of Mecklenburg County, alleging breach of an insurance contract and negligence. The Defendant removed the action to this Court on May 15, 2009. [D.I. 1]. On November 5, 2009, the Court issued an order granting the Defendant’s Motion to Dismiss as to the Plaintiffs negligence claim and denying it as to the Plaintiffs breach of contract claim. [D.I. 21], The Plaintiff was granted leave to amend its complaint on January 25, 2010 to add claims of unfair and deceptive trade practices and bad faith. [D.I. 28].
The Defendant issued an all-risks insurance policy to Mecklenburg County (the “County”) providing builder’s risk insurance for the construction of the new Meek
The Plaintiff claims portions of its work and materials were damaged or stolen, resulting in losses to the Plaintiff and requiring Plaintiff to perform repair work under its contract with the County. Plaintiff submitted four claims to the Defendant under the all-risks policy. The first was to recover costs that the County charged the Plaintiff for roof re-work, which the County alleged was at least partially due to Plaintiffs poor workmanship. The second claim was for the costs of lost and stolen hardware belonging to Plaintiff. The third was to recover costs that the County assessed Plaintiff for cleaning stucco debris out of cooling towers. The fourth claim was to recover costs that Plaintiff incurred for repairing damage to drywall that Plaintiff installed.
Defendant asserts the Plaintiff failed to give proper notice of their claims under the policy. The Plaintiff requested a copy of the insurance policy from Robert Lutz, the senior project manager for the County, on April 10, 2006. [D.I. 44-8]. Plaintiff allegedly took no action for 16 months, and then sent a follow-up letter to the attorney for the County on August 8, 2007. [D.I. 44-10]. Plaintiff contends that it was sent the incorrect insurance policy in the first instance, and that the County had represented that they would file the Plaintiffs claims with the insurance company. [D.I. 44-11]. Plaintiff reported the claims to Marsh, Inc., the insurance broker handling claims for the County, on September 7, 2007. Plaintiffs documents in support of its claims were submitted on October 2, 2007 to the County. Defendant asserts the claim documents did not contain specific dates or causes of loss for the claims and that the Plaintiff did not cooperate fully in the investigation of the claim. Plaintiff counters that the Defendant never undertook even a preliminary investigation of the claim.
II. Summary Judgment Standard
“Under the Federal Rules of Civil Procedure, summary judgment shall be awarded ‘if the pleadings, depositions, answers to interrogatories, and admissions on file, together with the affidavits ... show that there is no genuine issue as to any material fact and that the moving party is entitled to judgment as a matter of law.’ ”
Bouchat v. Baltimore Ravens Football Club, Inc.,
III. Plaintiffs Claims
A. Breach of Contract
“For a breach of contract claim, a plaintiff must show a valid contract existed, and a breach of its terms.... When examining whether an insurance policy is breached, we begin with the well-settled principle that an insurance policy is a contract and its provisions govern the rights and duties of the parties thereto. The insured party has the burden of bringing itself within the insuring language of the policy.”
Nelson v. Hartford Underwriters Ins. Co.,
Plaintiff counters that an all-risk policy is to be read broadly. “Recovery will be allowed under a policy affording ‘all risks’ coverage for all losses of a fortuitous (external) nature not resulting from misconduct or fraud, unless the policy contains a specific provision expressly excluding loss from coverage. The term ‘all risks’ is not to be given a restrictive meaning.”
Avis v. Hartford Fire Ins. Co.,
The Defendant’s claim that the Plaintiff did not provide prompt notice is similarly a question more suited for a jury. The policy requires notice “as soon as practical after the loss or damage.” [D.I. 12-5]. Courts have enforced an “as soon as practical” notice provision to bar claims, considering it to be a condition precedent for coverage.
