245 F. 94 | 7th Cir. | 1917
(after stating the facts as above).
On the other hand, it must be borne in mind that the pipes were laid in water of considerable depth, and no test in the ‘method designated was made by the city until some three years had elapsed from the date when the city took over the work. It should also be borne in mind that the city had an engineer to supervise the work and a man constantly on the job to see that it was properly done and in accordance with the specifications. While the contract called for the air test, it did not provide that the test should be made by the plaintiff. Defendant was never precluded from making the test called for by the contract. It used the intake continuously from October, 1907, and was at all times in position to determine whether the completed work answered the calls of the contract. A test or examination made some two or three years after the intake was completed, and when imperfections might be traced to causes other than those attributable to the plaintiff, was not conclusive. Upon all the evidence, we are of the opinion that the motion to direct a verdict in defendant’s favor was properly denied.
“Tlie jury unquestionably have allowed plaintiff $1,100 tor burying the pipe. * * * It is evident, also, that the trial judge considered that it was an item concerning which the jury should find tor the plaintiff.”
The figures amply support this statement. The amount paid plaintiff while the work was in progress was $5,717.69. The city paid for repairs, etc., $3,873.59. The verdict of the jury was $3,482.31. These three items make a total of $13,073.59. Exclusive of the item of SI,~ 100 for the 800 feet of trench, the amount due plaintiff was $10,900. This would indicate an overpayment on this basis of $2,173.59.
However, plaintiff contends that the item of $3,873.59 should be reduced, because the evidence warranted the jury in finding that a considerable portion of this item was unreasonable. But if we take from this aggregate of sums actually paid out by defendant such sums as the plaintiff contends should be deducted, we are still unable to account
But plaintiff was entitled to recover, and was erroneously denied, interest on $2,382.31 from November 10, 1910, the date fixed in his bill, to the rendition of the judgment. The legal rate being 6 per cent, in Wisconsin, this interest was $771.38. The difference between the $1,-100 erroneously allowed by the jury and the interest item is $328.62.
It is therefore ordered that, if the defendant in error, within 20 days after this opinion 'is announced, file a remittitur for $328.62 in the office of the clerk of the District Court of the United States for the Eastern District of Wisconsin, and a certified copy thereof in the office of the clerk of this court, the judgment, less the amount so remitted, will be affirmed, with costs of this court to the plaintiff in error; but, if this is not done, judgment will be reversed, with costs to the plaintiff in error, and with directions to grant a new trial.
<gss>Por other cases see same topic & KEY-NUMBER in all Key-Numbered Digests & Indexes
<&s»For other cases see same topic & KEY-NUMBDR in all Key-Numbered Digests & Indexes