OPINION
Opinion by:
In this statutory condemnation case, the City of San Antonio appeals a judgment rendered in favor of Kopplow Development, Inc., arguing the evidence is legally insufficient to support the jury’s verdict awarding Kopplow remainder damages. Kopplow has also filed a cross-appeal in which it contends the trial court erred in excluding certain evidence. We affirm the trial court’s judgment in part, and reverse the judgment in part and render judgment that Kopplow take nothing on its claim for remainder damages.
Background
Kopplow Development owns approximately 18.451 acres of land at the southeast corner of the intersection of Culebra Road and NW Loop 410 in San Antonio. At or around the time Kopplow purchased the property, Kopplow also obtained a 16-foot wide non-exclusive utility easement and a 25-foot wide temporary construction easement from Southwest Research Institute, primarily to obtain gravity sewer service to its property.
As part of a public works project, the City of San Antonio planned and constructed the Regional Storm Water Detention Facility (the “Detention Facility” or “Detention Project”) for the Leon Creek watershed located south of Kopplow’s property. On January 16, 2004, the City obtained a 207.513-acre drainage easement from Southwest Research Institute to construct the Detention Facility. Kopplow’s 16-foot wide non-exclusive utility easement and the City’s drainage easement overlap. As part of the Detention Facility, the City constructed a concrete “inflow wall” across a portion of Southwest Research Institute’s property where the two parties’ easements overlap. In a ten-year storm, the inflow wall protects Kopplow’s property from flooding. The inflow wall is 735 feet high. The lowest top bank elevation on Kopplow’s property is 741 feet. The City constructed a 24-inch sleeve in the inflow wall to allow for extension of a future sewer line on Kopplow’s property.
Aside from the inflow wall, the Detention Project also consists of two other components: a spillway and a large berm, or *291 dam, located to the south of Kopplow’s property. The berm is located approximately 1700 feet south of Kopplow’s property, and is 748 feet at its maximum height. The City concedes that this berm may make Kopplow’s property, a quarter of which is located in the 100-year floodplain, susceptible to flooding in the future. The following diagram illustrates the locations of the various components of the Detention Facility and Kopplow’s property-
[[Image here]]
On May 27, 2004, Kopplow filed an inverse condemnation suit against the City alleging that the entire Detention Facility would subject Kopplow’s property to flooding in the event of a 100-year flood, and sought an injunction against the building of the inflow wall on Kopplow’s non-exclusive easement. On June 25, 2004, the City filed its answer and counterclaim for statutory condemnation. The counterclaim for statutory condemnation solely concerns the construction of the inflow wall upon the 16-foot non-exclusive easement.
The case proceeded to a jury trial in March 2009. At trial, testimony was presented regarding the impact of the inflow wall on Kopplow’s property. Robert Browning, the City’s chief storm water engineer, testified that the purpose of the Detention Project was to detain storm water and reduce flooding downstream. He stated that the project consists of three independent components: the inflow wall; the emergency overflow spillway; and the protection berm. When asked whether the inflow wall causes Kopplow’s property to flood in a 100-year flood, Browning answered, “No, the inflow wall does not impact the floodplain line on his property.” Browning added that although the project as a whole causes the level of the 100-year floodplain to be two feet higher on Kop-plow’s property, the inflow wall does not have anything to do with the potential flooding. He stated that the wall merely controls when the water enters the basin during a 100-year event. Browning stated that removing the inflow wall would have an impact on the downstream property, but not on Kopplow’s property. Browning testified that it is the large berm that causes water to go on Kopplow’s property during a 100-year flood, not the inflow wall.
Dennis Rion, a civil engineer whose firm assisted Kopplow in developing the land, testified that the purpose of the City’s Detention Facility is to reduce the water surface elevation and potential flooding downstream. He stated that the effect of the Detention Project on Kopplow’s property is an increase of 2.16 feet in elevation in a 100-year flood event. Rion stated there is “no doubt” that the increase of a 100-year storm on Kopplow’s property is caused by the City’s Detention Facility. On rebuttal, Rion was specifically asked what would happen if the City had not built the inflow wall. He answered, “[I]n a hundred year storm ... it’s intuitive to me that the water surface elevation on [Kop-plow’s] property wouldn’t change much if *292 that inflow wall was there or not, but it is a critical part of the detention pond.”
