9 Wash. 276 | Wash. | 1894
Lead Opinion
The opinion of the court was delivered by
— A motion was made to dismiss this appeal on the ground that all of the parties to the action had not been served with notice thereof, which is based upon the fact that a written notice was given which had not been served upon all of the parties entitled to service under the statute. It appears, however, that an oral notice of appeal was regularly given in open court after the rendition of judgment, and an appeal bond was given within the time required thereafter. Consequently the written notice was superfluous, and the motion is denied.
This action was begun October 5, 1893, by the city of Seattle against I. Liberman and others to determine the conflicting claims of fifty or more claimants to funds in the hands of the city devoted to a street improvement.
On September 12, 1892, the respondent, the city of Seattle, through its board of public works, entered into a contract in writing with the defendant, I. Liberman, whereby said Liberman agreed to grade to the established grade Broadway and De Forrest streets in said city from Yesler avenue to the south line of Oak street, and construct sidewalks on both sides thereof between said points, as ordered by an ordinance of said city, approved August 23, 1892. The city agreed (in the language of the contract) “to pay said Liberman for said improvement at the following rates, to wit: Earth work per cubic yard fourteen and one-half cents (14-J-); rock per cubic yard seventy-five cents (75c.); sidewalks, box drains and cross-walks, including nails and spikes, ten and twenty-five one-hundredths dollars (§10.25) for each thousand feet board measure of
In said contract it was further provided as follows:
‘ ‘All said payments shall be made by warrants payable only from the local improvement fund, district No. 34, of Seattle, provided for by said ordinance No. 2309, and not otherwise, and said party of the second part agrees to look solely to said fund for the payment for said improvement, except that so much of said contract price as is the cost of improvement of street crossings shall be paid by said city from its general road fund, to wit, the street fund.
“Warrants shall be issued as follows: On or before the fifteenth day of each month during the progress of the work warrants shall be issued for seventy (70) per cent, of the contract price of the estimated amount of said work returned by the city engineer as having been done during the preceding calendar month, and the balance of said contract price, being thirty (30) per cent, thereof, shall be retained to secure the payment of laborers who shall have performed work thereon, and material men who shall have furnished materials therefor; and all such laborers and material men shall, for thirty days after the work has been completed, have a lien upon said thirty (30) per cent, so reserved for labor done and materials furnished, which lien shall be senior to all other liens, whether by judgment, attachment or contract; and said improvement shall not be deemed completed until the board of public works shall have filed with the city clerk a statement signed by a majority of them, declaring the same has been completed. But neither said statement nor any acceptance of said work by said board shall prevent said city from thereafter making any claim for uncompleted or defective work when the same is discovered.
“In case no lien is claimed against said thirty (30) per cent, so reserved during said thirty days, and no uncompleted or defective work shall have been discovered and reported by the city engineer during said time, then warrants for said unpaid balance shall be issued at the expiration of said period; but in case notice of any such lien is given the city during this period, by or on behalf of any*279 person claiming such lien, or in case the city engineer shall report any claim of the city by reason of uncompleted or defective work, then the amount of all liens so. claimed shall be reserved by said city until final determination of such lien claims, and the cost of perfecting such uncompleted or defective work shall be retained until such uncompleted or defective work shall have been perfected or arranged to the satisfaction of the board of public works, unless otherwise ordained by the city council. No warrants shall be issued in any event for any part of said thirty (30) per cent, so reserved until said party of the second part shall have filed with the city comptroller a certificate signed by the city engineer stating that said period of thirty days has elapsed and that no uncompleted or defective work has been discovered for which said city makes claim.
‘ ‘ This contract is made and entered into with reference to the charter of said city as amended and now in force, and the ordinances of said city now in force; and the provisions of said charter and ordinances relating to the subject matter of this contract are hereby made a part hereof, with the same effect as if said provisions were herein incorporated and expressly set forth. ’ ’
Liberman entered upon the work in accordance with the contract, and after some delay completed it, and it was accepted by the board of public works on August 22, 1893.
