CITY OF INGLEWOOD-LOS ANGELES COUNTY CIVIC CENTER AUTHORITY et al., Petitioners, v. THE SUPERIOR COURT OF LOS ANGELES COUNTY, Respondent; ARGO CONSTRUCTION CO., INC., et al., Real Parties in Interest.
L.A. No. 29919
In Bank. Supreme Court of California
Sept. 6, 1972
7 Cal. 3d 861
Donald E. Olson, City Attorney, R. Wicks Stephens II, Stephens, Jones, La Fever & Smith and Hassard, Bonnington, Rogers & Huber for Petitioners.
Martin & Flandrick and Stephen H. Galton as Amici Curiae on behalf of Petitioners.
No appearance for Respondent.
Paul M. Hittelman, Everett W. Maguire and Shapiro & Maguire for Real Parties in Interest.
OPINION
MOSK, J.—Petitioners seek mandate to compel respondent superior court to annul its judgment and a peremptory writ of mandate issued thereon, or, in the alternative, prohibition to prevent the enforcement of its judg
Section 25454 of the
Petitioner Authority was constituted pursuant to a “joint exercise of powers agreement” entered into in February 1970 by the City of Inglewood and the County of Los Angeles, as authorized by
Charles Luckman Associates (Luckman) was retained by the Authority as architects, and prepared preliminary plans for the civic center buildings, a $12,000,000 project. Luckman recommended that the Authority proceed with the construction of the project by means of a management contract. The operation of the management contracting method was summarized by Luckman as follows:
“Under the traditional lump sum method of bidding, contractors enter the project process upon the completion of working drawings. At this point in time they have little opportunity or incentive to contribute to cost reduction.
“The Management Contracting Method . . . differs from this traditional lump sum method in that the contractor is brought into the building project through competitive bidding at or shortly after, the completion of preliminary plans, rather than working drawings. He is then called upon to contribute his practical expertise during the development of the working drawings, and subsequently apply this expertise during construction, in order to achieve maximum economies. He is expected to provide cost estimates from time to time during development of working drawings to determine that the project is within budget so that some of the early phases of construction can proceed prior to completion of all of the drawings. This makes it possible to save a significant amount of time in the total building process.” The management contractor performs none of the construction itself unless he is awarded a separate contract therefor as the lowest responsible bidder in subsequent bidding under the traditional “lump sum” bidding procedures.3
The management contracting procedure was approved by the Inglewood City Council, and Swinerton was awarded the contract after various proceedings which will be described in detail infra.
I
Petitioners urge that the management contract here at issue was basically a contract for services as a consultant and supervisor-manager rather than a contract for a “construction project” and thus did not fall within the competitive bidding requirements upon which Argo relies. Those requirements are found in the
It is true that the management contractor was to perform services and to lend his experience and expertise in the preparation of the final plans, and in that respect may be likened to an engineer or an architect whose services may be procured without strict compliance with competitive bidding requirements. (See Kennedy v. Ross (1946) 28 Cal.2d 569, 581-582 [170 P.2d 904]; San Francisco v. Boyd (1941) 17 Cal.2d 606, 620 [110 P.2d 1036]; Cobb v. Pasadena City Bd. of Education (1955) 134 Cal.App.2d 93, 95 [285 P.2d 41].) However, our review of the other duties and obligations which were required of the management contractor in this case, including his guarantee of the outside price based on the subcontract bids, persuades us that the management contracting procedure as proposed and followed here is too closely akin to traditional lump sum general construction contracting to be held exempt from the statutory competitive bidding requirements. To hold otherwise as a broad principle would open the door to possible favoritism, fraud or corruption in the letting of other public construction contracts.
II
The next issue is whether petitioners applied the proper standards in determining that Swinerton was the lowest responsible bidder, as that term is used in
The parties are in agreement that factors such as those set forth above may be considered in determining whether a bidder is responsible. Argo challenges the award of the management contract to Swinerton not because petitioners employed such criteria but because petitioners made no determination, either express or implied, that Argo was not responsible. Instead, it is asserted, petitioners found Swinerton to be the relatively superior bidder and awarded the contract on this basis. Argo cogently argues: “To permit a local public works contracting agency to expressly or impliedly reject the bid of a qualified and responsible lowest monetary bidder in favor of a higher bidder deemed to be more qualified frustrates the very purpose of competitive bidding laws and violates the interest of the public in having public works projects awarded without favoritism, without excessive cost, and constructed at the lowest price consistent with the reasonable quality and expectation of completion.”
