16 Haw. 53 | Haw. | 1904
OPINION OF THE COURT BY
This is an action of assumpsit, brought by the plaintiffs, Clark & Henery, against H. Hackfeld & Company, Limited, and Castle & Cooke, Limited, upon a written undertaking to guarantee the payment to the plaintiffs of the sum of $26,000 upon their completion of certain dredging work, and the acceptance of the same by the United. States Government. The United States, through the appropriate office of the Engineer Corps of the Army, had called for tenders for dredging a channel through the bar at the entrance to Pearl Harbor in the island of Oahu. The amount of the appropriation available not appearing to be sufficient to pay the cost of the undertaking, and it appearing that the opportunity to have this harbor opened might be lost for a long and indefinite period, if the appropriation then made available by Congress was not expended at that time, private parties interested in the work, took steps to induce bidders to undertake a contract. The directors of the Ewa Plantation Company, Limited, whose lands are situated in the Pearl Harbor basin, bordering upon, or accessible to the lagoon, passed the following resolutions:
“Whereas, the United States Government has advertised for tenders to open Pearl Harbor, and
“Whereas, Messrs. Clark & Henery, a reliable firm of contractors, will agree to put in a bid to the United States Government to complete this work as above for the sum of $94,000.00 provided they are guaranteed the additional $26,000.00
“Therefore Be It Resolved, that we, the Directors of the Ewa Plantation Company, do hereby pledge our Company to pay*56 its pro rata of the aforesaid $26,000.00, upon the completion and acceptance of the work by tbe United States Government, tbis Company’s pro rata to be determined according to tbe joint interests of all plantations tbat may join in tbe guarantee.”
Tbe directors of tbe Oabu Sugar Company, Limited, whose lands are similarly located, passed tbe following resolutions:
“Whereas, tbe United States Government has advertised for tenders to open Pearl Harbor, and
“Whereas, tbe appropriation available is only $94,000.00 and tbe necessary work to be performed to make tbe channel 200 feet wide at tbe bottom and 30 feet deep will require an expenditure of $120,000.00, or $26,000.00 in excess of tbe appropriation available, and
“Whereas, Messrs. Clark & Henery, a reliable firm of contractors, will agree to put in a bid to the United States Government to complete tbis work as above for tbe sum of $94,000.00 provided they are guaranteed tbe additional $26,000.00
“Therefore Be It Resolved, tbat we, tbe Directors of tbe Oabu Sugar Company, do hereby pledge our Company to pay its pro rata of tbe aforesaid $26,000.00, upon tbe completion and acceptance of tbe work by tbe United States Government, tbis company’s pro rata to be determined according to tbe joint interests of all plantations tbat may join in tbis guarantee.
“Provided tbis sum does not exceed of $26,000.00, viz: $8,666.66
“And Provided tbat tbe agents of tbe Company Messrs. H. Hackfeld & Company, Limited, are satisfied tbat the opening of tbe channel to Pearl Harbor will open tbe same to commerce.”
Tbe defendants thereupon entered into tbe following written obligation which they delivere dto tbe plaintiffs.
“Honolulu, H. I., Feb. 12th, 1901.
“Messrs. Clark & Henery,
City.
Dear Sirs:—
We, tbe undersigned, agents of tbe Ewa Plantation Co. and tbe Oabu Sugar Co., knowing that the directors of tbe above Companies have tbis day pledged tbe above companies to pay you $26,000.00 upon tbe opening of Pearl Harbor, by tbe completion by you and tbe acceptance by tbe United States Government of a channel into said Pearl Harbor of 200 ft. wide at
Yours very truly,
Castle & Cooke,
J. B. Atherton,
President.
H. Hackfeld & Co., Limited,
Paul Isenberg,
President.”
