224 Wis. 503 | Wis. | 1937
The following facts were established without dispute: On June 14, 1930, the defendant copartnership, Joe Volpano & Son, as “party of the first part,” and the defendant corporation, Glens Falls Indemnity Company, as “sureties and parties of the second part,” entered into three separate contracts with the plaintiff, the city of Wauwatosa, for the laying of water mains in that city on Moore, Eleventh,
“That if the said Joe Volpano & Son . . . shall well and truly perform each and every part of its contract with the city of Wauwatosa, Wisconsin, . . . for furnishing, delivering, and erecting . . . 641' 12" water main and appurtenances, provided for in said contract, and shall pay all claims for all work and labor performed and materials furnished therefor to every person or party entitled thereto for, or in, or about, or under, such contract . . . then this obligation shall be void, otherwise the same shall remain in full force and effect.”
In each of the contracts there were provisions, which (so far as here material) read :
That Joe Volpano & Son “agrees to pay in cash to . . . the city of Wauwatosa, within thirty days from the date of the award of this contract, for all water pipe, . . . and all appurtenances necessary and required as specified for the construction of a complete water main, the amount of which is to be included in the total cost of the work as herein provided.”
That Joe Volpano & Son and the defendant corporation agree that “in the event the same and every portion thereof is not complete as is herein specified, and according to the schedule of performance as noted in the specifications, and at the time herein specified,” the city of Wauwatosa “may take charge of the said work and complete the same, or cause the same to be completed at the charge, cost and expense of” Joe Volpano & Son and the defendant corporation “and for such purpose may thereafter employ any other person or persons as may be selected by said city to carry out and complete said contract, and for that purpose may retain from any money or certificates hereinafter provided to be issued, or paid for said improvement, so much as may be necessary to complete said work as herein provided.”
That Joe Volpano & Son agree “to accept in payment for said work, special improvement bonds, to be issued therefor by the” city’s officers under the Wisconsin statutes “excepting*506 so much of said work as shall be a charge against the public, for which city orders upon the city treasury shall be paid and delivered to said party of the first part.”
That the defendant corporation acknowledges “full, complete and satisfactory consideration to it . . . paid, before the ensealing and delivery thereof, for each of the covenants and agreements, by it . . . in any and every manner herein made, and for the faithful performance thereof, and” does “hereby agree to and with” the city that Joe Volpano & Son “shall well and duly perform all and singular each and every covenant, condition and agreement herein by said party made.”
That Joe Volpano & Son and the defendant corporation “hereby acknowledge themselves . . . jointly and severally, to be firmly bound” to the city “for the faithful and complete performance all and singular by” Joe Volpano & Son “of each and every covenant, condition and agreement herein contained or mentioned in the plans and specifications as to be kept and performed by said party, or by either of said parties of the first and second part.”
Between June 14, 1930, and July 11, 1930, the plaintiff furnished materials to Joe Volpano & Son for use in the work to be performed under each contract; and on July 11, 1930, plaintiff’s city engineer gave Joe Volpano & Son three statements for the material so furnished. Each statement was addressed to “Joe Volpano & Son,” and stated, “you are to pay to the city treasurer the total amount of this invoice within thirty (30) days after the award and signing of contract, which will be on or before July 15, 1930.” The total amounts on each invoice were:
$1,499.39 for materials delivered for the Moore Ave. work
746.04 “ “ “ “ “ 11th "
579.29 “ “ “ “ “ 12th “
$2,824.72 total for the three invoices
On August 15, 1930, the city engineer, in separate certified reports to the city’s board of public works as to each contract, stated that Joe Volpano,& Son had completed laying the
$ 781.74 by check $1,154.76 in Bonds on the Moore Ave. contract
612.09 “ 513.16 “ " “ 11th “
516.98 “ 470.40 “ “ “ 12th “
$1,910.81 “ $2,138.32
1,910.81
Grand Total $4,049.13
The copartnership signed receipts that the amounts paid under each contract were in full payment for laying the mains.
On January 2, 1931, the city engineer reported to the board of public works that the contractors had failed to pay the city for materials which it had furnished. On February 6, 1931, the city demanded payment by the defendant corporation, as surety, of $3,350.59, owing by Joe Volpano & Son for materials furnished by the city under the three contracts, and a similar subsequent contract between the city and Joe Volpano & Son and the defendant corporation. Subsequently, Joe Volpano & Son assigned assets to the city, which were applied on the amount owing for materials furnished by it under the four contracts, and that left an unpaid balance, upon which the plaintiff recovered judgment against the defendants for $1,367.20, with interest and costs.
When Joe Volpano & Son, on July 15, 1930, failed to pay the amounts then due to the city for the materials which it had delivered, the contractor breached the provision in each contract “to pay in cash to the city of Wauwatosa, within thirty (30) days from the date of the award of this contract, for all” materials required “for the construction of a complete water main.” Because of that breach, the city had the right, under the contract, to take charge of the work on July 15, 1930, and complete it at the expense of the contractor and its surety; and also the right to “retain from any money or certificates” to be issued or paid for the improvement described in the contract “so much as may be necessary to complete said work as” therein provided. And, because the city had that right and opportunity to thus obtain full payment of
As the city was authorized to retain all that was necessary to pay its claims for the materials furnished out of the checks and bonds, which it delivered to Joe Volpano & Son on August 25, 1930, and they exceeded, in the aggregate, the claims on which it is seeking to recover herein, the latter would have been fully satisfied and discharged, but for its neglect or failure to exercise its right, and thus take advantage of its opportunity to obtain payment. Its failure to do so, and thus perform its duty toward the defendant corporation, as surety, clearly resulted in releasing the latter, to the extent that it was prejudiced thereby, from its obligations to the city. As the amount of those checks and bonds was in excess of the city’s claims, it would seem, in the absence of proof to the contrary, that the defendant corporation was prejudiced by that delivery to an extent which exceeds the amount which the city seeks to recover herein. It contends, however, that the defendant corporation was not prejudiced by the delivery of those checks and bonds because the contractor was free to use the amounts realized thereon to discharge lienable labor and material-claims, which the surety would otherwise have been obligated to pay. That might be true if it had appeared that the proceeds of the checks and of the bonds (which were liquidated at ninety per cent of their face value) were used entirely to pay lienable claims for labor or materials furnished in performance of the contracts with the city of Wauwatosa, and under which the defendant corporation was liable for such claims. There is no evidence to that effect. It does appear that all claims for labor and materials required in performing those contracts were paid, with the exception of the city’s claim; but it does not appear
By the Court. — Judgment reversed as to the Glens Falls Indemnity Company, with directions t» enter judgment dismissing the complaint against that defendant.