CJ Building Corp. v. TRAC-10CJ Building Corp. v. TRAC-10
This appeal arises from an order of the Hot Spring County Circuit Court entering judgment in favor of appellee, TRAC-10, against appellant, CJ Building Corporation (CJ), in the amount of $9,676.25 in attorneys’ fees and costs. On appeal, CJ argues that the circuit court erred in finding that TRAC-10 was the prevailing party under
CJ entered into a $1.4 million subcontract, dated October 29, 2002, with TRAC-10 to design, engineer, and construct four metal buildings for the Hot Spring County Power Plant (“project”). The scope of CJ’s work included design and installation of the heating, ventilation, and air conditioning (“HVAC”) systems for the buildings. After CJ completed its work and demobilized from the job site in September 2003, problems developed. TRAC-10 learned that CJ had not paid various suppliers or subcontractors, and the HVAC system in one building did not work properly. On February 3, 2004, CJ demanded a $56,126.77 retainage being held by TRAC-10, but TRAC-10 refused to pay because of the alleged deficiencies in CJ’s work.
On June 18, 2004, CJ filed a complaint against TRAC-10 for foreclosure of a materialman’s lien, asserting entitlement to the money owed on the subcontract. In its complaint, CJ named TRAC-10, Hot Spring Power Company, LLC, Hot Spring Power Company, LP, and Tractebel Project Development, Inc. as separate defendants. Specifically, CJ alleged that the Hot Spring Power Company was indebted to CJ in the sum of $63,287 for money owed for labor and materials. CJ commenced the action, claiming a first lien on the project. On July 8, 2004, TRAC-10 filed an answer, praying that CJ’s complaint be dismissed and requesting costs and expenses, including attorneys’ fees. Pursuant to
A bench trial was held on November 21, 2005. At the close of the evidence, the circuit court made the following ruling from the bench:
Well, obviously the dispute begins with the retainage amount of $56,126.77. Both sides have folly explained all the various joint exhibits. The court finds and agrees with the defendant’s position that the items on the board up there, the cleanup punch list, the National HVAC, the S&S Plumbing and the bond were expenses they incurred in getting the contract to par.
Therefore, those are deducted from the retainage leaving a balance of $13,927.21 that is owed to the plaintiff for which judgment is granted, plus interest and the maximum rate from today’s date.
All right, that’s the court’s judgment.
On December 8, 2005, the circuit court entered an order and ruled that TRAC-10 was contractually entitled to withhold $42,199.56 from the payment due to CJ.
Both parties filed timely motions for attorneys’ fees pursuant to
On February 22, 2006, the circuit court entered an order ruling that TRAC-10 was the prevailing party, denying CJ’s motion for attorneys’ fees, and granting TRAC-10’s motion for fees in part. The circuit court awarded TRAC-10 judgment against CJ for attorneys’ fees and costs in the amount of $9,676.25. On March 8, 2006, CJ filed a timely amended notice of appeal. From the February 22, 2006, order, CJ brings its appeal.
For its sole point on appeal, CJ argues that the circuit court abused its discretion by finding that TRAC-10 was the prevailing party. Specifically, CJ contends that, although it did not receive the $63,287 that it requested in its complaint, it nevertheless received $13,927.21 of the retainage. TRAC-10 responds, arguing that the case in controversy presented a breach of contract for which attorneys’ fees might be claimed pursuant to
We have said that attorneys’ fees are not allowed except where expressly provided for by statute. Harris v. City of Fort Smith,
Arkansas Code Annotated
In any civil action to recover on an open account, statement of account, account stated, promissory note, bill, negotiable instrument, or contract relating to the purchase or sale of goods, wares, or merchandise, or for labor or services, or breach of contract, unless otherwise provided by law or the contract which is the subject matter of the action, the prevailing party may be allowed a reasonable attorney’s fee to be assessed by the court and collected as costs.
Id. 1
To be the prevailing party under
CJ cites Marcum, supra, to support its argument that it is the prevailing party. In Marcum, there was a landlord and tenant dispute between the property owners, the Wengerts, and the lessee, the college fraternity, Phi Kappa Tau, and its officers, Marcum and Capo. The jury found that (1) the Wengerts were liable for conversion of the fraternity’s furniture and for breach of the lease; (2) the officers were not liable individually for any damage to the property; and (3) the fraternity was liable for minimal property damage. The fraternity and its officers moved for attorney’s fees as the prevailing parties, but the trial judge found that none of the parties were prevailing parties. On appeal, we reversed and remanded, explaining:
Clearly, the trial judge decided that no party was the “prevailing party” because they did not recover anywhere close to the amount of damages they were seeking. However, the trial court erred in basing [its] determination of who prevailed on the amount each party recovered under their claims. Instead, under Arkansas law, the prevailing party is determined by who comes out “on top” at the end of the case. This court provided the most recent discussion of the term “prevailing party” in Burnette v. Perkins & Associates,343 Ark. 237 ,33 S.W.3d 145 (2000), with regard to its application underArk. Code Ann. § 16-22-308 . While the issue in Burnette was whether there is a prevailing party in a case that is dismissed without prejudice before reaching the merits, the language regarding the term “prevailing party” is useful. The Burnette court determined that in order to be a “prevailing party,” one must prevail on the merits of the lawsuit. . . . Using this language, this court must analyze each cause of action and subsequent award by the jury to determine who was the prevailing party in the case.
Marcum,
Further, we have said that a successful defendant in a contract action may be considered a “prevailing party” for the purposes of
With this precedent in mind, we turn to the present case to determine the prevailing party. The dispute began with the retain-age amount of $56,126.77. CJ filed its complaint for foreclosure of the materialman’s lien, seeking $63,287 from Hot Spring Power Company, LP. TRAC-10 filed a bond, and in an agreed order dated July 30, 2004, CJ’s materialman’s lien claims were discharged, and Hot Spring Power Company was dismissed from the lawsuit. After conducting a bench trial, the circuit court “agree[d] with the defendant’s position” that TRAC-10 incurred expenses in “getting the contract to par[,]” but the circuit court deducted $42,195.56 from the retainage of $56,126.77 in arriving at the $13,927.21 judgment for CJ. On February 22, 2006, the circuit court ruled that TRAC-10 was the prevailing party and awarded TRAC-10 with $9,676.25 in attorneys’ fees and costs.
We agree with the circuit court’s rulings in its February 22, 2006, order finding that TRAC-10 was the prevailing party under
Affirmed.
Notes
Additionally, CJ claims to be a“successful party” under
When any contractor, subcontractor, or material supplier who has filed a lien, as provided for in this chapter, gives notice thereof to the debtor or owner of property which has been subjected to the lien in writing sent by registered or certified mail, and the claim has not been paid within twenty (20) days from the date of the mailing, and if the contractor, subcontractor, or material supplier is required to sue for the enforcement of his or her claim, the court shall allow the successful party in the action a reasonable attorney’s fee m addition to other relief to which he or she may be entitled.
Id.