This is an appeal from a judgment dismissing an action for legal malpractice on the ground that it was barred by the statute of limitations. We hold that for two of the claims, there was not objective proof of damage to start the running of the statute of limitations until the jury verdict in the case in connection with which the malpractice allegedly occurred.
I. FACTS AND PROCEDURAL HISTORY
On May 11, 2000, the City of McCall (City) entered into a contract with St. Clair Contractors, Inc., (St. Clair) for the construction of a storage lagoon to hold treated effluent. The City also contracted with J-U-B Engineers, Inc. (J-U-B) to be the project engineer overseeing the work. The City was represented by Susan Buxton (Buxton) and William McCurdy (McCurdy), attorneys at law, throughout the construction project. For convenience, we will use the word “Attorneys” to refer to Buxton and McCurdy and their respective law firms of Smith, Buxton & Turke, Chartered, and Brassey, Wetherell, Crawford & Garrett, LLP, for
merly
St. Clair encountered various delays during the course of the construction, and the City concluded that St. Clair was not performing according to the terms of the contract. On the alleged advice of its Attorneys, the City terminated its contract with St. Clair on February 12, 2001.
Employers Insurance of Wausau (Wausau) had issued a performance bond for St. Clair, and it hired a replacement contractor to complete the project. The City concluded that the replacement contractor’s work was deficient. Again, on the alleged advice of its Attorneys, the City decided in June 2001 to withhold payments to Wausau for its replacement contractor and to hire another contractor.
On December 20, 2001, Wausau filed an action in federal district court to recover against the City for wrongfully demanding payment under the performance bond and withholding payments and against St. Clair pursuant to an indemnity agreement. The Attorneys represented the City throughout the litigation in district court. In January 2002, the City began incurring defense costs in the Wausau lawsuit. On April 12, 2002, St. Clair filed a cross-claim against the City. Allegedly on the advice, of its Attorneys, the City released J-U-B from any liability on July 25, 2002.
On May 4, 2004, the jury awarded a total of $4,955,096 in damages against the City. After the district court denied the City’s motion for a new trial, the City hired another attorney to prosecute an appeal, which was not successful.
On May 3, 2006, the City filed this action against the Attorneys. In its first amended complaint, the City alleged: (a) Count One, the Attorneys negligently advised the City to terminate its contract with St. Clair; (b) Count Two, the Attorneys negligently advised the City to release any of its claims against J-U-B arising from its role as project engineer for the construction project; (c) Count Three, the Attorneys negligently advised the City to withhold payments from Wausau and hire another contractor in place of Wausau’s replacement contractor; (d) Count Four, the Attorneys negligently failed to advise the City of a conflict of interest regarding their advice to release J-U-B from liability and to advise the City to seek advice from independent counsel; (e) Count Five, the Attorneys negligently advised the City not to accept Wausau’s offer to settle with the City for $500,000; and (f) Count Six, the Attorneys have been unjustly enriched in the amount of legal fees paid for their services in the litigation against the City.
The Attorneys moved for summary judgment on two grounds: the decision to sue the Attorneys was made by the city manager who lacked that authority and the City’s cause of action against the Attorneys was barred by the statute of limitations. The City responded that the city manager had implied authority to commence this litigation and that his action had subsequently been approved by the city council. The City also contended that the running of the statute of limitations had been tolled under the doctrine of equitable estoppel.
When deciding the motions for summary judgment, the district court addressed the allegations in the City’s first amended complaint. 1 The district court rejected the equitable estoppel claim and held that the claims against the Attorneys were barred by Idaho Code § 5-219(4), the applicable statute of limitations. Based upon its decision that all claims alleged in the first amended complaint were barred by the statute of limitations, the district court held it would not decide the issue of whether commencement of this litigation had not been properly approved by the city council.
II. ISSUES ON APPEAL
1. Did the district court err in holding that the City’s claims were barred by the statute of limitations?
2. Did the district court err in holding that the statute of limitations did not bar the Attorneys from asserting the doctrine of equitable estoppel as a defense?
3. Did the district court err in awarding the Attorneys attorney fees pursuant to Idaho Code § 12-120(3)?
4. If the City’s claims are not barred by the statute of limitations, should this Court uphold the district court on the alternative ground that the city manager did not have authority to commence this lawsuit and, if not, that the city council lacked authority to later ratify that act?
