273 Mo. 279 | Mo. | 1918
This is an appeal from an order granting a new trial. The appellant, the city of Kennett, to be designated herein as the city, brought suit in the circuit court of Dunklin County against the Katz Construction Company and the American Surety Company, to be designated herein respectively as the contractor and the surety company, each a corporation, upon a bond for $18,000 of the former as principal and the latter as surety, given to the city to insure the faithful performance of a contract for furnishing the necessary materials and labor to construct certain lines of sewers in the streets and alleys of the city and for the performance of other work incident thereto and necessary to facilitate the disposal of sewage, for which the contractor was to' be paid a total sum of $35,204.06, in the amounts and at the times stated in the contract; and which contract it was alleged had been breached by the contractor. The surety company filed its separate answer. The city dismissed as to the contractor. A
The contract and bond on which this action is based contains among other provisions, the following:
“And it is hereby expressly agreed by and between all parties thereto that no extension of time, or alteration in, addition to, or omissions from the work provided for under said contract, plans and specifications, although without consent of said surety, shall violate this bond or discharge said surety. . . .
“Upon request of the contractor, the engineer will, upon or about the first of each month, make an estimate of work done and material delivered for the previous month, and payment will then he made by the council for ninety per cent of said estimate.”
The contract also provided that the work should be completed within nine months after its execution, which was in April, 1913, and for each day’s delay the contractor should pay $5 per day as liquidated damages. Thereupon the contractor commenced work under the contract. Subsequently certain changes were made in the plans and specifications at the request of the contractor. According to the testimony of expert engineers these changes did not increase the cost of construction or entail a delay in the work.
The work progressed under the contract until September 1, 1914. During this time thirteen estimates were rendered by the contractor to the city, aggregating $32,436.86. Of this amount ten per cent was withheld in accordance with the contract to be paid upon the completion and acceptance of the work, and the contractor was paid the difference, to-wit, $29,193.17, less $645 held by the city for delays in the work, which constituted the aggregate up to that time of the penalty therefor of $5 per day as prescribed in the contract.
After the delivery by the city of its warrant to the contractor in payment of estimate number 15 and the acceptance of same by it, owing to the amount of water in the ground where the sewers were being constructed, it was mutually agreed that work on the system should be suspended until such time as it was practicable to resume operations. At the time this agreement was entered into the contractor had been paid for all work then performed.
The total estimate to this date for work performed amounted to the sum of $34,400.15. The amount paid to the contractor was $30,960.14. The difference between the total estimates for work performed and the amount paid the contractor was $4,390.01, $950 of same being the aggregate penalty for delays occasioned by the contractor, and the balance, $3,440.01, being the amount, ten per cent, authorized to be withheld until the completion of the work.
Conditions thereafter permitting that work be resumed, the city notified the contractor to proceed to complete the work and that funds were available for its payment. At that time the city had available the sum of $6100, for the payment of this work, or more than the balance due the contractor under its bid. The contractor refused to perform any more work under the contract. Whereupon the city gave notice to the surety company, as surety on the contractor’s bond, of the
The purpose of this rule is salutary. It sharpens the issues in enabling the appellant to directly combat the ruling of the trial court and limits the review, upon appeal, to the reasons for such ruling instead of requiring a consideration of all the issues raised during the trial. The statutory provision which directs that orders for new trials shall specify the grounds therefor (Sec. 2023, R. S. 1909) is, if nothing more, a legislative recognition of the wisdom of the rule.
An examination and an analysis, in the light of the record, of the order sustaining the motion for a new trial, will determine the rule of procedure applicable in a review of this case. It is as follows:
“Now come the parties herein by their respective attorneys and defendant’s motion for a new trial again coming on to be heard, it is taken up, argued and submitted to the court, and the court being sufficiently advised in the premises, orders that the said motion should be sustained unless the plaintiff enters a remittitur of eleven thousand nine hundred dollars, which remittitur plaintiff now refuses to make. It is therefore ordered and adjudged by the court that said motion should be and is sustained, and a new trial herein ordered. To which ruling of the court the plaintiff objected and excepted at the time.”
On its face this order may be construed as being based on an excessive verdict. Such a construction is tenable only upon a superficial consideration of the order. The authority to enter a remittitur, on account of an excessive verdict, is limited to cases where the jury finds for more than the amount authorized in the instructions. This was not the case here. The penalty of the bond, $18,000, was the limit, under the pleadings, of the city’s right of recovery. The evidence sustained a finding in this amount under the instructions given. The order,
In addition, it is not inappropriate in defining the limit of our review, to say that the doctrine of a wide discretion with which courts are held, in a certain class of cases, to be vested in granting new trials, is inapplicable here. The giving of an instruction as to the measure of damages was the court’s reason for its action. This was a matter of law. There can be no discretion as to the law of a case. It is only when the court’s ruling is directed to the facts that the exercise of discretion is permissible. [Loftus v. Met. St. Ry. Co., 220 Mo. l. c. 481.]