The contractor’s compensation for the construction of sidewalks, box drains and cross-walks was to be measured by the quantity of lumber used, the cost of the nails, spikes and other material and all labor of preparing, laying down and completing the structures being included in the $10.25 per thousand feet of lumber used. In order to purchase the lumber needed to carry out his contract, Liberman gave to J. L. Taylor, one of appellants, the following order.
“Seattle, Wash., February, 25, 1893.
“eT. M. Carson, Esquire:
£ £ Please pay J. L. Taylor for lumber used in the improvement of Broadway, for sidewalks, box drains, culverts or*280 retaining walls, at the rate of seven dollars ($7.00) per thousand feet.
“Said lumber is estimated to amount to about 570,000 feet, which, at $7.00 per M. would be $3,990.00, and for this sum, more or less, according to the city engineer’s estimate this order is given in favor of J. L. Taylor; payments to be made according to the partial and final estimates of the city engineer as the work progresses.
‘ ‘ Order for three thousand nine hundred and ninety-nine dollars, more or less. I. Liberman. ’ ’
“I hereby release the above amount only from order given me by I. Liberman for the full amount due and to become due on Broadway. J. T. Nelson.”
This order was endorsed at the comptroller’s office as follows:
‘ ‘ I. Liberman to J. L. Taylor and release of amount of lumber at $7.00 per tho. by J. T. Nelson. Release by Nelson to Fischer & Macdonald. Filed March 11, 1893.”
There had been a previous order to J. T. Nelson, but on March 15, 1893, Nelson released all claims on the fund.
On the 20th day of March, A. D. 1893, Fischer & Macdonald caused to be filed with the city comptroller an order as follows:
“Seattle, Wash., March 20, 1893.
“Ji M. Carson, City Comptroller, City of Seattle:
“Please pay to Fischer & Macdonald all money now due or which may become due on Broadway and De Forrest street contract. I. Liberman. ’ ’
Indorsed: “Filed March 20, 1893,
“J. M. Carson, Compt.'n
Fischer & Macdonald were a wholesale grocery firm in. Seattle, and this order was given them as security for groceries and money furnished Liberman by them. The rights of appellant Taylor and respondents Fischer & Macdonald were fixed by these orders. Later on Taylor- assigned his claim to appellant Keeler. On September 1, 1893, Fischer & Macdonald filed the following instrument:
*281 “t/1 M. Carson, City Comptroller:
‘ ‘ For and in consideration of the sum of four thousand ($1,000) dollars, to me in hand paid by Fischer & Macdonald, I hereby sell, assign, transfer and set over to said Fischer & Macdonald all of that certain claim against the city of Seattle, a municipal corporation in King county, Washington, amounting to about fifty-six hundred ($5,600) dollars, being a balance due me upon a contract for the grading and side walking of Broadway and De Forrest streets in the said city of Seattle, together with all sums of money due me from said city, and authorize said Fischer & Macdonald to receive from said city said sum and receipt therefor. Witness my hand and- seal this 1st day of September, 1893. I. Liberman.”
During the progress of the work monthly estimates were returned by the city engineer allowing the contractor for seventy per cent, of the work completed in each month. In making payments to Keeler under said order, it seems some question was raised as to whether he was entitled to the full rate of $7 per thousand for lumber furnished each month out of the money coming to the contractor for that month, or whether he was to get but seventy per cent, of the $7 per thousand out of the partial payments as the work progressed.