5. Are the Attorneys entitled to an award of attorney fees on appeal pursuant to Idaho Code § 12-120(3)?
III. ANALYSIS
A. Did the District Court Err in Holding that the City’s Claims Were Barred by the Statute of Limitations?
“An action to recover damages for ‘professional malpractice’ must be commenced within two years after the cause of action has accrued.”
Lapham v. Stewart,
This Court has held that a cause of action for professional negligence cannot accrue until some damage has occurred.
Stephens v. Steams,
Potential harm or an increase in the risk of damage is not sufficient to constitute some damage. For example, in
Parsons Packing, Inc. v. Masingill,
Likewise, in
Bonz v. Sudweeks,
In
Chicoine v. Bignall,
In
Chicoine,
an attorney represented Chicoine in a lawsuit brought against him and others that resulted in a jury verdict for damages against Chicoine in 1983. Chieoine’s attorney timely filed a motion for a judgment notwithstanding the verdict (J.N.O.V.). He later filed a motion for a new trial. The district court entered an order granting the motion for a J.N.O.V., but this Court reversed that order on appeal.
O’Neil v. Schuckardt,
In December 1989, Chicoine brought an action for malpractice against his attorney. Even though he had incurred attorney fees in defending the action after his attorney’s negligent act in failing to timely request a new trial, this Court held that “there was no objective proof of some actual damage to Chicoine until this Court reversed the order granting a new trial in
O’Neil II.”
This Court also applied the “objective proof of some damage” standard in
Fairway Development Co. v. Petersen, Moss, Olsen, Meacham & Carr,
The ease was remanded to the district court. After the court dismissed Fairway Development’s challenge to its assessments, Fairway Development appealed again. On February 23, 1988, this Court reversed the dismissal and remanded the case back for review of the appraisal method used by the county.
Fairway Development Co. v. Bannock County,
On remand, the district court did not reach the issue of the proper method of appraisal. Instead, on November 3, 1988, the court dismissed the claims on the ground that Fairway Development had failed to exhaust its administrative remedies years earlier.
On December 12, 1991, Fairway Development filed suit against Petersen. The case was dismissed based upon the statute of limitations, and Fairway Development appealed. This Court held that Fairway Development’s malpractice claim accrued on November 3, 1988. It stated, “Accordingly, we hold there is objective proof that Fairway Development suffered some actual damage when the district court dismissed Fairway Development’s claims on November 3, 1988.”
These cases stand for the following. The statute of limitations for professional malpractice does not begin to run until the plaintiff would have a cause of action against the professional.
Stephens v. Steams,
In addition, there must be objective proof that would support the existence of some actual damage.
Chicoine v. Bignall,
Counts One and Three of the First Amended Complaint. In Count One, the City alleged that the Attorneys negligently advised the City to terminate its contract with St. Clair, and in Count Three it alleged that the Attorneys negligently advised the City to withhold payments from Wausau and hire another contractor in place of Wausau’s replacement contractor. Relying primarily upon our holding in
Griggs v. Nash,
As acknowledged by the Chicoine Court, the Idaho Supreme Court has previously held that “some damage” occurs for the purposes of Idaho Code § 5-219(4) when attorney fees are paid to defend a lawsuit that resulted because of the alleged malpractice of a lawyer. As stated by the Chicoine Court, “[t]he existence of the damage [does] not depend on the outcome of the lawsuits, since only ‘some damage’ is necessary for the action to accrue under I.C. § 5-219(4).”
____The Plaintiffs were on notice from the pleadings filed by Wausau that Wausau was claiming that the actions that the Plaintiff took, allegedly based upon the legal advice from the Defendants, were actionable in a court of law. Once the payment of legal fees was incurred in the defense of Wausau’s claims the statute of limitations began to run. (Citations omitted.)
In
Bonz v. Sudweelcs,
Although we stated in
Chicoine
that “[t]he existence of the damage did not depend on the outcome of the lawsuits, since only ‘some damage’ is necessary for the action to accrue under I.C. § 5-219(4),” in that case the existence of some damage actually did depend upon the outcome of the lawsuit. We held, “Chicoine asserts that the action against Bignall did not accrue pursuant to I.C. § 5-219(4) until July 1989, when this Court reversed the trial court’s granting of a new trial. We agree.”
