In the Matter of NANCY A. CLARKE, Appellant, v TOWN OF SAND LAKE ZONING BOARD OF APPEALS et al., Respondents.
Supreme Court, Appellate Division, Third Department, New York
860 NYS2d 646
Petitioner owns property in the Town of Sand Lake, Rensselaer County adjacent to lakefront property owned by respondents Richard P. Morris and Diane Y. Morris. The Morrises’ predecessor in interest obtained approval from the Town Planning Board, as required under local zoning provisions dealing with scenic preservation areas, for construction of a house that was closer to the lake than permitted by the setback requirements of the zoning ordinance. Their predecessor also obtained appropriate permits for the septic system. The Morrises purchased the property and transferred the permits. On June 8, 2006, upon a request for modification of the original conditions, the Planning Board approved the construction of a home 28 feet from the shoreline on one side and 35 feet from the shoreline on the other side, rather than the 100 feet in the setback requirements. The Morrises and their predecessor removed five dilapidated trailers from the property, some of which were located within five feet of the shoreline and had inadequate septic systems, but all of which could have remained as preexisting uses. On June 9, 2006, respondent Town of Sand Lake Code Enforcement Officer issued a building permit. Excavation began on July 14, 2006. After a modular home was situated on the property and all construction was complete, the Town issued a certificate of occupancy on October 20, 2006.
Petitioner commenced this
Statutes of limitations bar petitioner’s challenge to the building permit. State law requires an appeal of the issuance of a building permit to the ZBA within 60 days after filing (see
Nevertheless, petitioner’s challenge is barred by the doctrine of laches. Petitioner was aware that excavation and construction were occurring on the neighboring property in July 2006. She acknowledges that the Morrises informed her of the impending plans for a new house as early as May 2006. Despite this knowledge prior to and during the construction, petitioner did not appeal to the ZBA or seek a preliminary injunction until late October 2006—after the house was complete, the certificate of occupancy was issued and the Morrises had moved in (see Ughetta v Barile, 210 AD2d 562, 563 [1994], lv denied 85 NY2d 805 [1995]). Because petitioner delayed in seeking to protect her interests and offered no reason for not acting sooner, the
The ZBA’s determination was not arbitrary or capricious in its rejection of petitioner’s contention that the Morris house was built on a public road. While petitioner presented testimony from neighbors that the turnaround which extended from the mapped roadway onto the Morris property was used by the public and maintained by the Town so as to attain the status of a public highway by use (see
Cardona, P.J., Peters, Carpinello and Stein, JJ., concur.
Ordered that the judgment is affirmed, without costs.
