74861. CITY OF LAGRANGE v. GEORGIA POWER COMPANY.
74861
Court of Appeals of Georgia
NOVEMBER 4, 1987
REHEARING DENIED NOVEMBER 24, 1987
(363 SE2d 286)
SOGNIER, Judge.
“This is a court for the correction of errors of law. As such, we are bound to apply the plain language of pertinent statutes as written. Issues of policy are properly addressed to legislative bodies.” Thomaston Mills v. Kierbow, supra at 370. “The [Workers‘] Compensation Act constitutes a complete code of laws upon the subject of the rights and remedies of employers, employees, and their dependents. [Cits.] This court can neither rewrite the law nor hedge it about with restrictions not included in it.” St. Paul Fire &c. Ins. Co. v. Miniweather, 119 Ga. App. 617 (3) (168 SE2d 341) (1969). We are not at liberty to impose any limitations or exceptions upon an employee‘s statutory right to recover compensation in the absence of a clear legislative intent. General Motors Corp. v. Hargis, 114 Ga. App. 143 (1) (150 SE2d 303) (1966).
If the legislature intends that temporary total disability wage benefits are to cease at the end of a person‘s work-life, it has not said so. Nor has it hinted at any standard of measure for ascertaining such an event. The Workers’ Compensation Act is a humanitarian measure which should be liberally interpreted by this Court to carry out that purpose. Atha v. Jackson Atlanta, Inc., 159 Ga. App. 433, 436 (283 SE2d 654) (1981).
Judgment affirmed. McMurray, P. J., and Sognier, J., concur.
DECIDED NOVEMBER 4, 1987 — REHEARING DENIED NOVEMBER 24, 1987 —
Susan V. Sommers, Judith A. Hodges, Alfred A. Quillian, Jr., for appellant.
Johnny B. Mostiler, for appellee.
SOGNIER, Judge.
The City of LaGrange and Georgia Power Company filed a joint petition for a declaratory order with the Georgia Public Service Commission (PSC), to determine which had the right under the Georgia Territorial Electric Service Act,
The record reveals that in an effort to attract new industry to the City, the Development Authority of LaGrange constructed a building in an industrial park on speculation. Temporary electric service to the site during construction was provided by the City on application of the contractor, and service was transferred to the Authority after completion of the shell. The building was purchased by a manufacturer of plastic bags, and electric service was again transferred, this time to the contractor hired by the purchaser to complete construction of the facility. When operational, the premises, located within an area annexed to the City after March 29, 1973, will have single-metered service and a connected load in excess of 900 kilowatts. Both appellant and appellee own lines and are authorized to provide service to the location.
The Georgia Territorial Electric Service Act generally provides for assignment of electric suppliers by geographical location. However,
The City contends the trial court erred by affirming the PSC‘s order because, having lawfully provided service to the premises during construction,
Our rejection of the City‘s interpretation of subsection (b) is further supported by an examination of subsection (f) of the statute, which, while not addressing itself at all to large load consumers, specifically provides that a supplier may furnish temporary or construction service to premises in some instances and yet not acquire the exclusive right to provide permanent service to the premises. Since subsection (f) is nowhere qualified as an exception to subsection (b), the interpretation urged by the City places the plain language of subsection (f) in conflict with subsection (b).
Such a result is not only anomalous, it is unnecessary. The PSC interpreted subsection (b) so as to harmonize all three subsections of the statute to provide a reasonable and sensible construction. Under the PSC‘s interpretation, the providing of temporary service to a construction site by one supplier of electric service does not foreclose the large load consumer from choosing another authorized supplier for the permanent service to the completed site. In this manner subsection (a) is given its plain and unambiguous meaning that large load customers may choose among the authorized electric suppliers; subsection (b) continues to authorize every supplier who once furnishes permanent service to premises in accordance with the Act to have, notwithstanding any other provision, the exclusive right to continue serving those premises; and subsection (f), which simply has no bearing on this issue, remains viable according to its plain language in the situations in which it was intended to apply without any conflict with subsection (b).
