Opinion for the court filed by Circuit Judge KAREN LeCRAFT HENDERSON.
On November 13, 1997 the Federal Energy Regulatory Commission (Commission, FERC) issued a license order awarding the Oconto Falls (Wisconsin) hydroelectric project to N.E.W. Hydro (NEW).
See
I.
In 1977 the Federal Power Commission issued Wisconsin Electric Power Company (WEPCO) a license to operate a hydroelectric project (Oconto Falls Project) located on the Oconto River near Oconto Falls, Wisconsin, to expire Decern-
*1158
ber 31, 1993. In 1988 WEPCO filed a notice of intent to refile an application for relicensure but it failed to file its application before the December 31, 1991 deadline. Instead, WEPCO initiated discussions to sell the Oconto Falls Project to NEW. The sale was not completed by the December 31, 1991 deadline, however, and because no other party filed a notice of intent to file an application, the Oconto Falls Project became orphaned.
1
In February 1992 the Commission issued a public notice pursuant to Part I of the FPA, 16 U.S.C. §§ 791a-823a, to solicit license applications. At that time NEW informed the Commission of its intent to file an application. In May 1992 the City informed the Commission of its intent to file a competing application. In addition the City petitioned FERC for an order declaring that any license application for the Oconto Falls Project was subject to a municipal preference pursuant to section 7(a) of the FPA, 16 U.S.C. § 800(a).
2
The Commission ruled instead that section 15 of the FPA, 16 U.S.C. § 808, governs an orphan proceeding and therefore declared the municipal preference inapplicable.
3
This court subsequently affirmed the Commission’s decision.
See Oconto Falls v. FERC,
In the meantime WEPCO accepted NEW’s offer to acquire the Oconto Falls Project conditioned on NEW’s licensure by the Commission.
See
License Order,
Pursuant to section 10(j) of the FPA, the Commission must include as license conditions any recommendations from “State fish and wildlife agencies” unless the Commission determines that the recommended conditions are “inconsistent with the pur
*1159
poses and requirements” of the FPA or other laws. 16 U.S.C. § 80S(j)(l), (2). During the licensing process, WDNR recommended that the Oconto Falls Project licensee be required to reduce fish entrainment,
i.e.,
their passage into and through the turbines of the hydroelectric project. On November 13, 1997 the Commission issued an order granting NEW the Oconto Falls Project license.
See
II.
The court upholds FERC’s factual findings “if supported by substantial evidence” and upholds its order so long as it uses reasoned decision making.
Texaco, Inc. v. FERC,
A. Jurisdiction
The Commission challenges the court’s jurisdiction to review WDNR’s petition because it petitioned for review of the Rehearing Order instead of the License Order. Under section 313(b) of the FPA:
Any party to a proceeding under this chapter aggrieved by an order issued by the Commission in such proceeding may obtain a review of such order in the United States court of appeals ... by filing in such court, within sixty days after the order of the Commission upon the application for rehearing, a written petition praying that the order of the Commission be modified....
16 U.S.C. § 825Z(b). Section 313(b)’s plain language indicates that “the order of the Commission upon the application for rehearing” (rehearing order) which begins the sixty-day limitations period is different from the “order of the Commission” (“aggrieving” order) which the petitioner is to identify in its petition. Section 313(b) provides review of the “aggrieving” order but the rehearing order simply determines the accrual date of the sixty-day limitations period. It would make little sense to provide for relief from the “aggrieving” order but at the same time require the petitioner to specify the rehearing order in its petition.
4
Thus, in order to properly petition for review of a Commission order, section
*1160
313(b) requires a petitioner to identify the “aggrieving” order which in this case is the License Order. In its petition for review, however, WDNR specified only the Rehearing Order.
See
WDNR’s Petition for Review 1 (Jan. 11, 1999). Federal Rule of Appellate Procedure 15(a) requires that a petition for review of an agency order must “specify the order or part thereof to be reviewed.”
See also Entravision Holdings LLC v. FCC,
B. WDNR’s Petition
Section 10(j)(l) of the FPA requires the Commission to place a condition on a license “based on recommendations received pursuant to the Fish and Wildlife Coordination Act (16 U.S.C. § 661 et seq.) from ... State fish and wildlife agencies.” 16 U.S.C. § 803(j)(l) (Supp.1999). Section 10(j)(2) of the FPA further requires that:
Whenever the Commission believes that any recommendation referred to in paragraph (1) may be inconsistent with the purposes and requirements of this sub-chapter or other applicable law, the Commission and the agencies referred to in paragraph (1) shall attempt to resolve any such inconsistency, giving due weight to the recommendations, expertise, and statutory responsibilities of such agencies.
