181 Mo. App. 254 | Mo. Ct. App. | 1914
Plaintiff's action is to enforce the lien of six special tax bills issued by the city of Maryville, a city of tbe third class, for grading, paving and curbing one of its streets about one mile in length; the paving to be with vitrified brick, laid down on four inches of sand. Plaintiff is the assignee of the bills. The work was accepted by the city and tax bills issued. The judgment in the circuit court was for the defendant.
At the trial plaintiff introduced the tax bills and thereby made a prima-facie case. Defendant then took up the burden of defence on these grounds as set out in his brief.
First: That resolution “ D, ” the preliminary resolution declarifig the work of improvement necessary, did not include and describe the work of grading or reducing said street to the established grade as required by statute.
Second: That there was no estimate of the cost of the improvement prepared and filed by the city engineer with the board of aldermen, and that if the paper filed by him be considered an estimate, that the contract price at which the work was let was above and in excess of said estimate.
Third: That there was not a substantial compliance by the contractor, with the provisions of paving ordinance No. 85, the specifications therein contained and the contract for the improvement, in the following:
B: That the sand foundation for the pavement was not constructed four inches thick after rolling, in compliance with the paving ordinance, specifications and contract.
C: That the parkways were not filled and finished level with the curbing in compliance with the paving ordinance, specifications and contract.
D: That the sand bed or foundation was not prepared and smoothed off to a true and even surface with the templet stretching from curb to curb, as required by the paving ordinance, specifications and contract.
E: That the curbing was not finished with a coat of neat cement, troweled and finished to a uniform surface and color throughout, as required by the paving ordinance, specifications, and contract.
The court properly found against defendant on the first ground. The resolution was sufficient under all the decisions on that subject. It meets the requirements stated in City of Kirksville v. Coleman, 103- Mo. App. 215. The reference to another ordinance for the grade was sufficient. It was not necessary that the plaintiff should introduce the latter in evidence.
As-to the second gound; when defendant states there was no estimate filed he evidently does not wish to be understood literally, but rather that the paper filed was not a proper estimate. His position is that if it be considered a proper estimate the contract price was in excess of it, and thereby the tax bills were invalidated. The estimate was made by the city engineer that being one of his duties under the statute, section 9407, Revised Statutes 1909. It stated approximately the number of feet or yards, in each of the following divisions of the work, placed in a horizontal- column, viz., paving brick-, curbing, sand, excavation and oak
The next point of defence is, that the grading was not done as established and required by the ordinance. The proposition defendant undertook to establish under this objection was that the grade of the street as paved by the contractor varies from the ordinance from one to twenty-four inches. These variations were at different points named in the evidence. The maximum was at a point midway between two streets. At this point the abutting lots set above the grade named in the ordinance, between six and seven feet; but as actually graded only between four and five feet.. The contractor was paid by the yard and by lessening the depth of the cut the abutting property was benefited and the owners have less to pay. The ordinance contained these provisions: “All work shall be done under the supervision and to the satisfaction of the City Engineer.” ■ “The Engineer shall furnish all lines and grades and mark same on the ground as needed. The-contractor shall carefully preserve all such marks and. if reasonable care is not exercised in preserving same-the contractor will be charged up with the cost of re-setting the same.”
The engineer set the grade stakes at this point (Johnson v. Duer, 115 Mo. l. c. 377),, and the contractor did the work in accordance with them, without, knowing they made any change. So therefore, with no-harm to the property owner, with no profit to the contractor, or bad faith in him, and with a finished work as serviceable as if the variation had not occurred, we-find no reason either within the bounds of the strict, rules of law which properly govern cases of this character, or of fairness to the contractor who is not shown
Another ground taken against the validity of the bills is that the sand foundation for the brick did not comply with the contract requiring it to be four inches in depth after being rolled. Prom the nature of such work it would be impossible to get a foundation of precisely four inches' varying neither more nor less. And it would be practically impossible to get as much as four inches at every part, unless a much greater quantity was put down. In such instances as this the law that a substantial compliance is all that may be required is both wise and just.
We do not regard the record as disclosing any evidence of a character to show there was no substantial compliance. Defendant stated that he measured in one place while the work was in progress and found only two and three-fourths inches of sand. We count this as nothing. At that time there might have been a spot not yet filled which no one could say at the trial, more than four years afterwards was left at that depth. There was other evidence introduced by defendant
The ordinance provided as follows: “"Whenever the parkway back of the curb needs fillin to bring the same to proper grade the surplus dirt excavated out of the street to be paved shall be deposited therein in á uniform manner and the surface of the Same when filled to the proper height shall be left to a uniform and even surface. ’ ’ Other parts of the ordinance provided that the dirt need not be hauled a greater distance than 1000 yard, unless there was extra pay. Defendant contends there was no. compliance with this part of the ordinance. But there was a failure of proof in this respect. The chief reliance here is that at one place the parkway was neglected, and that eighty-three loads of dirt were thrown in there.by Costello so as to secure a foundation for a sidewalk. Passing by any question whether the word “parkway,” as used in the ordinance meant the sidewalk space, we find that at this place there was a ditch which was stated by some of the witnesses to be twenty feet deep. It was perhaps impracticable to fill this, or to secure it when filled. At any rate, there was no evidence to show that the failure to fill this was a failure to substantially meet the terms of the ordinance. There was nothing to show that the surplus dirt from this street was not used at other places. Furthermore, we are of the opinion that clearly the ordinance did not contemplate the filling of a ravine ranging from ten to twenty feet in depth. As illustrative of our position in this respect, see Excelsior Springs v. Ettenson, 120 Mo. App. 215, 230, 231.
The next objection to the bills is that the sand foundation was not smoothed off and curved to the subgrade of earth with a “templet, reaching from curb to curb as required by the ordinance. ’ ’ The evidence shows that the proper smoothing and curve was made and as the engineer stated with one kind or character of templet; but on the trial court reminding him that
Coming to the last of the foregoing objections, viz., that the curbing was not troweled off “with a neat coat of cement,” as required by the oridnance, we find that this was not done. There was no showing of guaranty of the work, or of its maintenance and there is a failure of evidence to show that the curbing as a whole was in bad condition. Some witnesses stated one or more places where it was cracked or otherwise defective. But considering the entire length and the time since its construction we think these defects unsubstantial; and they are not made a part of defendant’s' objection. While this will not defeat the entire tax bill (Porter v. Paving Co., 214 Mo. 1, 17-19) the fact remains that the finish called for was not given; and the record does not show what the cost of such finish would be, and we therefore are without data whereby we may ascertain what sum should be deducted from the. price. The cost of the curbing is stated in each tax bill to be $20.63. In such circumstances we have concluded that plaintiff’s case failed in that respect. We will therefore strike that part from plaintiff’s claim (Hoag v. Ward, 186 Mo. 325, 348; Neil v. Ridge,