148 N.Y.S. 436 | N.Y. App. Div. | 1914
This is an action against a street paving company and its sureties for damages resulting from an alleged failure of the paving company to comply with the terms of its contract with the city as to keeping the pavement laid by it in repair.
The contract was dated April 13,1903, and provided for paving with asphalt pavement Twenty-third street from Avenue A
The contract provided that the contractor should “maintain said pavement in good condition to the satisfaction of the President for the period of five years from the final completion and acceptance thereof,” and to carry out this provision it was further provided that the contractor should, when notified so to do by the president of the borough, repair and make good any defects which should develop “at any time during the period of five years from the date of the acceptance of the whole work. ”
The repairs, for the refusal to make which defendants are now sued, were required to be made wholly in these parts of the street in which the pavement had been completed in October, 1903, except possibly a small and negligible portion not affecting more than half a dozen square feet. The earliest notice to
The plaintiff’s contention is that the period of five years during which the contractor was bound to keep the pavement in repair did not begin to run until the whole work had been completed and formally accepted by the city and a final certificate given. If this contention be upheld, the result will be that as to ninety-seven per cent of the work done, the contractor’s obligation to keep the pavement in repair will be extended to six years through no fault of its own, hut solely in consequence of the act of the city in permitting á portion of the surface to he paved to be so occupied that the contractor could not complete its work. Such a result would be manifestly inequitable. In every contract of this nature there is an implied obligation on the part of the employer to give to his contractor access to the place at which the work is to be performed and reasonable facilities for performing it. (Mansfield v. N. Y. C. & H. R. R. R. Co., 102 N. Y. 205, 213; Del Genoveses. Third Ave. R. R. Co., 13 App. Div. 412; affd., 162 N. Y. 614.) The contractor in this case was hound by its contract to commence work when ordered so to do by the borough president, and to proceed to its completion promptly. This it did - so far as it was able, and its inability to completely finish it was due to the positive act of the city in granting permits for the occupation by another of a part of the street. As to the portion so occupied the contractor was powerless. It could not gain access except by the act of the city, and it not only refused to act, but continued to renew the permits for occupation by the builders.
The case is entirely similar to one recently decided in this court. (City of New York v. Interstate Paving Company, 151 App. Div. 114.) In that case as in this the contract was for the paving of a street; a part of the work was completed, hut the remainder could not be completed because another contractor was working there; the completed part was thrown open to public traffic, but final acceptance and the giving of the final certificate was postponed until the whole work had
It follows that the judgment and order appfealed from should be reversed. Both parties moved at the trial for the direction of a verdict, thus conceding, as indeed is obvious, that no disputed question of fact is involved. The complaint should, therefore, be dismissed, with costs to appellants in this court and the court below.
McLaughlin and Dowling, JJ., concurred; Ingraham, P. J., and Hotchkiss, J., dissented.
Judgment and order reversed, with costs, and complaint dismissed, with costs. Order to be settled on notice.