The circumstances of this lawsuit also differ from those in
Griggs v. Nash,
After the transaction closed, the Nashes did not make any payments on their loan. In a letter to them dated October 4,1984, EMSI blamed Trout for problems that had arisen, including failing to disclose information he had learned regarding the property while representing the Nashes on a prior sale that required a foreclosure. Trout had allegedly learned that the property appraised for only $31,800.
On July 30,1985, the Griggses sued EMSI, Van Gelder, and others, but not Trout. One of the claims asserted against EMSI and Van Gelder was that the property was worth only $31,800, that they had negligently failed to investigate its value, and that they had misrepresented the value as being $65,000. EMSI waited until September 23, 1987, before filing its third-party claim against Trout. This Court held that EMSI and Van Gelder’s claim against Trout accrued by at least September 9, 1985, because at that point they were incurring attorney fees while defending the Griggs’ lawsuit.
In Griggs, Trout was only retained to close the loan transaction; he was not representing EMSI or Van Gelder in any subsequent legal proceedings. Griggs was not a case, like Fairway Development and Chicoine, in which Trout was retained to represent EMSI and Van Gelder in an ongoing legal dispute during which he allegedly gave negligent advice.
The mere fact that Wausau and St. Clair commenced litigation against the City would not have given the City a cause of action against its Attorneys. The giving of legal advice often carries with it the risk of litigation. The fact that the City was sued does not, by itself, constitute a breach of duty by the City’s Attorneys. Had the City attempted to sue its Attorneys because it had been sued after following their advice, the City would not necessarily have been entitled to recover. For example, it would be difficult to conceive of a situation in which the City could have recovered on a malpractice claim against its Attorneys had the City prevailed in the litigation. Even when an attorney is negligent, that breach of duty may not be a proximate cause of the resulting damage
Under the circumstances of this case, the existence or effect of any alleged negligence on the part of the City’s Attorneys regarding their legal advice and strategy depended upon the outcome of the litigation against the City by Wausau and St. Clair. There would not be objective proof of actual damage until that occurred.
Fairway Development Co. v. Petersen, Moss, Olsen, Meacham & Carr,
Therefore, the district court erred by granting summary judgment as to Counts One and Three. However, this analysis only applies to Counts One and Three of the first amended complaint.
Counts Two and Four of the First Amended Complaint. In Count Two, the City alleged that its attorneys negligently advised the City to release any of its claims against J-U-B arising from its role as project engineer for the construction project, and in Count Four, the City alleged that the Attorneys negligently failed to advise the City of a conflict of interest regarding their advice to release J-U-B from liability and to advise the City to seek advice from independent counsel. On July 25, 2002, the City released J-U-B from liability. That was the date on which the City lost its opportunity to recover against J-U-B, and the date on which the damage occurred if the Attorneys negligently advised the City to release J-UB from liability or breached a duty by failing to advise the City to seek advice from independent counsel before releasing J-U-B.
Treasure Valley Bank v. Killen & Pittenger, P.A.,
Count Five of the First Amended Complaint. In Count Five, the City alleged that the Attorneys negligently advised the City not to accept Wausau’s offer to settle with the City for $500,000. When the offer was rejected in September 2003, the City lost its opportunity to settle this case for that amount. That was the date on which the City would have suffered objectively ascertainable damage from the alleged negligence of its attorneys in advising it to reject that offer.
Treasure Valley Bank v. Killen & Pittenger, P.A,
Count Six of the First Amended Complaint. In Count Six, the City alleged that the Attorneys have been unjustly enriched in the amount of legal fees paid for their services in the litigation against the City. The district court dismissed this claim, stating, “Although styled as a claim of unjust enrichment, Count Six is clearly premised upon legal malpractice.” The City has not challenged that holding on appeal. Therefore, we uphold the district court’s ruling that the doctrine of unjust enrichment does not provide the City with an independent cause of action under the facts of this case.
B. Did the District Court Err in Holding that the Doctrine of Equitable Estoppel Did Not Bar the Attorneys from Asserting the Statute of Limitations as a Defense?
“The only non-statutory bar to a statute of limitation defense in Idaho is the doctrine of equitable estoppel.”