In interpreting
We find no merit in any argument that the Supreme Court‘s holding in City of Calhoun v. North Ga. Elec. &c. Corp., 233 Ga. 759 (213 SE2d 596) (1975) requires a different result. Although both City of Calhoun and the case sub judice involve the Georgia Territorial Electric Service Act, that is the only point of reference these cases have in common since City of Calhoun was concerned solely with a constitutional challenge to the Act, and does not suggest or intimate the validity of a different interpretation.
Since we find that the PSC correctly interpreted the statute, the superior court did not err by affirming the PSC‘s order.
Judgment affirmed. Birdsong, C. J., Deen, P. J., Carley, Pope and Benham, JJ., concur. McMurray, P. J., Banke, P. J., and Beasley, J., dissent.
BEASLEY, Judge, dissenting.
The PSC ruled that the city lawfully provided service initially to the site of the manufacturing plant under construction pursuant to the Act because at the time service was provided to the construction site the connected load was less than 900 kilowatts, “and thus service was provided by the assigned provider, the city. Thus, the question presented is whether an electric supplier who lawfully extends and furnishes electric service to a construction site at which a premises is to be constructed which, at the time of initial full operation, will require 900 kilowatts or greater, may preclude the operation of the ‘customer choice’ provisions of [
The city contended that its initial providing of electric service to the construction site of the premises constituted service as contemplated by
After noting that the Act empowered it to arbitrate disputes and, where there was no clear cut resolution, to resort to statutory construction and common sense application of the Act, the PSC concluded that “to allow the city‘s contention to prevail would emasculate the provisions of subsection (a),” and thus “a distinction should be drawn between temporary construction service and permanent service, for purposes of subsection (a) ‘customer choice’ provisions . . . By encouraging healthy competition between electric suppliers for large load customers, electric suppliers will strive to provide reliable electric service at the least cost to the consumer . . . Therefore, in instances where a premises under construction takes temporary or construction service from an electric supplier lawfully authorized to provide that electric service and the premises, at initial full operations, will be utilized by one consumer and have single-metered service of 900 kilowatts or greater, the customer shall be entitled to select an electric supplier for permanent service pursuant to
The city‘s argument is that the plain and unambiguous language of the Territorial Electric Service Act, specifically the “grandfather” provision of
While the aims expressed by the PSC in its interpretation of the purposes of the Act may be desirable public policy, they are not in accord with the construction previously endorsed by our Supreme Court and stated in City of Calhoun v. North Ga. Elec. &c. Corp., 233 Ga. 759, 767-68 (5) (a) (213 SE2d 596) (1975), where the Act was unsuccessfully attacked as an unconstitutional restraint of trade. The Court recognized that “under the standards set forth in the Act, even though a particular area may be assigned to an electric supplier, other electric suppliers already serving customers in that area may continue to serve those customers as well as new customers located near their lines.” It explained that the restriction on competition was valid because “unrestricted competition between electric suppliers could injure existing public service and otherwise adversely affect the public interest. . . [t]o the extent the assignment of service areas under the Act restrains competition, the restraint is for the benefit of the public in minimization of duplication of facilities and prevention of other adverse economic and environmental effects.” (Indention omitted.)
Not only was the statutory interpretation reached by the PSC and affirmed by the superior court here inconsistent with the con-
Moreover, “statutes must not be interpreted to thwart the avowed purpose of the legislature.” Hardison v. Booker, 179 Ga. App. 693, 696 (4) (347 SE2d 681) (1986). The legislative intent and policy is specifically declared within Section 2 (
Bearing in mind the goals of the Act, I conclude that the right of an over-900 kilowatt customer to choose its supplier is made subordinate to the right of an assigned electric service supplier to continue service once it has been lawfully extended and furnished under
“‘Service’ means retail electric service and includes temporary or construction service as well as permanent service. . . .”
The 900-kilowatt “customer choice” exception of
I am authorized to state that Presiding Judge McMurray and Presiding Judge Banke join in this dissent.
BEASLEY, JUDGE
