Cleary v. Sohier

120 Mass. 210 | Mass. | 1876

By the Court.

The building having been destroyed by fire without fault of the plaintiff, so that he could not complete his contract, he may recover under a count for work done and materials furnished. Lord v. Wheeler, 1 Gray, 282. Wells v. Calnan, 107 Mass. 514, 517. Judgment for the plaintiff.