CITY OF SAN DIEGO, a California municipal corporation, Plaintiff-Appellee, v. CHRISTINE TODD WHITMAN, an individual in her capacity as Administrator of the United States Environmental Protection Agency; UNITED STATES ENVIRONMENTAL PROTECTION AGENCY, Defendants-Appellants.
No. 00-56561
UNITED STATES COURT OF APPEALS FOR THE NINTH CIRCUIT
Argued and Submitted February 8, 2001. Filed March 13, 2001
242 F.3d 1097
Before: Harry Pregerson, William C. Canby, Jr., and David R. Thompson, Circuit Judges.
John R. Reese, McCutchen, Doyle, Brown & Enersen, Los Angeles, California, for the plaintiff-appellee.
Appeal from the United States District Court for the Southern District of California Rudi M. Brewster, Senior District Judge, Presiding. D.C. No. CV-00-00436-RMB
OPINION
THOMPSON, Circuit Judge:
The United States Environmental Protection Agency (“EPA“) appeals the district court‘s entry of a preliminary injunction in an action brought by the City of San Diego seeking judicial review, under the Administrative Procedure Act (“APA“),
The district court concluded that the EPA‘s letter was subject to judicial review under the APA as “final agency action.” The district court issued a preliminary injunction enjoining the EPA from enforcing a July 15, 2000 deadline for submission of the City‘s application for renewal of its modified NPDES permit until after the court conducted a bench trial and a decision in the case had become final following any appeal.
We have jurisdiction over the EPA‘s appeal of the district court‘s preliminary injunction pursuant to
BACKGROUND
The City of San Diego operates the Point Loma Wastewater Treatment Plant, a publicly-owned wastewater treatment facility that discharges pollutants into the Pacific Ocean. The Clean Water Act (“CWA“) prohibits such discharge except as authorized by a NPDES permit. See
The City wanted to obtain the benefits of modified secondary treatment requirements for its Point Loma Wastewater Treatment Plant, but failed to submit an application for a section 301(h) modified permit by the deadline specified in
Within the deadline imposed by OPRA, the City submitted an application for a section 301(h) modified permit. Pursuant to that application, on December 12, 1995, the EPA and the State of California issued a section 301(h) modified permit for the Point Loma facility, which incorporated the substantive requirements of OPRA.1 This permit was due to expire December 15, 2000. An application for renewal of the modified permit was to be filed six months before the permit expired (June 15, 2000).2 See
On December 13, 1999, the Mayor of the City of San Diego wrote to EPA Administrator Carol Browner “request[ing] your assistance regarding an issue impacting the City of San Diego‘s application for renewal of its National Pollutant Discharge Elimination System (“NPDES“) permit for its Point Loma Wastewater Treatment Plant under the Clean Water Act.” The Mayor stated:
By law, the City of San Diego must submit a renewal application for its NPDES permit for Point Loma by June of 2000 (
40 C.F.R. 122.46 ,125.59 ). . . .As detailed below, the City‘s position is that OPRA was intended to govern the reopening of the waiver application window only. Once a permit is granted, the renewals are to be governed not by OPRA, but by the waiver regulations applicable to all dischargers. Given the obvious significance of this issue, and its impact on the nature and consideration of the application, it must be resolved before the City can file its renewal application. . . .
The City is presently developing the information necessary to submit its renewal application for Point Loma. EPA‘s interpretation of OPRA is of obvious and primary importance to the effort, as it will dictate how the City must proceed towards renewal of its permit. In the absence of this determination, the City will be faced with the prospect of submitting dual and inconsistent renewal applications, which will not only be wasteful, but will also wreak havoc on the City‘s wastewater programmatic and financial planning efforts.
I encourage the City to submit its application for renewal of its 301(h) modified permit promptly and in accordance with OPRA. I assure you that EPA Region IX will give fair and timely consideration to the City‘s renewal application. In addition, like all other EPA actions on 301(h) modified permit applications, Region IX‘s action on the City‘s application will be subject to review by the Environmental Appeals Board (“EAB“) once Region IX makes its decision on the City‘s application for renewal of the 301(h) modified permit. If the City bases its application on its own interpretation of the applicability of OPRA conditions, the City could raise the OPRA issue in an appeal to the EAB. This letter, however, cannot constitute “final agency action” for purposes of obtaining judicial review. Final agency action occurs upon completion of the permit appeal process described above.