Yale v. National Indem. Co.,
The more difficult issue for the Plaintiffs breach of contract claim is the statute of limitations. The general statute of limitations for breach of contract actions in North Carolina is three years. N.C. Gen.Stat. § 1-52(1). The policy also requires that any legal action be brought within three years after the insured gains knowledge of the direct loss or damage. [D.I. 12-5], The issue of whether a cause of action is barred by the statute of limitations should be submitted to a jury “when the evidence is sufficient to support an inference that the limitations period has not expired.”
Piles v. Allstate Ins. Co.,
Plaintiffs argument that the action did not accrue until the Defendant breached the contract is not compelling. First, they rely on an inapposite case in which the court found that the statute of limitations prescribed in the insurance contract could not be less than that prescribed by law (there was a direct statutory violation).
F & D Company v. Aetna Ins. Co.,
The record and the parties are both unclear on the actual dates of loss. As discussed, Plaintiff submitted four claims to the Defendant. The first was to recover costs that the County charged the Plaintiff for roof re-work, which the County alleged was at least partially due to Plaintiffs poor workmanship. The second claim was for the costs of lost and stolen hardware belonging to Plaintiff. The third was to recover costs that the County assessed Plaintiff for cleaning stucco debris out of cooling towers. The fourth claim was to recover costs that Plaintiff incurred for repairing damage to drywall that Plaintiff installed.
As to the first claim of roof-rework, the record is clear that the Plaintiff received notice of the damage and the County’s intent to hold them responsible
As to the second claim for lost and stolen hardware, the hardware was allegedly stolen on or about August 20, 2006. See Exhibit 37 of the Master Deposition Exhibits, Tab 3, MARSH-01-00138. Defendant does not dispute this date. This claim is not barred by the statute of limitations.
As to the third claim for stucco debris, while it is clear from the record that much of the clean up occurred prior to April 15, 2006, the record does not demonstrate that the Plaintiff was charged for such rework, or on notice that they would be charged, until February 2007. When the damage to Cleveland Construction occurred is a matter best left for the jury. Summary judgment on the statute of limitations defense for this claim is denied without prejudice to the Defendant raising the defense at trial.
As to the fourth claim for drywall repairs, the record is clear that such repairs (and presumably the accompanying damage) occurred throughout the construction project. Plaintiff was clearly on notice of such repairs because they were actually performing them, and the record is clear that the County put the Plaintiff on notice that such repairs would be their responsibility as early as March 2, 2006. Any such damage that occurred prior to April 15, 2006 is barred by the statute of limitations. Thus, any claim arising from a Change Order Ticket or Time and Material Ticket dealing with the drywall damage and dated April 15, 2006 or earlier is barred by the statute of limitations. Any claim arising from a Change Order Ticket or Time and Material Ticket dated April 16, 2006 or later is allowed. Summary judgment on this claim as to the statute of limitations is thus granted in part and denied in part. Denial is without prejudice to Defendant raising the defense at trial.
In accordance with the foregoing analysis, summary judgment is DENIED IN PART and GRANTED IN PART as to the breach of contract claim.
B. Bad Faith
Bad faith against an insurance company on the refusal to settle a claim requires three elements.
Lovell v. Nationwide Mutual Ins. Co.,
Plaintiff urges the Court to go beyond the Defendant’s definition of insurance bad faith to settle and to rely on
Dailey v. Integon General Ins. Corp.
It is clear under the case law that punitive damages for a bad faith claim require some sort of aggravated conduct. The record indicates that the Defendant did not undertake an investigation of the claim; however, the Defendant’s conduct does not rise to the level of aggravated conduct seen throughout the relevant case law, and thus summary judgment for the bad faith claim is GRANTED. The Plaintiff has provided sufficient evidence to withstand summary judgment as to their unfair and deceptive trade practices claim.
C. Unfair and Deceptive Trade Practices
Plaintiff has produced evidence that although the Defendant received notice of the claim, the Defendant never investigated the claim. Violations of N.C. Gen.Stat. § 58-63-15 are violations of N.C. Gen.Stat. § 75-1.1 as a matter of law.
Gray v. North Carolina Ins. Underwriting Assoc.,
SO ORDERED.