Lynn Eckmann, a real estate appraiser, testified that the value of the easement taken by the City (on which the inflow wall was built) was $4,600. She also stated that the inflow wall did not damage the remainder of Kopplow’s fee property. Eckmann elaborated that the 24-inch sleeve constructed in the inflow wall allowed Kop-plow to extend its sewer line and develop its 18 acres. Eckmann stated that the storm water facility as a whole increased the ultimate development floodplain on Kopplow’s property by 2.16 feet. She opined that if Kopplow hypothetically had to fill the remainder property with two feet of fill, damages in the amount of $408,400 would be warranted. She assigned zero damages to Kopplow’s remainder property based on the City’s taking of the easement. Kopplow’s appraiser, David Bolton, testified that the difference in value between the whole property before taking and the remainder after taking was $815,000.
The charge asked the jury three questions:
1. On June 25, 2004, what was the fair market value of the part taken?
2. Does the City’s use of the part taken proximately cause damages to the remainder?
3. On June 25, 2004, what was the difference between the fair market value of the remainder before the taking and the fair market value of the remainder after the taking?
During deliberations, the jury sent the following note to the trial court:
Do we have to consider the inflow wall only (inflow wall/part taken) when answering # 2; or do we consider the SW Regional Detention Facility as a whole? Or is this a question we (as the jury) have to answer.
The court instructed the jury to consider the evidence and instructions and to continue deliberating. The jury found that as of the date of the taking, the value of the part taken (iethe inflow wall built across Kopplow’s easement) was $4,600, that the use of the part taken was a proximate cause of damages to the remainder, and that the remainder had been damaged in the amount of $690,000. The trial court rendered judgment on the jury’s verdict. The City moved for a new trial and for judgment notwithstanding the verdict (JNOV); the trial court denied the motion for JNOV, and the motion for new trial was overruled by operation of law. Both parties appealed.
Discussion
The City brings four issues on appeal: (1) there is no evidence, or the evidence is factually insufficient, to support the jury’s affirmative answer to Question No. 2 because the evidence is undisputed that the City’s use of Kopplow’s easement causes no damages to Kopplow’s remainder; (2) because the evidence is undisputed that the City’s use of Kopplow’s easement causes no damages to Kopplow’s remainder, the jury’s answer to Question No. 3 can only be zero; (3) notwithstanding the first two issues, the Campbell 1 rule precludes remainder damages in the statutory condemnation case of Kopplow’s easement; and (4) any claim for damages based on a claim of inverse condemnation is premature. We first address whether the evidence at trial was sufficient to support the jury’s affirmative answer to Question No. 2.
Standard of Review: Legal and Factual Sufficiency
“The final test for legal sufficiency must always be whether the evidence at
*293
trial would enable reasonable and fair-minded people to reach the verdict under review.”
City of Keller v. Wilson,
Damages to Kopplow’s Remainder
The Texas Constitution provides: “No person’s property shall be taken, damaged or destroyed for or applied to public use without adequate compensation being made..». ” Tex. Const. art. I, § 17. When an entire tract of property is condemned, the landowner is entitled to payment of the local market value' of the property. Tex. Prop.Code Ann. § 21.042(b) (West Supp. 2010). When only a part of a person’s property is taken, however, the constitution requires adequate compensation both for the part taken and “severance damages” to the remainder.
State v. Schmidt,
If a portion of a tract or parcel of real property is condemned, the special commissioners shall determine the damage ■to the property owner after estimating the extent of the injury and benefit to the property owner, including the effect of the condemnation on the value of the property owner’s remaining property.
Tex. Prop.Code Ann. § 21.042(c) (West Supp.2010).
Severance damages are determined by “ascertaining the difference between the market value of the remainder of the tract immediately before the taking and the market value of the remainder of the tract immediately after the appropriation, taking into consideration the nature of the improvement, and the use to which the land taken is to be put.”
Schmidt,
(1) the land taken from the condemnee landowner was indispensable to the ... project;
(2) the land taken constituted a substantial (not inconsequential) part of the tract devoted to the project; and
(3) the damages resulting to the land not taken from the use of the land taken were inseparable from those to the same land flowing from the condemnor government’s use of its adjoining land in the ... project.
*294
Schmidt,
In Schmidt, the State took a strip of frontage property from the landowners as part of a project to modify Highway 183 into a controlled access highway. Id. at 770-71. The project called for Highway 183 to be elevated, thereby reducing the visibility and convenience of access to the landowners’ property. Id. at 771. The property owners claimed additional compensation for decreased market value of the remainder tract due to impaired visibility and accessibility. Id. at 772. The court denied recovery of severance damages, stating that the claimed diminution of value was due entirely to the State’s modifications to Highway 183 and not to the use of the strip taken from the landowners. Id. at 778. The court further emphasized that although the parts taken were indispensable to the entire project, they did not constitute a substantial part of the property devoted to the project, and the damages resulting to the remaining tracts were not inseparable from those caused by the taking. Id. at 779. Therefore, the Campbell rule prevented the landowners from recovering severance damages. Id. at 778-79.