Id.
§ 803(j)(2). We have held that section 10(j) “requires the Commission to afford significant deference to fish protection recommendations of state and federal fish and wildlife agencies.”
Granholm ex rel. Michigan Dep’t of Natural Resources v. FERC,
The Commission derived its assumptions from WDNR’s studies of the fish populations of the Oconto Falls reservoir conducted in 1984 and 1989.
See, e.g.,
License Order,
Finally, WDNR argues that the Commission improperly failed to impose a barrier net requirement. According to WDNR, because the barrier net at a nearby project (Pine Project) cost only $50,000, the Commission erred in estimating the cost of a barrier net at the Oconto Falls Project at $540,000. The Commission, however, distinguished the Pine Project barrier net on several grounds: the Pine Project was located in a more sheltered area of the reservoir and in much shallower water; the type of net used at the Pine Project was unsuitable for the Oconto Falls Project; WEPCO’s analysis projected $540,000 for a barrier net for the Ocon-to Falls Project; and the Commission concluded that a fish protection device at the Oconto Falls Project would not have a significant beneficial effect on fishery resources. The Commission gave WDNR’s recommendation to construct a net barrier similar to the Pine Project’s barrier “due weight” but adequately distinguished the Oconto Falls Project’s needs based upon substantial evidence.
C. The City’s Petition
The City first contends that the Commission should have concluded that the City’s ability to comply with a license was superior to NEW’s ability under section 15(a)(2) of the FPA. Under section 15(a)(2), the Commission is required to consider (and explain such consideration in writing) each of the following:
(A) The plans and abilities of the applicant to comply with (i) the articles and conditions of any license issued to it and (ii) other applicable provisions of this subchapter.
(B) The plans of the applicant to manage, operate and maintain the project safely.
(C) The plans and abilities of the applicant to operate and maintain the project in a manner most likely to provide efficient and reliable electric service.
(D) The need of the applicant over the short and long term for the electricity generated by the project or projects to serve its customers....
(E) The existing and planned transmission services of the applicant, taking into consideration system reliability, costs, and other applicable economic and technical factors.
(F) Whether the plans of the applicant will be achieved, to the greatest extent possible, in a cost effective manner. .
(G) Such other factors as the Commission may deem relevant....
16 U.S.C. § 808(a)(2). Applying these factors, the Commission determined that there were no environmental or economic differences between NEW’s and the City’s applications.
*1162
The City contends that its license application was superior to NEW’s because of the City’s relationship to local agencies; its increased cost effectiveness; its ability to'finance the Oconto Falls Project at a lower interest rate; its technical experience in operating public water and sewer operations; and its closer headquarters.
5
The Commission, however, considered the City’s arguments. It determined that: proximity was not significant because many licensees are headquartered far from their projects with no bad effect; the Congress intended that municipal preference not apply in relicensing proceedings; NEW had experience with hydro-power projects which the City lacked, including operating the Oconto Falls Project since 1992; both applicants had emergency plans; and although the City’s projected cost effectiveness was 8.4 per cent greater than NEW’s, forecasts of economic benefits are considered comparable unless the difference is more than 20 per cent,
see City of Augusta et al.,
Also unconvincing is the City’s argument that the Commission erroneously applied a “first to file” tie-breaker to grant NEW the license. First, the City asserts that section 4.37(b) of the Commission’s regulations, 18 C.F.R. § 4.37(b), prohibits the Commission from using the “first to file” tie-breaker.
6
The Commission’s interpretation of its regulations is entitled to substantial deference.
See Associated Builders & Contractors, Inc. v. Herman,
*1163
Next, the City argues that the “first to file” tie-breaker is an impermissible retroactive policy change. According to the City, the Commission is bound by its prior decision “to deny any applicant or class of applicants a preference” because “the purpose of Congress was to place all applicants in a relicensing on an equal footing.” Order No. 513, FERC Stats, and Regs., ¶ 30,854, at 31,443-445 (1989) (finding rules of preference inappropriate in subsequent license proceedings). Order No. 513, however, does not address orphaned projects and does not dispense with tie-breakers in all section 15 proceedings. As we earlier determined, “Congress never envisioned the problem of orphaned projects. The statute is simply silent on the subject....”