Instead of filing an application for renewal of its modified permit, the City filed the present action in district court. The City sought judicial review under the Administrative Procedure Act,
The EPA moved to dismiss the City‘s complaint for lack of subject matter jurisdiction. The EPA argued that its letter was not “final agency action;” that the dispute was not ripe for review; that the City had not exhausted its administrative remedies; and that
The district court denied the EPA‘s motion to dismiss for lack of subject matter jurisdiction. It determined that the EPA‘s letter “constitute[d] a final action reviewable in this court because it constitute[d] Defendants’ definitive position on the applicability of
The district court denied the City‘s motion for summary judgment on the ground that “there are material issues in dispute as to the correct interpretation of
The EPA appeals the district court‘s preliminary injunction. Its principal argument on appeal is that its letter did not constitute “final agency action” and thus the district court lacked subject matter jurisdiction.
DISCUSSION
A. Standard of Review
We review de novo the question of subject matter jurisdiction. See Ecology Ctr., Inc. v. United States Forest Serv., 192 F.3d 922, 924 (9th Cir. 1999).
B. Final Agency Action
The APA provides for judicial review of “final agency action.”
As a general matter, two conditions must be satisfied for agency action to be “final“: First, the action must mark the “consummation” of the agency‘s decisionmaking process—it must not be of a merely tentative or interlocutory nature. And second, the action must be one by which “rights or obligations have been determined,” or from which “legal consequences will flow.”
Id. at 177-78 (internal citations omitted).
The EPA‘s letter does not satisfy the first of the Bennett v. Spear requirements for final agency action—that the action mark the “‘consummation’ of the agency‘s decisionmaking process.” Id. The EPA‘s decision-making process on the City‘s application for renewal of its section 301(h) modified permit will not even begin until the City files its application. If and when the City is aggrieved by the EPA‘s decision regarding its application, the City‘s recourse is to appeal to the Environmental Appeals Board (“EAB“), as a prerequisite to review by this court. See
It is the EAB‘s decision that will constitute the “consummation of the agency‘s decision-making process.” This point is made in the EPA‘s letter itself: “This letter, however, cannot constitute ‘final agency action’ for purposes of obtaining judicial review. Final agency action occurs upon completion of the permit appeal process described above.”6 The letter described the appeal process and made it clear that the decision of the EAB would represent the consummation of the decision-making process on the issue of whether the City‘s application for renewal of its section 301(h) modified permit should be governed by OPRA or by the regulations applicable to all dischargers. Until the administrative appeal process is completed, judicial review is premature. See Sierra Club v. United States Nuclear Regulatory Comm‘n, 825 F.2d 1356, 1362 (9th Cir. 1987) (“We will not entertain a petition where pending administrative proceedings or further agency action might render the case moot and judicial review completely unnecessary.“). Cf. Ontario v. EPA, 912 F.2d 1525, 1532 (D.C. Cir. 1990) (agency action was final because it was “unambiguous and devoid of any suggestion that it might be subject to subsequent revision“); Ciba-Geigy Corp. v. EPA, 801 F.2d 430, 436-37 (D.C. Cir. 1986) (agency action was final because “[n]ot only did the statement of position admit of no ambiguity, but it gave no indication that it was subject to further agency consideration or possible modification.“) (internal citation omitted).7
The EPA‘s letter also fails to satisfy the second requirement of the Bennett v. Spear finality test—that the agency action impose an obligation, deny a right or fix some legal relationship. See Bennett, 520 U.S. at 178; Association of Am. Med. Colleges v. United States, 217 F.3d 770, 780-81 (9th Cir. 2000). The EPA‘s letter simply responds to the City‘s request for “assistance” on the issue of whether it can expect the EPA to apply OPRA‘s conditions to its application for renewal of its section 301(h) modified permit. The letter only “encourage[s]” the City to submit its application in accordance with the EPA‘s interpretation of OPRA and informs the City that it can raise the OPRA issue on appeal to the EAB if it chooses to complete the application in accordance with its own interpretation of OPRA.
C. Conclusion
Because the letter fails the finality test of Bennett v. Spear, it does not constitute “final agency action” required for judicial review under the Administrative Procedure Act,
Issuance of this court‘s mandate is stayed for thirty days from the filing of this opinion, and in the event any petition for rehearing is filed, issuance of the mandate is further stayed until a decision on all petitions for rehearing becomes final.
VACATED and REMANDED.
DAVID R. THOMPSON
UNITED STATES CIRCUIT JUDGE
