117 Wash. 506 | Wash. | 1921
The purpose of this action was to recover damages to real property, claimed to be due to the negligence of the defendant in improving one of its streets. The cause was tried to the court and a jury, and resulted in a verdict in favor of the plaintiffs in the sum of $400. Motions for judgment notwithstanding the verdict and, in the alternative, for a new trial were made and overruled. The defendant appeals.
The appellant city is a municipal corporation of the third class, one of the streets of which is Brawne avenue. The respondents own property which abuts upon this street. During the latter part of the year 1919, the appellant improved the street by grading and graveling, but the grade thereof was not made lower than the previously established grade. After the improvement was completed, the surface of the property of the respondents was from four to fifteen feet above the street level. In making the improvement the lateral support of the abutting property was removed except for a one to three slope; that is, for every three feet of elevation, the slope extended into the street one foot. The soil of the bank left exposed was of a clay formation and such as was likely to disintegrate and slide when subjected to the operation of the elements. During the latter part of January, 1920, a slide occurred which extended back on the lot from six to ten feet. There was evidence from which the jury could find that a one to three slope, taking into considera
After the slide occurred, and on February 17, 1920, the respondents filed a claim with the appellant for damages. It is first contended that this claim did not comply with the statutory requirement in that it was not filed in time and did not contain the “items of damages” claimed by the respondents. The statute, Rem. Code, §7998 (P. C. §665), among other things, requires that a claim shall be filed within- thirty days after the time when the damages occurred and shall contain the items of damages. The evidence, as appears from the facts already stated, shows that the slide occurred during the latter part of January, 1920, and that the claim was filed on February 17, 1920. There is no merit in the contention that the claim was not filed within the time.
As to the items of damage, the claim sets out in detail the description of the property, the making of the improvement, the character of the soil, the removal of the lateral support, the extent of the slide, and claims damages in the sum of $600. The damages claimed were those resulting to real property and were specified in one item. The claim was sufficient in this respect. Allbin v. Seattle, 98 Wash. 275, 167 Pac. 922.
Upon the merits, it is claimed that there was no showing that the appellant city had been guilty of negligence in making the improvement. The evidence shows that the bank was of a clay formation and, as one witness stated, was “treacherous material in lots of ways. ’ ’ The character of the soil was such that the bank was likely to slide when subjected to the operation of the elements, and this fact was known to the officers and agents of the appellant, or they were charged with knowledge thereof. It should be stated
The judgment will be affirmed.
Parker, C. J., Holcomb, Mackintosh, and Hovey, JJ., concur.