42 A.D.2d 749 | N.Y. App. Div. | 1973
In an action inter alia to recover upon a surety bond, plaintiff appeals from an order of the Supreme Court, Westchester County, dated October 26, 1972, which denied its motion for summary judgment. Order affirmed, with $20 costs and disbursements. No opinion. Shapiro, J. (concurring). In this action to recover damages in the sum of $100,000 from defendant Public Service Mutual Insurance Company on its surety bond' and against the other defendants on an agreement to pay a stipulated charge of $200 per day for each day of delay in the construction and completion of certain buildings, the plaintiff, the City of Rye, appeals from an order which denied its motion for summary judgment. I agree that the order should be affirmed, but, in addition, I would dismiss the complaint. The nonsurety defendants, Marcel Weiss, Warwick Village, Inc., Milton Harbor Company and 720 Milton Road, Inc., were engaged in the construction of a group of 12 luxury co-operative apartment houses on a 12-acre tract in Rye based on building permit from the City of Rye received on January 31, 1966. In 1964 the developers applied to the Planning Commission of the City of Rye for approval of a variable height apartment development of three two-story shoreline buildings, three four-story buildings and underground garage and six two-story peripheral buildings. Such a development was permitted in an RA-4 zone, limited to a maximum height of 45 feet for all apartment buildings and an average height of 30 feet for all the buildings. The nonsurety defendants’ development was approved by a Planning Commission resolution on September 8, 1964 on condition that all work should be completed “in conformity with plans approved by the Planning Commission and in conformity with all applicable state, county and city regulations prior to the issuance of a certificate of occupancy.” On September 14, 1965 the Planning Commission modified its year-old resolution of approval to provide: “ No certificate of occupancy shall be issued for any building until all buildings are completed or until a bond sufficient to guarantee completion of the remainder of the buildings has been filed with the City.” Earlier, on June 18, 1965, the developers had applied for a building permit for nine two-story buildings and three four-story apartment buildings and underground garage. As above stated, a building permit was granted on January 31, 1966. Temporary certificates of occupancy were issued for three buildings, K, L and M, on April 14, 1967 and reissued on July 14, 1967 and October 14, 1967. Temporary certificates of occupancy were issued for the four-story buildings on December 29, 1967. Pinal certificates of occupancy were issued for all of these seven buildings on October 29, 1968. On the day before the issuance of the temporary certificates of occupancy on the four-story buildings, defendant Weiss signed a letter agreement which is the basis of the city’s action, in which, “in order to induce” the city "to deliver a temporary Certificate of Compliance with respect to ” the completed four-story buildings (collectively, the “Island and Garage Buildings”), he covenanted that he would deposit a surety bond of $100,000, to be held by the city as security for the commencement of construction of the remaining buildings, called the peripheral buildings; no later than April 1, 1970 or their completion within one year after that date. The agreement provided for the
On page 28 of its brief the appellant says: “ Obviously, although a bond is filed to secure faithful performance and a time is specified for the completion of the project, some penalty is required to secure compliance within the time specified. If this were not so, then builders or contractors could seriously obstruct and interfere with the use of highways and sidewalks by their excavations or constructions if they were permitted to delay, without any limitation or restriction, the completion of such projects. Whether or not the penalty be by a lump sum payment or a per diem charge, the purpose is the same, namely, to obtain compliance within the time specified.”
. The resolution of the Planning Commission of the city dated September 14, 1965 provided that no certificate of occupancy for any of the buildings should he issued until all the buildings were completed or until a bond sufficient to guarantee the completion of the buildings would be filed.
. The developers ratified the bond by filing a statement with the Attorney- " General, representing that a completion bond was to be posted by them, in accordance with the plaintiff’s condition.