39 Ind. App. 420 | Ind. Ct. App. | 1906
Appellees, subcontractors, filed their complaint in three paragraphs against appellants, the Shutt Improvement Company, railway contractors, and the Cleveland, Cincinnati, Chicago & St. Louis Railway Company, and sought a judgment against the appellant Shntt Improvement Company for work and labor performed under a certain contract with appellees, and sought to enforce a mechanic’s lien, for the value of said work and labor, against the railroad company.
The court made a special finding of facts, which may be summarized as follows: Prior to October 10, 1903, said defendant railway company began the work of relocating its track in Dearborn county, Indiana. The defendant Shutt Improvement Company, a corporation engaged in the business of railroad construction, from October 1, 1903, to October 1, 1904, was engaged as general contractor, under a written contract with the defendant railway company, in the construction of a new roadbed upon the right of way of the defendant railway company, in Dearborn county, Indiana, and said contract included the excavation of a great number of yards of earth and the making of fills therewith, and included all excavations and fills hereinafter mentioned as contracted to be done by the plaintiffs herein between bridges No. 147 and No. 163. The plaintiffs, Scott and.Walker, partners doing business under the firm name and style of Scott & Walker, were engaged in the contracting business, and on October 10, 1903, they entered into a contract with the defendant Shutt Improvement Company to do the excavating that then remained undone between bridges No. 147 and No. 163. Said contract, which was in writing, was as follows:
“Cincinnati, Ohio, October 10, 1903.
Shutt Improvement Company,
Cincinnati, Ohio.
Gentlemen:
We propose to do the excavation for you on the work Bird is now on for twenty cents per cubic yard and one cent per cubic yard per each 100 feet from east side of creek, extra for all work that goes over Tanner’s*424 creek, you to finish and build the bridge over Tanner’s creek.
Any portion of the work which we are unable to complete by reason of uncompleted bridge piers, or present railroad tracks, or for any other cause over which we have no control, is to be omitted. In other 'words, our work is to be continuous and completed at once. Payment of ninety per cent to be made monthly, and balance on completion of contract.
Yours very truly,
Scott & Walker.
Accepted with the understanding that sufficient force is to be put on to complete by Eebruary 1, 1904.
Shutt Improvement Company, by E. W. Shutt.”
Scott & Walker began work under said contract on October 15, 1903, and there was then to be executed upon that part of the right of way covered by their contract an estimated yardage of 41,329. Bird, as subcontractor, had theretofore been engaged on the same work covered by the contract of the plaintiffs, working under a contract with the defendant Shutt Improvement Company. The estimated amount of excavation in the work originally was 53,681 cubic yards, and the estimated amount of yardage taken out by Bird was 12,352. The plaintiffs continued to work on said contract until November 26, 1903, when they ceased work thereon, and after April 1, 1904, the work was completed by the defendant Shutt Improvement Company. The plaintiffs did preparatory work on said contract by clearing, grubbing, digging out stumps, etc., by filling up gullies so that an excavating machine might pass over, and did work in sloping banks left unfinished by subcontractor Bird. Plaintiffs’ predecessor, Bird, the plaintiffs, and defendant Shutt Improvement Company used an excavator in said work and neither one of them at any time used a steam shovel. Plaintiffs temporarily ceased work under said contract on November 26, 1903, because the ground was so frozen that repeated efforts to work the excavator resulted
Appellants rely particularly upon the tenth and eleventh assignments of error, namely, that the court erred in overruling the separate motions of appellants for a new trial. Appellants especially contend that, from the evidence, the finding and ultimate facts contained in findings seventeen and nineteen are contrary to law, and are not supported by any evidence, and are contrary to all the evidence produced at the trial. Said findings are as follows: “17. The defendant Shutt Improvement Company was in default, under said contract, after December 20, 1903, in that it failed, on or before that day, to pay to the plaintiffs ninety per cent of the contract price for the work done by them during the month of November, preceding.” “19. The plaintiffs, after November 26, 1903, kept teams and equipment on the work, and were ready and willing to resume work at any time that the condition of the ground would permit, up to the time of the default of the defendant construction company hereinbefore found, and the plaintiffs were not theretofore in default.”
“In other words, our work is to be continuous and completed at once.”
This proposition was accepted by the following writing, signed by appellant improvement company:
“Accepted with the understanding that sufficient force is to be put on to complete by February 1, 1904.”
It is in evidence, also without dispute, that the general contract for the reconstruction of nineteen miles of the roadbed of what is known as the *Big Four railroad provided that the contractor was limited in time for the performance of the entire contract and was liable to a payment of $500 liquidated damages for failure to complete the contract on time. The general contract provided that the railroad company should have the right to take over completed
It does not clearly appear from the contract or contracts that the- parties intended to make time essential, but intention may be inferred from the acts of the parties. The evidence shows that after appellees had ceased work because of the frozen ground, appellant improvement company, with knowledge of the fact, promised to pay appellees what was due them, and afterwards it paid them a part thereof and talked about appellees’ taking another job of work from appellant improvement company, and, on February 29, appellant improvement company, by letter, informed appellees that frost was out of the ground and that work could be completed. Appellees frequently looked at and had the ground tested, and kept their equipments on the ground until about April 1, 1904. It does not appear that before the trial of the cause there was anything in the conduct of either of the parties to indicate that they considered time as of the essence of the contract. Was the Shutt Improvement Company in default in failing to pay ninety per cent
Judgment affirmed.