The first construction put upon this order by the comptroller was to the effect that Keeler was entitled to only seventy per cent, of the $7 per thousand on the partial estimates, the remaining thirty per cent, of the price of the lumber as called for by the order to await the final estimate. Payment was made to Keeler in the month of March for the February estimate, and in the month of April for the March estimate, in accordance with this construction. In the month of May the comptroller departed from this construction of the order and assumed that Keeler was entitled to the full $7 per thousand for lumber delivered so long as there was sufficient money due the contractor
The full cost of the improvement under the contract, including earth work, rock work, clearing, grubbing, sidewalks and other structures, was $14,619.07. Under the contract and charter thirty per cent, of this sum was reserved “to secure the payment of laborers who shall have
The city claimed to be a party without interest and only asked that the fund be properly distributed. Taylor and Keeler claimed that under their order they were entitled all along to §7 per thousand feet for all lumber furnished; that there was furnished 520,092 feet amounting to §3,-640.64; that there became due to the contractor Liberman for such lumber §5,330.94; that the city had a right to retain therefrom only thirty per cent, of the amount due the contractor, leaving §3,731.66 due in moneyas the work progressed, which was more than sufficient to pay their claim; that by accepting and filing the order from Liberman to Taylor, and the assignment thereof from Taylor to Keeler, and paying money thereunder, the city had accepted said order and assignment, and was bound
The first question to be disposed of is the claim on the part of the respondents that the appellants should be held to have abandoned their appeal in consequence of a stipulation entered into after the appeal was taken. Such stipulation is as follows:
“It is hereby stipulated and agreed by and between all parties in the above entitled action, through their respective attorneys, that said city, the plaintiff, pay forthwith to*285 each person to whom any money is payable under the final judgment and decree rendered herein by the superior court seventy-two per cent, of the full amount payable to such persons, respectively, by the terms of said judgment and decree, said payment to be made either to said parties or to their attorneys, said sum to be paid as agreed by this stipulation amounting to $4,031.18, which sum is to be paid ratably from the street fund of said city and the local improvement fund district No. 34, as stated in the complaint. And it is further agreed that payment of said sum of $4,031.18 to the several persons aforesaid shall be deemed and held for all purposes to have been properly paid and disbursed by the plaintiff, so far as any liability of the plaintiff is concerned, and no further, and shall extinguish to that extent the liability of the plaintiff on the contract in the complaint mentioned.
“It is further stipulated and agreed that the appeal bond given by said defendants Taylor and Keeler shall serve also as the appeal bond for such other defendants as may join in said appeal in the manner provided by law and that no other bond shall be required by the other defendants so joining in said appeal. This stipulation shall be filed in duplicate in the superior court and in the supreme court, and the judgment of the supreme court, if any appeal be completed and decided, shall not in any event hold the plaintiff liable for moneys paid out under this stipulation. ’ ’
It appears that the amount stipulated was paid by the city to the various claimants, appellants and Fischer & Macdonald being included. We do not think this stipulation should be given the effect of depriving appellants of the benefit of their appeal. It clearly was not intended to have such an effect. It is apparent therefrom that the appellants at least understood their appeal should not be prejudiced thereby, and there was nothing upon the face of the stipulation to indicate that the respondents had any other intention. In fact, the stipulation provided for the maintenance of the appeal in stipulating as to the bond,
The city contends that it should not be held liable in any event beyond the amount of the fund devoted to the improvement in question, and that the controversy is really between appellants and Fischer & Macdonald, and if appellants are entitled to any more money they should recover the same from Fischer & Macdonald and not from the city, on the ground that if the city had not paid to Keeler the full amount he was entitled to under the order given to Taylor, it had paid the same to Fischer & Macdonald; that Fischer & Macdonald are parties to the suit, and are not shown to be insolvent, and that the court is in a position to do justice between all the parties. This last claim is here referred to as it is, in a measure, connected with the claim that the appellants have waived their appeal by entering into the stipulation in consequence of having consented thereunder that certain moneys should be paid to Fischer & Macdonald. The relief sought by appellants, however, was against the city only. It is not clearly apparent what the additional sum paid to Fischer & Macdonald under the stipulation was for, as it seems that the amount demanded by them was based upon several different claims. If the particular amounts to which Keeler was entitled, however, were paid to Fischer & Macdonald, such payments were made prior to this time, during the pendency of the work. The city was a party to this stipulation, and at the time it entered into it was fully advised of appellants’ claim in the premises, and is bound as much as any of the other parties thereby.
To hold that the stipulation would deprive appellants of the benefits of their appeal would be to hold that parties pending a suit cannot stipulate as to the disposition of a part of the subject matter over which there may be no controversy — and it is not certain that there was any contro
It appears that certain moneys are yet in the hands of the court, and it may be that the court will be in a position to protect the city in the premises, at least in a measure, by retaining any further moneys, if any, which might be due to Fischer & Macdonald, and were it not for the stipulation it might be that the city could recover the excess of moneys, if any, paid to them. We are of the opinion, however, that the city, having stipulated to pay Fischer & Macdonald the additional sum after the decree was rendered, cannot hereafter ask to recover the sum paid nor any part thereof.
