185 Ind. 626 | Ind. | 1916
— This appeal is from a judgment in an action in the court below for damages claimed by appellees against the city of Newcastle. The complaint alleges, in substance, that the appellees in the year 1907 contracted with appellant to build a portion of Race street in appellant city by grading and paving the same with brick, and by constructing cement sidewalks on either side thereof. That the appellees. proceeded to construct the street according to the contract but that before the completion of the same or during its construction, they were delayed by the failure of the city to remove certain telegraph, telephone or other poles that were in the street, and that, by reason of the delay caused by such failure on the part of appellant, appellees were compelled to delay the work until the summer of 1908, at which time they completed the work on the street, which was accepted by the city
To this complaint appellant filed a demurrer-which was overruled. Appellant then filed an answer in three paragraphs, the first being a general denial, the third a plea of payment and the second an answer which was in substance as follows: That the work and improvement of Race street in the town of Newcastle, Indiana, set out and described -in the complaint and the contract filed with the complaint and all proceedings had in relation to. such improvement were had and entered into under and by virtue of §265 of an act of the general assembly entitled “An act concerning municipal corporations,” approved March 6, 1905, and all acts amendatory and supplementary thereto, and the entire cost of the improvement was assessed as special benefits to the abutting and adjacent property owners, and the town of Newcastle assumed and agreed to pay no part of the cost of the improvement. That the appellees did not give any bond to the approval of the board- of trustees of the town to secure the performance of the contract set out in the complaint as provided by law, until July 7, 1908, and all acts, omissions and transactions set out and complained of by appellees had been consummated and had transpired prior to that date and the alleged causes of action sued on had all accrued prior to that date.
To this answer appellees replied in two paragraphs, the first a general denial, and the second, in substance, as follows: That in the month of July, 1907, the town of Newcastle, by proper, resolution, determined to improve the street 'in the town, known as East Race street, by grading and paving the same with brick, and cement curb and sidewalk. That under and pursuant to the
Appellant demurred to this reply, which demurrer was overruled. Following this ruling there was a trial by jury on the issues formed by general denial. The jury returned a verdict for appellees for the sum of $250 upon which the court rendered judgment for the appellees. Appellants filed a motion for a new trial setting up as causes therefor that: (1) the verdict of the jury was not sustained by the evidence; (2) the verdict of the jury was contrary to law; (3) the court committed certain errors in the trial of the said cause in giving instructions and in admitting evidence. This motion was overruled by the court. The rulings of the court on the demurrers to the complaint and reply and on the motion for a new trial are assigned as error in this court.
At the conclusion of the offer of evidence the court in its instructions to the jury directed them to disregard that portion of the complaint which claimed damages for the loss of interest paid on money borrowed to carry on the construction of the street, and for any loss occasioned by the fact that the appellees were unable to use the workmen hired and
It will be noted that the bond is to secure the performance of the contract, and to save the city harmless from the acts of the contractors. As alleged, the contract has been performed. That consideration is disposed of. There is no indication that there was any harm'done to the city by acts
It is unnecessary to enter further into the discussion of the questions raised by the alleged error in overruling the motion for a new trial since they are identical with those raised by the demurrers to the complaint and reply, except as above noted with respect to the correctness of the position of the court on the kind of relief asked for. There was no error committed by the court below as shown by the record, and the judgment is sustained.
Note. — Reported in 114 N. E. 221. Prevention of performance of contract, right to recover, 59 Am. St. 283. See also 28 Cyc 1058.