Oconto Falls,
More plausible, but still unconvincing, the City argues that the “first to file” tie-breaker is unfairly prejudicial because the Commission’s delay in granting the City’s petition to obtain WEPCO’s ICP prevented it from filing its application before NEW filed. The City’s argument, however, assumes that it had the same right to WEPCO’s ICP as did NEW. In fact the City’s rights significantly differed from NEW’s. When NEW’s offer to buy the Oconto Falls Project fell through, WEPCO hired NEW to operate the project. NEW’s access to WEPCO’s ICP arose from its contractual relationship with WEPCO, a relationship which the City had every right to seek but failed' to pursue. As the Commission recognized, “the City was free to bid on the project, when [WEPCO] solicited offers.” License Order,
Not to be deterred, the City also attacks NEW’s agency relationship with WEPCO, arguing that WEPCO improperly acted as a co-applicant in violation of 18 C.F.R. § 16.25. While section 16.25 precludes a previous license holder such as WEPCO from filing a license application in response to the Commission’s notice soliciting applications, it does not address “co-applicant” status.
8
The Commission appropriately determined that neither the FPA nor its own regulations prohibited WEPCO from conditionally selling the Oconto Falls Project to NEW, from hiring NEW as its operating agent or from initially refusing to provide the City with the ICP. White an agency relationship may provide some advantages in filing a license application, it does not constitute a coappli-cant relationship in violation of section 16.25.
See
License Order,
For the foregoing reasons, we conclude that the Commission did not err in granting NEW a license to operate the Oconto Falls Project and, accordingly, both WDNR’s and the City’s petitions for review are
Denied.
Notes
. An orphaned project is a facility “for which the licensee files a notice of intent to apply for a relicense but neither the licensee nor any other applicant files a timely relicense application.”
Oconto Falls v. FERC,
. In issuing a preliminary permit or original license, "the Commission shall give preference to applications therefor by States and municipalities” so long as the competing applications are "equally well adapted ... to conserve and utilize in the public interest the water resources of the region.” 16 U.S.C. § 800(a).
.Section 15, as amended, “makes the municipal preference inapplicable in relicensing proceedings even when the licensee is not seeking to renew the license.”
Oconto Falls,
. Section 313(b) of the FPA also requires a party to petition for rehearing before it seeks judicial review. WDNR argues that to interpret section 313(b) to require a party to petition for review of the “aggrieving” order effectively makes the required rehearing order nonreviewable. This court has previously determined that a rehearing order does not constitute a new order unless it significantly modifies the original order.
See Southern Natural Gas Co. v. FERC,
. The Commission responds that the City waived its arguments regarding cost effectiveness, inclusion of campground costs and lower financing rate because the City failed to preserve them on rehearing. Although the City did not make these specific cost effectiveness challenges, it did challenge the Commission’s determination of the two applicants’ relative cost effectiveness.
See
City’s Rehearing Request 4-8. In making the cost effectiveness argument, the City preserved its specific arguments related to that challenge.
See City of Vernon v. FERC,
. 18 C.F.R. § 4.37(b) provides:
If two or more applications for ... licenses (not including applications for a new license under section 15 of the Federal Power Act) are filed ... the Commission will select between or among the applicants on the following bases:
[[Image here]]
(b) If both of two applicants are either a municipality or a state, or neither of them is a municipality or a state, and the plans of the applicants are equally well adapted to develop, conserve, and utilize in the public interest the water resources of the region, taking into consideration the ability of each applicant to carry out its plans, the Commission will favor the applicant with the earliest application acceptance date.
The Commission has held that section 4.37(b) applies where, as here, one applicant is a non-municipality and the other applicant is a municipality ineligible for the section 7(a) municipal preference.
See Idaho Water Resource Bd.,
. 18 C.F.R. § 4.37 is inapplicable to “new license [applications] under section 15 of the Federal Power Act.”
. When a project becomes orphaned, the Commission is required to publish a notice “soliciting applications from potential applicants other than the existing licensee.” 18 G.F.R. § 16.25.