Here, the City maintains that the undisputed evidence refutes Kopplow’s claim that the easement taken will cause the Kopplow property to flood an additional two feet in the event of a hypothetical 100-year flood. In support of its argument, the City relies on the testimony of Browning and Eckmann, who both unequivocally stated that the inflow wall did not cause damages to Kopplow’s remainder property, and the testimony of Rion, who stated that the water surface elevation on Kop-plow’s property would be the same in a 100-year storm whether or not the inflow wall was present. Both Browning and Rion stated that in a 100-year flood, the inflow wall would be underwater by ten feet, and would not hold any water in such an event. The City argues that in the face of such unequivocal evidence, the jury must have improperly considered the impact of the entire Detention Facility on Kopplow’s remainder property when answering Question No. 2, as evidenced by its note to the trial court.
In addition, the City contends that the
Campbell
rule applies, and therefore prevents Kopplow from recovering severance damages. The City concedes that the easement taken was indispensable to the Detention Facility project; however, it maintains that the inflow wall is not a substantial part of the property devoted to the project and Kopplow’s remainder damages are not inseparable from those caused by the taking.
See Schmidt,
Kopplow responds that it is entitled to severance damages because the condemnation caused special damage to its property that prevents development of the property without extensive reclamation. Kopplow contends that the instant situation is nearly identical to the facts in
State v. McCarley,
We find
McCarley
distinguishable, however, because in that case the evidence clearly showed that the part taken caused damages to the remainder property.
See id.
In contrast, after reviewing the evidence in this case, it is undisputed that the part taken did not cause damages to Kop-plow’s remainder property. Thus, we agree with the City that the evidence is legally insufficient to support the jury’s affirmative answer to Question No. 2.
See City of Keller,
We next address the City’s contention that Kopplow’s inverse condemnation claim is premature. Although Kopplow plead for damages for inverse condemnation, it now contends that a separate inverse action was not appropriate or necessary in light of the already pending statutory condemnation proceeding because it was entitled to recover for all reasonably foreseeable damages naturally flowing from the statutory condemnation action.
See City of La Grange v. Pieratt,
Kopplow responds that it did not seek damages merely for future flooding, but also for the inability to develop its remainder property absent an expensive reclamation project, which constituted an injury that accrued prior to trial. Kopplow further contends that it cannot bring a valid inverse condemnation claim in the future if the property at issue was the subject of a previous, proper statutory condemnation action.
See Dahl ex rel. Dahl v. State,
We agree that Kopplow’s inverse condemnation claim is premature. In order for flooding (and any reclamation associated with raising a floodplain) to amount to a physical taking, the flooding must be repeated. In
Howard v. City of Kerrville,
Further, we are not persuaded that Kopplow is barred from bringing a subsequent inverse condemnation claim. The
Dahl
court held that the appellants’ inverse condemnation claim was defective where the appellants’ pleadings demonstrated that their inverse condemnation claim covered the
identical
property lawfully condemned by the State in a previous proceeding.
Dahl,
In conclusion, we affirm the portion of the trial court’s judgment awarding Kop-plow $4,600 as compensation for the part taken by the City. We reverse the portion of the trial court’s judgment awarding Kopplow $690,000 for remainder damages, and render judgment that Kopplow take nothing on its claim for remainder damages.
Cross-Appeal
Kopplow presents two issues in its cross-appeal: (1) the trial court erred in excluding evidence of the value of the whole property before considering the benefit of Kopplow’s vested right to develop the property in accordance with its existing site development permit; and (2) the trial court erred in submitting a proximate cause question, because compensability of remainder property damages is a question of law for the court. Due to our holding that the evidence is legally insufficient to support the jury’s award of remainder damages, we conclude that any issue relat *297 ed to damages is moot. Because the City s use of the condemned property did not cause damages to Kopplow’s remainder, there can be no compensation for damage to the remainder. Kopplow’s issues on its cross-appeal are therefore overruled.
Conclusion
Based on the foregoing analysis, we affirm the portion of the trial court’s judgment awarding Kopplow $4,600 as compensation for the part taken by the City. We reverse the portion of the trial court’s judgment awarding Kopplow $690,000 for remainder damages, and render judgment that Kopplow take nothing on its claim for remainder damages.
Notes
.
Campbell v. United States,
. "In an inverse-condemnation suit, a property owner seeks compensation for a taking that has allegedly already occurred and requests just compensation from the government. The general elements of an inverse condemnation are: ‘(1) an intentional act of a government entity; (2) accomplished for a public purpose; (3) that damages or takes property from a private citizen.’ ”
State, Tex. Water Development Bd. v. Hearts Bluff Game Ranch, Inc.,