The laborers’ liens and the amounts adjudged to them under the decree are not contested here, and consequently will remain as fixed by the lower court.
It is further contended by the city and Fischer & Macdonald that Taylor and Keeler were only entitled to seventy per cent, of the seven dollars per thousand feet for lumber called for by the order, and that this is apparent in consequence of the following language used in said order: ‘ ‘Payments to be made according to partial and final estimates of the city engineer as the work progresses. ’ ’ But we do not so construe it. Liberman was entitled under his con
It is further contended by the city that the comptroller had no authority to bind the city by an acceptance of this order, but conceding this we do not think it alters the situation.
“An order to pay out of a specified fund has always been held to be a valid assignment in equity and to fulfill all the requirements of the law.” Christmas v. Russell, 14 Wall. 69, 84.
And this holds good although the fund is not actually in being, if it will in due course of things arise from a contract or arrangement already entered into when the order was given. 3 Pomeroy, Eq. Jur., §1288.
Consequently this order to Taylor operated as an assignment of Liberman’s claim to the extent of seven dollars per thousand feet for the lumber furnished, due from the first payments as the work progressed, and the city had notice of it and was bound thereby, regardless of any acceptance by the comptroller.
It is also contended by the city that appellants are es-topped from making a further claim against the city in consequence of having accepted the payments as made without protest, at the time they were made. It is contended
The judgment is reversed, and the cause remanded with instructions to the lower court to enter a judgment in favor of appellant Keeler against the city for the balance of the moneys called for by the order in question, in
Dunbar, C. J., and Anders, J., concur.
Dissenting Opinion
(dissenting). — I am unable to agree with the conclusion to which the majority of the court have arrived, for the reason — First, That by joining in the stipulation for the distribution of the money, the appellants waived their right to further prosecute the appeal. I understand the rule to be that a party cannot accept any of the benefits of a judgment, and at the same time prosecute his appeal therefrom. This rule is so well settled that I deem it unnecessary to cite any authorities in support thereof. That the appellants derived certain benefits from the judgment of the court by virtue of the stipulation referred to, there can be no doubt, and I think that after signing the same they could not further prosecute their appeal.
Secondly, I am unable to agree with what is said by the majority as to the relations which were established between the city and appellants Keeler and Taylor, and the respondents Fischer & Macdonald, by reason of the orders given by the contractor. These orders were upon the comptroller of the city, and were in no manner acted upon by its common council. The comptroller is the agent of the city so far as his duties are provided by law or its ordi
It follows that if the city was bound at all it was by reason of the acceptance of such orders by the comptroller. But, since he was given no authority to do this, it is impossible to see how the city could be affected by his action in that regard. So far as he acted upon the orders, and made payment to the payees named therein, the contractor would doubtless be bound by reason of the doctrine of estoppel ; but such action on his part could not establish any liability on the part of the city. The opinion of the majority seems to concede that unless the city had assumed some contractual relation with appellants and said Fischer & Macdonald it would not be liable to them, if this is so, before they could recover they would have to show a binding contract upon the part of the city, and since the common council is the only body clothed with power to authorize such a contract, authority from it should have been shown before it could be assumed that any contract had been entered into. Under the provisions of the charter of the city of Seattle the comptroller certainly had no power to enter into contracts of this kind so as to bind the city, unless authorized by the- common council, and no such authority having been shown, his acts, even if sufficient to show an
There is another reason why the appellants should not have the relief which is awarded them by the opinion of the majority. The city practically proceeded in rem, against a certain definite sum of money which was in its possession, and asked the court to make distribution thereof. This being so, the subject matter of the suit was only such sum of money, and the court was without jurisdiction to award any other judgment than one disposing of such fund.
In my opinion the judgment should be affirmed.
Concurrence Opinion
(concurring). — I concur, with the reservation that the ground of recovery against the city is that the contract with Liberman segregated the cost of the lumber, and made it payable independently, as though it alone were the subject of the agreement.