130 N.Y.S. 468 | N.Y. App. Div. | 1911
Lead Opinion
The defendant The Sicilian Asphalt Paving Company appeals from an interlocutory judgment overruling its demurrer to the complaint.
The complaint sets forth a Contract between the city of New York, and the appellant for the grading and repaving of the roadway of Forty-fifth street, from Tenth to Eleventh avenues in the city of New York. The work of repaving was completed and accepted on June 29, 1904. Thereafter a permit was issued to the defendant Consolidated Telegraph and Electrical Subway Company to open said street for the purpose of laying a trench across it. It is said, although not material to this appeal, that the subway company agreed to hold the city harmless from any injury that might occur to persons or property in consequence of said opening; that the appellant was notified of the issuance of- said permit and consented thereto, with the understanding that appellant would restore the pavement at the expense of the subway company when the latter' had refilled the trench. It is alleged that on the 30th of January, 190Í, the appellant was notified (by whom it is not stated) by a written notice to restore the pavement over the openings made by the subway company, but failed to do so, whereby the said pavement was allowed to be and remain in an open, defective' and dangerous condition from the time of the excavation up to. and after June 9, 190†. The complaint then set’s forth the particulars of an accident which happened to one Antonucci on June 9, 1901, in consequence of the defective condition of the pavement; his subsequent action against the city for damages; notice to the appellant to come in and defend; its refusal to do so, and the recovery of a judg
We consider that it is entirely clear that the provisions pf clause J, above quoted, do not sustain a cause of action upon the facts pleaded. That clause is limited to the precautions, to be taken by appellant, and the risks to be assumed by it during the performance of the work, which might well be held to cover work performed in making repairs, as well as in" originally laying the pavement, but cannot well be extended, by any fair construction of the language, to cover an assumption of risk while no work was in progress. If the plaintiff can recover at all it must be under that provision of clause M which requires the contractor (appellant) within five days after the receipt of notice so to do to restore the pavement over all openings made by corporations or plumbers for certain purposes, and over all trenches for which permits may be issued by the president.
The judgment appealed from must be reversed and the demurrer sustained, with costs and disbursements, with leave to plaintiff to amend its complaint within twenty days upon payment of costs in this court and the court below.
Dissenting Opinion
(dissenting):
I am unable to concur in the opinion of Mr. Justice Scott for the following reasons: Under the appellant’s contract it was obligated, after putting down the pavement, to maintain it in good condition for a period of five years. The maintenance included (a) the repairing of such natural defects as might appear, ■ e. g., cracks, depressions, etc., and (b) the restoring of the pavement after it had been removed with the consent of the city for certain specified purposes... The appellant was not obligated to perform any of the work speci fied under the maintenance clause until notified by the city to do so, and where the defect was caused by the removal of the pavement with the city’s permission, this had to be restored within five days after notice given. The complaint alleges that in January, 1901, the appellant was notified to restore the pavement where it had been removed by the defendant Consolidated Telegraph and Electrical Subway Company, and up to June 9, 1901, it failed to comply with the notice or do any part of the work required, or take any precautions whatever to prevent persons lawfully using the street being injured. On the day last named a person rightfully using the street was injured on account of the defect and subsequently recovered a judgment for $2,000 and costs against the city. The appellant had due notice of the commencement of the action and was afforded an opportunity to defend the same. This it refused to do, and the city, having paid the judgment, seeks in this, action-to recover from the appellant the amount paid.
It does not need the citation of authorities to sustain the proposition that where one, for a valuable consideration, undertakes to keep a public street in repair and fails to perform, he thereby makes' himself, liable for whatever damage the city may sustain by reason of his failure. The contract in suit provided that the appellant should keep the pavement ‘ ‘ in good condition ” for the period of five years and that “ during the period of maintenance the contractor shall within five (5) days after the receipt of notice so to do, restore the pavement over all openings made by corporations or plumbers for making new service connections, or repairing, renewing, or removing the same, and over all trenches made for carrying sewers, water or gas pipes or any other sub-surface pipes or conduits, for the building or laying of which permits may be issued by the President.” The complaint alleges that at the time stated thérein, at the special instance and request of the Consolidated Telegraph and Electrical Subway Company, the president of the borough of Manhattan issued and granted to it permission to open the pavement across the street covered by the appel
Ingraham, P. J., concurred.
Judgment reversed, with costs, and demurrer sustained, with costs, with leave to plaintiff to amend on payment of costs.