J.R. Simplot Co. v. Chemetics Int’l, Inc.,
(1) a false representation or concealment of a material fact with actual or constructive knowledge of the truth; (2) that the party asserting estoppel did not know or could not discover the truth; (3) that the false representation or concealment was made with the intent that it be relied upon; and (4) that the person to whom the representation was made, or from whom the facts were concealed, relied and acted upon the representation or concealment to his prejudice.
Id.
Equitable estoppel does not eliminate, toll, or extend the statute of limitations.
Ferro v. Society of Saint Pius X,
The district court held that the City failed to produce evidence supporting its claim of equitable estoppel. The court stated as follows:
The Court finds there is neither evidence in the record nor any proffered by the Plaintiff suggesting the Defendants in this case made a false representation or concealed a material fact that the Defendants had actual or constructive knowledge of being untrue. There is no evidence in this case warranting the inference that the Defendants knew the Plaintiff was in breach of contract with St. Clair. Put differently, there simply is no evidence establishing or permitting the Court to reasonably infer that the Defendants concealed any material facts or made any false representations which lulled the Plaintiff into inaction during the statutory period. Additionally, there is no evidence before the Court establishing the Plaintiff relied on any representations by the Defendants in waiting to file this action.
On appeal, the City does not point to evidence showing that the Attorneys made a false representation or concealed a material fact with actual or constructive knowledge of the truth. It argues the district court should have inferred that the Attorneys did so. According to the City, attorneys are presumed to know the law. If an attorney errs in advising a client as to the applicable law or in predicting the strength of the opposing side’s ease, we should infer that the attorney did so knowing that such advice was false.
“Generally, a statement about a future event does not constitute a misrepresentation. A misrepresentation must be as to a past or existing fact.”
Ferro,
C. Did the District Court Err in Awarding the Attorneys attorney fees pursuant to Idaho Code § 12-120(3)?
The district court awarded the Attorneys attorney fees pursuant to that portion of Idaho Code § 12-120(3), which provides, “In any civil action to recover ... in any commercial transaction unless otherwise provided by law, the prevailing party shall be allowed a reasonable attorney’s fee to be set by the court, to be taxed and collected as costs.” The statute defines a “commercial transaction” as “all transactions except transactions for personal or household purposes.” Based upon our recent opinion in
Blimka v. My Web Wholesaler, LLC,
In
Fuller v. Wolters,
The first portion of Idaho Code § 12-120(3) only provides for the awarding of attorney fees in actions to recover on what would be contract actions. It begins, “In any civil action to recover on an open account, account stated, note, bill, negotiable instrument, guaranty, or contract relating to the purchase or sale of goods, wares, merchandise, or services____” However, the latter portion of the statute does not contain any such limitation. It mandates the awarding of a reasonable attorney’s fee to the prevailing party “in any commercial transaction.” The latter portion of the statute is not limited to contract actions. It “does not require that there be a contract between the parties before the statute is applied; the statute only requires that there be a commercial transaction.”
Great Plains Equip., Inc. v. Northwest Pipeline Corp.,
From time to time the Court has denied fees under I.C. § 12-120(3) on the commercial transaction ground either because the claim sounded in tort or because no contract was involved. The commercial transaction ground in I.C. § 12-120(3) neither prohibits a fee award for a commercial transaction that involves tortious conduct, nor does it require that there be a contract. Any previous holdings to the contrary are overruled.
The district court correctly held that following our decision in Blimka, Fuller v. Wolters is overruled.
D. If the City’s Claims Are Not Barred by the Statute of Limitations, Should this Court Uphold the District Court on the Alternative Ground that the City Manager Did Not Have Authority to Commence this Lawsuit and, if not, that the City Council Lacked Authority to Later Ratify that Act?
The decision to file this lawsuit against the City’s former Attorneys was made by the McCall City Manager without the prior approval of the City Council. The Attorneys contend that the City Manager lacked the authority to make that decision under Idaho’s open meeting laws. Although the City Council later ratified the decision in a vote conducted in accordance with the open meeting laws, the Attorneys contend that such ratification is of no effect because the City cannot ratify a void act. The district court did not address this issue because it ruled that the City’s claim was barred by the statute of limitations. On appeal, the Attorneys argue that if we determine that the district court erred in dismissing the City’s complaint pursuant to the statute of limitations, we can uphold the dismissal on this ground. The parties have briefed and argued this issue, and because it will be an issue on remand we will address it.