The plaintiffs, relying upon the foregoing assurances, put in a tender and obtained a contract for dredging a channel as aforesaid. This contract they faithfully carried out, to the satisfaction of the Federal officials, who accepted the work and paid the contract price. Demand was then made by the plaintiffs upon the defendants for the payment of said sum of $26,000. Not obtaining payment, action was. brought. The defendant H. Hackfeld & Company, Limited, answered, filing a general denial. The defendant Castle & Cooke, Limited, answered confessing judgment for, ind paying into court, two thirds of the sum sued for, with interest, costs and attorney’s fees, and disclaiming any release as to its joint liability for the balance. Jury was waived. The court, on the trial of the cause, found that all of the material allegations set forth in the complaint had been established by competent testimony, and entered judgment for the plaintiffs and against the defendants for the remaining one third of the $26,000 claimed, to wit: $8,666.66 with interest, costs and attorney’s fees. The defendant Hackfeld & Co. excepted to the findings as being contrary to law and the evidence, moved for a new trial, and upon its motion being overruled, brought the case here on bill of exceptions.
The numerous questions raised by the bill of exceptions were at the argument grouped by the defendant under three heads, which as set out in defendant’s brief are as follows:
1. Are H. Hackfeld & Company, Limited, liable under their contract of guaranty, assuming that all of the conditions thereof have been fulfilled?
2. Have the conditions in fact been fulfilled ?
1. The construction of the written obligation sued upon is at the foundation of plaintiffs’ case. Is it, as contended by defendant, a pure contract of guaranty, dependent for its validity upon the existence of another contract between the plaintiffs and the alleged principals, or is it an absolute and independent undertaking on the part of the defendants who signed it to make a definite payment on a contingency stated. As tending against the construction claimed by the defendant it should be observed that the undertaking in question is absolute in form. It is not even made conditional upon the default of the Ewa Plantation Company and the Oahu Sugar Company. It is a positive undertaking to “Guarantee said payment” upon the completion of the work under contemplation. The only contingency stated as a prerequisite to the liability of the defendants is that the work should be completed in a stated manner and to the satisfaction of certain persons. This is a very different obligation from that which would result if the letter sued on had set out a definite contract between the plantation companies and plaintiffs, or had referred to such a contract by terms sufficiently definite to iden-. tify it, and had then proceeded to guarantee that such contract was a good and enforceable contract, and that defendants would make good any loss resulting to plaintiff, up to the amount named, in case plaintiffs should fail to collect from the principals. We are not at liberty to so radically change the obligation signed by defendants as to incorporate into it the above terms and qualifications. Tet it would be necessary to read them into the contract in order to construe it in the manner contended for by defendant. To constitute the contract a guaranty of another prior contract between the principals and the plaintiffs there must be harmony as to the subject matter and amount involved. What contract could have existed between the plantations and the plaintiffs by virtue of the resolutions ? The resolutions show that in the case of the Ewa Plantation Company, Limited, authority was given to pledge said company for its pro rata of $26,000; and in the case of the Oahu Sugar Company,
One of the recognized tests to distinguish an absolute guaranty from a collateral one is whether the contract definitely guarantees a payment, as distinguished from a course of conduct by another; or that a written instrument is of a given character, or has a given value. The following are examples of undertakings held to be absolute:
“For value received we guarantee the within note until paid”, City Sav. Bank v. Hopson, 53 Conn. 453.
“We sign the above note for security for payment thereof,*60 which we hereby guarantee for a valuable consideration received,” Beardsley v. Hawes, 71 Conn. 39.
An example of a conditional guaranty is, a guaranty that a note is “good and collectible,” Bull v. Bliss, 30 Vt. 127. In Woodstock Bank v. Downer, 27 Vt. 539, the language'was “I guarantee the said note is good, and the payment of the same.” The court says: “Though the guaranty that the note was good, standing alone, might have been but a conditional promise, yet when it is added “and the payment of the same”, it evidently becomes an absolute promise. It is a promise that the makers will pay the note according to its tenor; no notice then that the makers had not paid the note was necessary.” In the case at bar it is payment which is guaranteed.