Has the city, therefore, well sustained the burden it assumes in showing that the trial court, stript of discretion, has ruled erroneously in granting a new trial? If so, then the verdict should be upheld, unless the surety company has, in addition, called our attention to other matters in the record sufficiently prejudicial in their nature to warrant our ruling otherwise.
This contention is urged on the ground that this provision is mandatory and exclusive and leaves no other remedy in the city upon a breach of the contract. There is no merit in this contention. The most casual reading leads to the conclusion that while the grant of power in the board of aldermen is complete, the right to exercise it is purely permissive. The
Whether this be construed as a comment on the conduct of a party to the suit, or as a failure to in-' troduce the contractor as a witness, the rule as to the propriety of the remarks is the same. In alleged errors of this character it must appear that the prejudicial effect of same was sufficient to influence the rendition of the verdict; otherwise, it will not be regarded as material. [Gulf, C. & S. F. R. R. Co. v. Curb, 66 Fed. 519, 13 C. C. A. 587.] In the application of this rule liberal latitude is allowed counsel in their deductions from the evidence. [Jaggard v. Railroad, 264 Mo. 142.] While the cases are not numerous on this subject, the rule is nevertheless well established' as to the right of counsel to comment upon the failure of a party to testify in his own behalf in a civil action. Only impliedly has the question been passed upon in this court. In Scullin v. Wabash Ry. Co., 184 Mo. 695, it was held that the remarks of counsel for the plaintiff, who in his argument stated that defendant could have gone to the scene of the accident and with the same train determined within what distance it could have been stopped and then could have brought its witnesses and had them swear to this fact, were not such a violation of legitimate argument as amounted to error. The Kansas City Court of Appeals has more directly passed upon this matter. In Stagner v. Rich Hill, 119 Mo. App. 281, an action against a city for injuries from defects in a sidewalk, it was held that
The remark complained of that the “American Surety Company was incorporated in this State to do business for hire” cannot under a reasonable interpretation of same be held to have been prejudicial. It was but a characterization of the company’s nature and the purpose of its creation. This was certainly permissible and in making it counsel did not state other than the truth or under the guise of argument assume the functions of a witness. The words employed do not indicate that they were expressed in a manner to which serious protest can be urged. The objection to same must therefore be held to be trivial.
A like reason authorized the trial court to refuse the surety company’s instructions numbered 12 and 13, as to what constituted a failure to make payments for work performed under the terms of the contract and the consequent nonliability of the surety company if such proof satisfied the jury. These instructions were covered by the surety company’s instruction numbered 10, which had been given by the court. When an issue has been definitely defined for the guidance of the jury, the refusal of instructions in detail comprehending the same subject will not constitute error.
The surety company in signing the bond made this provision as much a part of its agreement as any other portion of the obligation. What was shown to have been done thereunder was, therefore, with the express assent of the surety company and did not change its obligation. [Howard County v. Baker, 119 Mo. l. c. 405; Hax-Smith Furn. Co. v. Toll, 133 Mo. App. 404; Ashenbroedel Club v. Finlay, 53 Mo. App. 256; Reissaus v. Whites, 128 Mo. App. 135; Fidelity Co. v. Robertson, 136 Ala. l. c. 409; People’s Lumb. Co. v. Gillard, 136 Cal. 60; Lumber Co. v. Surety Co., 124 Iowa, 619; Kretschmar v. Bruss, 108 Wis. 396; Blauvelt v. Kemon, 196 Pa. St. 128.]
The exception to this rule is when it appears that the changes made are so extensive as to substitute a different contract from the original. [Swasey v. Doyle, 88 Mo. App. 536; Miller-Jones Furn. Co. v. Ice Co., 66 Ark. 287; Consaul v. Sheldon, 35 Neb. 247; House v. Surety Co., 21 Tex. Civ. App. 590.] There is no evidence of such changes here. On the contrary, expert witxiesses testified that the changes were advantageous to the contractor, in that they entailed no additional time and lessened the cost of construction. When this is the case the rule is not applicable even in the absence of an agreement as to the changes by the surety; the test of the application of the rule generally being evidence of such a change as will increase the surety’s burden either iix the cost of coxxstruction or an extension of the term of performance. [Benjamin v. Hillard, 23 How. (U. S.) 149; Prescott Nat. Bank v. Head, 11 Ariz. 213, 21 Ann. Cas. 990.] Absent these, there is no injury and hence no ground of complaint. The surety company, however, is precluded from making this defense under
Reversed and remanded with directions.