Idaho Code § 50-811 provides that the city manager is “the administrative head of the city government under the direction and supervision of the council” and has “general supervision over the business of the city.” The City argues that these statutory provisions include the authority to authorize the commencement of this lawsuit. The authority that can be exercised by a city manager must be considered in context with Idaho’s open meeting laws.
Idaho’s open meeting laws are codified at Idaho Code §§ 67-2340 through 67-2347. Section 67-2340 “declares that it is the policy of this state that the formation of public policy is public business and shall not be conducted in secret.” Although the statutes do not define what constitutes “the formation
In this case, the governing body of the City is the city council. I.C. § 50-805. With few exceptions, a “decision” of a governing body must be made by voting at meetings open to the public. I.C. § 67-2342(1). Idaho Code § 67-2341(1) defines a “decision” as “any determination [or] action ... on which a vote of a governing body is required ..., but shall not include ministerial or administrative actions necessary to carry out a decision previously adopted in a meeting held in accordance with sections 67-2342 through 67-2346, Idaho Code.” Thus, the governing body is not required to vote on “ministerial or administrative actions” that are necessary to carry out decisions previously reached in accordance with the open meeting laws. If an action cannot be characterized as “ministerial or administrative” in order to carry out a prior decision of the governing board, then the action must be previously approved by the governing board in accordance with the open meeting laws.
In
Farrell v. Board of Comm’rs, Lemhi County,
On May 24, 2007, the city council ratified the filing of this lawsuit at a meeting held in compliance with the open meeting laws. The Attorneys argue that such action cannot operate to authorize a decision that was not initially made in conformity with the open meeting laws. Idaho Code § 67-2347(1) provides, “If an action, or any deliberation or decision-making that leads to an action, occurs at any meeting which fails to comply with the provisions of sections 67-2340 through 67-2346, Idaho Code, such action shall be null and void.” Relying upon
Worlton v. Davis,
The Worlton case does not support the Attorneys’ argument. In Worlton, the plaintiffs brought an action to enforce a covenant not to compete in an employment contract entered into between a physician and a partnership. One of the members of the partnership when the contract was made had been a layperson, who acted as the partnership’s business manager. The employment contract gave the layperson the right to supervise the physician, resulting in the layperson having the right to attempt to practice medicine through a licensed employee. This Court held that the employment contract was therefore void as against public policy and that it could not be validated by estoppel or ratification based upon the physician’s continued employment after the retirement of the layperson.
In Worlton, the contract itself was void as against public policy because it enabled a layperson to practice medicine without a license. The Court held that in such circumstances, it will leave the parties in the identical position in which it finds them and not enforce the contract. The contract between the City and its current attorneys is not contrary to public policy. There is no public policy prohibiting a city from hiring legal counsel, or banning it from filing a legal malpractice action against its former Attorneys.
where deliberations are conducted at a meeting violative of the Open Meetings Act but no firm and final decision is rendered upon the questions then discussed, the impropriety of that meeting will not taint final actions subsequently taken upon questions conscientiously considered at subsequent meetings which do comply with the provisions of the act.
Likewise, in
Petersen v. Franklin County,
E. Are the Attorneys Entitled to an Award of Attorney Fees on Appeal Pursuant to Idaho Code § 12-120(3)?
The Attorneys seek an award of attorney fees on appeal pursuant to Idaho Code § 12-120(3). Because we are vacating the judgment and remanding this case for further proceedings, any determination of the prevailing party is premature until the case is finally resolved.
MBNA America Bank, NA v. Fouche,
IV. CONCLUSION
We vacate the judgment of the district court. We affirm the dismissal of Counts Two, Four, Five and Six of the First Amended Complaint, and we remand this case for further proceedings that are consistent with this opinion.
Notes
. Prior to the motions for summary judgment, the City filed a second amended complaint, which added an allegation that the Attorneys negligently failed to advise the City that under certain circumstances the deadline for completion of a construction contract could be extended. The district court did not address this allegation, possibly because the Attorneys had filed answers to the first amended complaint before the City filed its second amended complaint, and it could not then file that complaint without leave of court, I.R.C.P. 15(a), which leave the City apparently did not obtain.
. There is no contention that the city council had previously made a policy decision establishing guidelines setting forth the circumstances under which the city manager could file lawsuits without the prior approval of the city council.
