151 N.Y.S. 554 | N.Y. App. Div. | 1915
On the 24th day of June, 1909, the defendant De Marco entered into a contract with the plaintiff, pursuant to the provisions of which, in consideration of the privilege of the picking over ashes, street sweepings and rubbish delivered at dumps, incinerators and land fills in the boroughs of Manhattan and The Bronx for the period of three years from July 5, 1909, and reclaiming the part thereof of commercial value, he agreed, among other things, to pay to the plaintiff the sum of $1,717
This is an action on the bond, and it is brought against the principal and surety to recover a balance of the weekly payments which the former as the contractor agreed to make to the city. The issues in another action brought by the city against the contractor to recover damages for the same breaches of the contract as this action is predicated upon were by stipulation tried with the issues herein. In both actions the contractor interposed counterclaims, alike in each action, for damages claimed to have been sustained by him through alleged breaches of the contract on the part of the city. The court found in favor of the plaintiff in the other action, and adversely to the contractor on all issues presented by the counterclaim; and that decision has been reviewed concurrently with the one made in this action, and no prejudicial error having been found is to be affirmed, without opinion. (City of New York v. De Marco, 167 App. Div. 898.) The court on the same evidence, having properly decided in the other action that the contractor was not entitled to recover on any of the counterclaims, the disallowance of the same counterclaims in this action followed logically. We are of opinion, however, that the court erred in dismissing the complaint. It was dismissed as to the surety company on the theory that the surety was released by a modification of the agreement between the city and the contractor without its knowledge or consent. The city having recovered in the other action, the trial court was of opinion that there was no necessity of another judgment against the contractor for part of the same amount in this, and, therefore, also dismissed the complaint as to the contractor.
The contractor entered upon the discharge of his duties under the contract and exercised the privileges thereby granted, and no controversy arose between him and the city with respect to such duties or privileges, or with respect to the obligations of the city, until on or about the 24th day
The agreement upon which the trial court based the dismissal of the action against the surety company is a release executed by the contractor to the city, under date of September 30, 1911. It recites the making of the contract and the differences which arose between the parties thereunder as herein stated, and that they had agreed to compromise their respective claims to and including the date thereof by the contractor paying the city the sum of $858.50 per week from April 24, 1911, to June 20, 1911, and $525 per week from the latter date to September 30, 1911, for the privileges exercised by him under the contract “ without prejudice to and saving any further claim for damage which he,” the contractor, might sustain from “any continuance of the alleged breach of contract” by the city “after the first day of October, 1911,” and by the city accepting said sums “ in full settlement of all debts and money obligations claimed ” by it to have become due from the contractor, “ hut without prejudice to any claim ” which it might elect to make against
There is no force in the contention that, by thus compromising its claims against the contractor, the city acknowledged or admitted that it was guilty of a breach of the contract, and that the surety company was thereby released. The settlement was with respect to the contract in so far as it had been executed, and it was clearly provided that it was in no manner to be construed as affecting the rights of either party under the contract in so far as the contract remained executory. A settlement with respect to accrued claims under a contract, which does not release either party from performance of his obligations under the contract in so far as they remain executory does not discharge a surety from liability for a future breach. (See Cohn v. Spitzer, 145 App. Div. 104; Loos v. McCormack, 107 id. 8.) This action is to recover for alleged breaches of the contract accruing after the execution of the release. The city has made no settlement with the contractor with respect to the period for which it seeks to recover in this action. The surety company could be fully subrogated to the rights of the city against the contractor by satisfying the claim of the city made in this action. The court, therefore, erred in dismissing the complaint against the surety company; and it follows logically that it erred in dismissing the complaint against the principal, for the surety company is entitled to have the judgment run against the principal so that it may be subrogated to the rights of the city thereunder, without bringing another action.
The court, however, found the material facts, and it is unnecessary to order a new trial. Conclusions of law numbered first and third are, therefore, reversed, and conclusions
Ingraham, P. J., McLaughlin, Dowling and Hotchkiss, JJ., concurred.
Judgment reversed as to defendant surety company and judgment ordered for plaintiff, with costs, as directed in opinion. Order to be settled on notice.