We agree with these assertions, and we hold that the contract for a public construction project must be awarded to the lowest monetary bidder as commanded by
The trial court found that petitioners chose to award the contract to Swinerton because they viewed Swinerton as more qualified than Argo and that the qualifications of Argo to perform the contract were never questioned. An examination of the procedure followed in making the award lends credence to the trial court findings.
Petitioners proceeded as follows: The “Notice Inviting Bids” for the fee to be charged the Authority as management contractor stated, inter alia, that final evaluation and award would be made on the basis of the proposal submitted by the lowest responsible bidder, the contractor‘s financial resources, his surety and insurance experience, construction experience, completion ability, personnel, equipment, work load, and other factors pertinent to a project of the scope involved. Bidders were required to include eight informational items in their bids, the first six of which related to financial responsibility.6 A uniform point system was applied to the financial responsibility information submitted. The highest score attainable was 38, but any contractor who scored 30 or more on this scale was to be considered “qualified.”
Twelve bids were received. They were reviewed, analyzed, and evaluated by Luckman as an architect and by the staff of the director of public works of the city (reviewing panel). The bids of nine were rejected, and it was ultimately determined that Argo and Swinerton were among the three lowest bidders. Under the formula applied to determine the total bid cost Argo‘s bid was some $70,000 lower than that of Swinerton.7
Swinerton achieved 34 on the financial responsibility information questionnaire, while Argo obtained a score of 30, the minimum necessary for qualification.
Thereafter, each of the three lowest bidders was interviewed by the reviewing panel, and further information was sought with respect to its experience and capabilities. The three contractors were evaluated in terms of their construction experience, completion ability, personnel, work load, and client relationships. Again, a uniform point system was applied, this time to reflect the performance capabilities of the three low bidders. Out of a maximum of 61 points, Swinerton rated highest with 55 points, while Argo scored second with 42 points.
The reviewing panel, in a report to the Authority which set forth the details of the procedure it had followed in its investigations including the results of the evaluation scores attained by Swinerton and Argo, recommended that Swinerton be awarded the contract as the lowest responsible bidder. The report did not state that Argo was unqualified to perform the job but pointed out that, based upon the evaluation scores and the interviews, the panel believed that by selecting Swinerton the city would obtain excellent construction talent, experience, and other qualities important to the successful completion of the project. The architect representative on the panel, in a separate report to the Authority, stated that while Argo was considered capable within its field of construction, Swinerton‘s qualifications were considered to be so superior as to justify its selection as the lowest responsible bidder.
The recommendations of the reviewing panel were discussed by members of the Authority on December 17, 1970. At that meeting, the public works director, a member of the panel, explained the panel‘s choice of Swinerton. He emphasized, for example, that Argo was primarily a school contractor and the maximum height it had built was four stories, whereas Swinerton had experience with high rise structures (the city‘s project was deemed a high rise building). He offered other reasons as well for the panel‘s choice of Swinerton over Argo. Representatives of Argo contended at the meeting that the contract could only be awarded to Swinerton if the Authority found Argo to be irresponsible, and that Argo was in fact qualified to do the job.
It is evident from the procedure followed by the Authority that, as Argo charges and the trial court found, petitioner merely determined that Swinerton was superior to Argo in its ability to perform the contract, and that no determination was made whether in fact Argo, the lowest bidder, was also qualified to perform the contract. Since petitioners did not comply with the mandate of
III
Finally, it is contended that the award to Swinerton must be set aside because Argo was not afforded a full evidentiary hearing as to whether it was a responsible bidder.9 Due process requires, asserts Argo, that prior to awarding a contract to one who is not the low monetary bidder, the Authority must conduct a hearing, which shall include a full panoply of judicial trial procedures, including pleadings, cross-examination of witnesses, and formal findings. No case so holding is called to our attention, and Housing Authority of Opelousas, La. v. Pittman Const.
In that case, Louisiana law provided that a public works contract must be awarded to the lowest responsible bidder, but a higher bidder had received the award primarily on the basis of evidence received by the awarding authority from the higher bidder casting doubt upon the low bidder‘s responsibility. The contractor submitting the low bid was not present at the meeting and was not afforded an opportunity to rebut the charges prior to the award. It was held that the low bidder was entitled to be informed of the charges made against him and to reply to those charges. However, opined the court, the awarding authority was not required to “conduct FBI investigations, hold elaborate hearings, adhere to legal rules of evidence, and function as a judicial body.” (264 F.2d at p. 704.)
We hold that prior to awarding a public works contract to other than the lowest bidder, a public body must notify the low monetary bidder of any evidence reflecting upon his responsibility received from others or adduced as a result of independent investigation, afford him an opportunity to rebut such adverse evidence, and permit him to present evidence that he is qualified to perform the contract. We do not believe, however, that due process compels a quasi-judicial proceeding prior to rejection of the low monetary bidder as a nonresponsible bidder.
