244 Pa. 616 | Pa. | 1914
Opinion by
In 1910 the defendant corporation erected a large byproduct coke plant; in the course of this work a contract was let to the plaintiff to build a pipe-line sewer over 10,000 feet in length, to carry discharged water from the plant to a nearby river; the sewer was laid in a trench and was constructed of terra cotta in sections of from two and one-half to three feet long, each section having one end in the form of a hub or bell, into which fitted the straight end of the connecting pipe, and the joints were to be filled with cement mortar; all materials were furnished by the defendant, and the plaintiff did the work pursuant to the terms of a written contract and certain plans and specifications, under the direction of the defendant’s engineer; the contract included, in addition to the sewer pipe line, the construction of an electric conduit and water line, all for $30,500; the conduit was abandoned under a mutual arrangement, with an allowance on that account, and there was no controversy over the water line; extra work was performed and charged for by the plaintiff; ninety per cent, was paid to the plaintiff on monthly estimates made by the engineer of the defendant; the suit at bar was to recover in assumpsit for the retained ten per cent.; the verdict favored the plaintiff, and the defendant has appealed from a judgment thereon.
The contract provided that the plaintiff’s work should be “first class in every respect for the purpose intended,” that “ninety per cent, of the value of the work performed by the contractor and accepted by the company” should be paid in monthly instalments, and the balance upon “final completion and acceptance,” thát “the work shall be understood to be accepted when the engineer shall certify in writing to the contractor that the said work in all its parts has been completed,” that “the word engineer” meant the chief engineer of the defendant company, under whose direction and control the work was to
The defendant company claimed that after the sewer pipe was completed it leaked at several points, due to bad workmanship of the plaintiff; but the latter, while admitting the defective condition of the pipe line, contended that it resulted from the defendant’s faulty engineering. The trial judge told the jury, that if they found the plaintiff had performed his work in accordance with instructions from the defendant’s engineer and that after inspection it had been accepted, the defendant company could not subsequently complain about its quality; but he left it for the jury to decide whether in point of fact the work had been so performed and accepted, telling them that if they believed from all the evidence in the case that it had, then such acceptance was sufficient to support the plaintiff’s averment of complete performance, and entitled him to recover; adding the further instruction, however, that if they found the work had not been accepted by the defendant, then it was necessary for the plaintiff specifically to prove substantial performance. The appellant contends tha,t these instructions and the court’s attitude during the trial, as indicated by the rulings on the evidence, show an erroneous construction of the written contract, further, that the evidence was not competent or sufficient to prove inspection and acceptance of the work by the defendant, and that, even if it was, under the pleadings, the jury should have been told that actual substantial performance had to be first shown before the plaintiff could recover, and that the proofs were not sufficient to establish that fact.
After reading the evidence and considering the ap
When the contract is read, it will be noticed that a final certificate from the engineer is not required; the provision upon the point simply states that “the work shall be understood to be accepted when the engineer shall certify......and the trial judge took the right
None of the authorities cited by either side rules the present case; in Erbeck v. Traction Co., 237 Pa. 121, chiefly relied upon by the appellant, the relevant provisions of the contract were quite different from those at bar; and since we-concur in the view that the present contract required no final certificate, the numerous authorities upon the point as to what will constitute a waiver of such a requirement need not be referred to. We conclude that the evidence did not present a departure from the pleadings, that the proofs were sufficient to sustain the verdict, and that the trial judge’s construe
It is not necessary to pass upon each of the forty assignments of error; a number of them complain of rulings on the evidence to which no exception was taken at the trial, and these are dismissed; none of the others shows reversible error, and they are overruled.
The judgment is affirmed.