As to the usé of the word “guarantee” it may be observed that, while due weight must be given to the fact of its use, the word by itself is not conclusive as to the legal effect of the instrument. A qualified guaranty may be expressed without the use of the word “guaranty” at all. So on the other hand “guaranty” may be used to express an original undertaking. Two instances occur in the resolutions of the plantation companies in this case of non-technical use of the word guaranty. In the last preamble both companies set out that Messrs. Clark & Henery will agree to undertake the work, “provided they are guaranteed the additional $26,000.” and at the end of the first resolution the language used is, the “pro rata to be determined according to the joint interests of all plantations that may join in the guarantee.” Yet it is not contended that the plantations were acting as sureties of another. There is no reason to suppose that the word “guarantee” is used in the defendants’ contract in a sense different from that in which it is used in the resolutions. If used in the same sense the legal effect of defendants’ guaranty would be this: Defendants, after reciting certain facts of which they had knowledge (the fact that Oahu Sugar Company, Limited, and Ewa Plantation Company, Limited, had this day pledged themselves to pay plaintiffs $26,000 upon the opening of Pearl Harbor by the completion by plaintiffs and the accept
Is the contract sued on good in law as an independent contract ? It is objected first that no proof was made of the acceptance of the guaranty contained in defendants’ letter. It is doubtful if any notice is required in a case like the present even if the contract is held to be a guaranty. This is not such a case as would call for notice of acceptance by the custom of merchants, as when advances proposed to be made to a trader are guaranteed. In the case of unilateral contracts the performance of the act specified in the offer as the consideration makes the promise binding. Notice of acceptance is generally unnecessary. Harriman on Contracts, §149. In Bascom v. Smith, 164 Mass. 61, speaking of the case of the offer of a promise for an act the court says: “Ordinarily there is no occasion to notify the offerer of the acceptance of such an offer, for the doing of
In the- case above given as an example, the guaranty of a trader’s account, the reason for notice of acceptance is plain. The relations would be likely to extend over a long period of time and it would be only reasonable that the guarantor should know whether or not such an obligation has become a fact.
Notice of acceptance need not be proved by direct testimony but may be inferred. “It may have come from the plaintiffs, or the makers of the note, or from other source”, Woodstock Bank v. Downer, 27 Vt. 539. Knowledge that the offer has been accepted is equivalent to notice, when notice is necessary. Barnes Cycle Co. v. Reed, 91 Fed. 481. We think the evidence supports the finding upon this point.
It is next urged that no consideration has been shown for the contract. “Consideration involves the surrender of a legal right or the incurrence of a legal obligation”, Harriman, Cont. §106. It is not necessary that the consideration should be set out in the contract. Cummings v. Dennett, 26 Me. 397. It may be shown by the proofs to exist. We think the evidence amply justifies the finding of a consideration, which must have been found to support the decision of the court below. After the receipt of defendants’ letter, and in consequence of it, which is a fair inference from all the facts shown, plaintiffs incurred a very onerous legal obligation: to wit, they entered into a contract with the United States to dredge the bar at the entrance to Pearl Harbor in accordance with the specifications prepared by-the Army Engineer in charge. The facts recited in the preamble of the resolutions of the directors of the plantation companies, which defendants made a part of their contract, show that the work was undertaken by plaintiffs in consequence of the undertaking to pay the plaintiffs the sum of $26,000 in addition to
Defendants’ second main contention is that the conditions of the contract of February 12, have not been fulfilled in that it. has not been shown that the defendant H. Hackfeld & Company, Limited, was satisfied that the opening of the channel of Pearl Harbor would open the same to commerce, or that said corporation was satisfied when the work was completed that it did open the said harbor to commerce. The reference in defendants’ contract to the resolutions in the words “as per resolutions passed” renders the latter a part of the contract. The only question is. as to the satisfaction of the agents of the Oahu Sugar Company, Limited, Messrs. H. Hackfeld & Company, Limited. The other-provisions of the resolutions have been complied with. The satisfaction called for,' is not satisfaction with the manner in which the work might be performed; that matter was left to the Federal officials solely. There is little or no analogy therefore to-the case of a contract calling for the performance of work to the satisfaction of an architect. The satisfaction required is as to-
3. The view which we have taken of the nature of the defendants’ undertaking, and the construction to be placed on it, ren
The exceptions are overruled.