Let a peremptory writ of mandate issue directing the trial court to vacate its judgment and the peremptory writ of mandate issued thereon and to make new findings and conclusions of law and enter a new judgment in accordance with the principles set forth herein.10
Peters, J., Tobriner, J., and Sullivan, J., concurred.
In the instant case, the services to be rendered by the management contractor may be likened to those provided by the Authority‘s architectural firm, and indeed those services were proposed by the architect to complement its own services in preparing final plans and specifications and in supervising the work of construction, in an attempt to provide the city and the Authority with the most efficient and desirable construction at the lowest cost. The management contractor was to perform no actual work of construction nor furnish any materials, labor, supplies or equipment for the project. All of such work and materials were to be let out to bid to the lowest responsible bidders in subsequent bidding under the traditional bidding procedure applicable to ordinary lump sum contracts. At the time when Swinerton was chosen as the management contractor, only the preliminary plans for the project had been prepared; bids for the actual work of construction were to await completed final plans and specifications, which the management contractor would assist in preparing.
As the majority acknowledge, strict compliance with competitive bidding requirements need not be maintained in procuring an expert‘s services to prepare plans and specifications. (Kennedy v. Ross, supra, 28 Cal.2d 569, 581 [engineer retained to prepare plans for sewage treatment and disposal plant].) As noted in San Francisco v. Boyd, supra, 17 Cal.2d 606, 620, “The employment of a person who is highly and technically skilled in his science or profession is one which may properly be made without competitive bidding.” In San Francisco, the approved employment was of a civil engineer to aid in the solution of traffic and transit problems. (See also Cobb v. Pasadena City Bd. of Education, supra, 134 Cal.App.2d 93, 95.)
I do agree, however, that the management contract in the instant case contains certain provisions, such as the “guaranteed outside price” clause, which justified the Authority‘s action in requiring that contract to be competitively bid. Yet as the management contract is more in the nature of a contract for expert services than an ordinary lump sum construction
The majority opinion accurately describes the elaborate rating and evaluation system used by the Authority to determine which bidder would be chosen as the “lowest responsible bidder.” I would emphasize that every bidder was given advance notice of the bid evaluation system; bidders were told that an award would be made on the basis of the bidder‘s financial resources, surety and insurance experience, construction experience, completion ability, personnel, equipment and work load, as well as the amount of the bid. On the basis of the information received from the bidders, bids were evaluated or rated in accordance with a uniform point system reflecting the performance capabilities of each bidder. In short, the evaluation system employed in the instant case seems well suited to achieve an accurate assessment of the bidder‘s qualifications while minimizing the risks of favoritism or collusion. It is significant that at no time prior to the bid opening did Argo or any of the bidders object to the method of evaluating or awarding bids or to the method of bid solicitation. And nothing in the record suggests that the Authority may have acted with an improper motive in awarding the contract to Swinerton.
As the majority concede, the term “lowest responsible bidder” is broad enough to include the attributes of quality, fitness and capacity to perform. (See Raymond v. Fresno City Unified Sch. Dist., supra, 123 Cal.App.2d 626, 629; Swanson v. Hilderbrand (1949) 94 Cal.App.2d 161, 164 [210 P.2d 95]; Cyr v. White (1947) 83 Cal.App.2d 22, 27-29 [187 P.2d 834]; Hodgeman v. City of San Diego (1942) 53 Cal.App.2d 610, 615-616 [128 P.2d 412]; West v. Oakland, supra, 30 Cal.App. 556, 560-561; 10 McQuillan, Municipal Corporations, §§ 29.73, 29.73a, pp. 423-425, 429-430.) In the context of the “hybrid” management contract involved
I would hold that the Authority‘s award to Swinerton was within its powers and did not constitute an abuse of its discretion. Accordingly, I would annul the trial court‘s judgment in its entirety.
Wright, C. J., and McComb, J., concurred.
BURKE, J.
Notes
Section 10 of the agreement relates to the design and construction of city facilities only. It provides, inter alia, that “Upon approval of the final plans and specifications for the City Project by City, Authority shall call for competitive bids to let necessary construction contracts for the City Project. Authority shall award such construction contracts to the lowest responsible bidders after the approval of said bidders by City. The City Project shall then be constructed by the lowest responsible bidders in accordance with the plans and specifications approved by City. . . .
“. . . Pursuant to Section 4 hereof, all powers of Authority and City . . . related to construction shall be exercised in the manner provided in this Agreement. . . .”
The Inglewood City Charter (in art. XXXIII, § 1) provides that a contract for the construction of a public building costing more than $2,000 shall be let to the lowest responsible bidder.
