City of Homestead v. BeardCity of Homestead v. Beard
CITY OF HOMESTEAD, Appellant,
v.
Thomas M. BEARD, etc., et al., Appellees.
Supreme Court of Florida.
Michael L. Rosen, D. Bruce May and Susan L. Turner of Holland & Knight, Tallahassee, for appellant.
David E. Smith, Director of Appeals, Florida Public Service Com'n, and J. Christian Meffert of Bryant, Miller & Olive, P.A., Tallahassee, and K. Crandal McDougall, Miami, Florida Power & Light Co., for appellees.
McDONALD, Justice.
On August 7, 1967, the city of Homestead (City) entered into a territorial agreement with Florida Power & Light Company *451 (FPL), a privately owned utility company. The agreement defined the geographic boundaries of their respective service areas in and around the city of Homestead. At the time of the agreement, the City's municipally owned electric utility was exempt from the regulatory jurisdiction of the Florida Public Service Commission (PSC).[1] However, because of the PSC's regulatory authority over FPL, the parties submitted the agreement to the PSC for approval. The agreement did not provide for a specified duration or termination date. The PSC, in Florida Public Service Commission Order No. 4285, issued December 1, 1967, approved the agreement. In response to a petition for certiorari filed by customers whose service was being transferred pursuant to the new agreement, this Court upheld the PSC's order approving the agreement. Storey v. Mayo,
In a letter to FPL dated May 11, 1988, the City gave formal notice of its intent to terminate the agreement effective August 7, 1988 and invited FPL to negotiate a new agreement. FPL responded that the agreement remains in full force and effect until a mutually acceptable change is approved by the PSC. On July 22, 1988, FPL filed a petition for declaratory statement with the PSC seeking a determination as to the rights and obligations of the parties under the agreement. On December 2, 1988, the PSC issued the declaratory statement requested by FPL, stating that the territorial agreement was a valid and binding agreement, but denying FPL's demand for prohibitive or injunctive relief against the City.
In response to a subsequent motion for reconsideration or clarification by FPL, the PSC stated that the agreement is subject to modification by the PSC in a proper proceeding, but declined to elaborate further because the City had filed an action in Dade County Circuit Court seeking a judicial declaration that the agreement is terminable upon the giving of reasonable notice. After the circuit court's denial of FPL's motion to dismiss and motion to abate on grounds that the PSC had exclusive jurisdiction in the matter, the PSC intervened and filed a petition for writ of prohibition in this Court. In Public Service Commission v. Fuller,
On September 4, 1990, the City initiated the present proceedings by filing a petition to "Acknowledge Termination or in the Alternative, Resolve Territorial Dispute" with the PSC. FPL responded by filing a motion to dismiss, which the PSC granted in Florida Public Service Commission Order No. 23955, issued January 3, 1991.[2] The City then filed a notice of administrative appeal to obtain review of that order by this Court.[3]
The City's position is that because it was not subject to the PSC's jurisdiction when *452 the agreement was executed, the territorial agreement should be construed pursuant to the law of contracts rather than the law governing PSC orders. The City further asserts that, under the law in existence when the agreement was executed, a contract lacking a definite period of duration was terminable at will by either party. Thus, because the instant agreement did not have a provision governing its duration, the City had a contractual right to terminate the agreement at will and the PSC had no statutory or case law authority to deprive the City of its right to terminate. We disagree. In the absence of an express provision to the contrary in the approved agreement, the statutory and decisional law surrounding the modification or termination of PSC orders governs the territorial settlement agreement in the instant case.
In Fuller, this Court held that the territorial agreement between the City and FPL "has no existence apart from the PSC order approving it and that the territorial agreement merged with and became a part of" the PSC order.
Any modification or termination of that order must first be made by the PSC. The subject matter of the order is within the particular expertise of the PSC, which has the responsibility of avoiding the uneconomic duplication of facilities and the duty to consider the impact of such decisions on the planning, development, and maintenance of a coordinated electric power grid throughout the state of Florida. The PSC must have the authority to modify or terminate this type of order so that it may carry out its express statutory purpose.
Id. (emphasis added). While these statements were made in the context of a jurisdictional issue, the principles set forth are applicable to the instant case.
In City Gas Co. v. Peoples Gas System Inc.,
We recognize that when the agreement was executed, municipally owned electric utilities were exempt from state agency supervision under section 366.11, Florida Statutes (1967), and that they enjoyed "the privileges of legally protected monopolies within municipal limits." Storey,
*453 In Fuller, we expressly stated that there was "clear commission authority over these territorial agreements."
The City was able to enter into the instant agreement only by obtaining PSC approval. The City may not accept the benefits flowing from antitrust immunity for a territorial agreement by obtaining PSC approval and then claim the agreement is not subject to the laws governing PSC orders.[4] Therefore, the law governing the modification or termination of PSC orders was applicable to the instant agreement to the extent it did not contradict the express terms of the agreement.[5]
Moreover, even if we were to hold that the law of contracts should be strictly applied to the agreement, we would not construe the agreement to have granted the City the right to terminate at its discretion. When a contract does not contain an express statement as to duration, the court should determine the intent of the parties by examining the surrounding circumstances and by reasonably construing the agreement as a whole. See Southern Bell Tel. & Tel. Co. v. Florida E. Coast Ry. Co.,
The City cites cases which hold that a contract for an indefinite period, which by its nature is not deemed to be perpetual, may be terminated at will upon the giving of reasonable notice. Perri v. Byrd,
In contrast, the instant agreement involves the settlement of a territorial dispute. There is no mutuality of obligation problem and neither party owes the other any further affirmative obligation, but merely has the negative duty to refrain from entering the service area of the other. Parties usually enter into settlement agreements with the intention of permanently resolving their conflicts with respect to the subject matter of the agreement. Further, PSC orders are generally considered final absent the commission's inherent authority to modify or terminate them in a proper proceeding. See Peoples Gas Sys., Inc. v. Mason,
In Storey, we stated that FPL and the City had executed the agreement "[i]n order to end the unsatisfactory effects of this type of expensive, competitive activity."
A party would be hesitant to make substantial investments in franchised areas if the other party could terminate the franchise at will. In the instant agreement, FPL refrained from competing with the City for twenty years, transferred a large number of its customers to the city,[8] and made investments in territories in which it believed it had an exclusive franchise.[9] The detriment to FPL as a result of these acts cannot be undone and it is unlikely that FPL intended to place itself in a position in which the City could unilaterally deprive it of its franchised areas under the agreement and, thus, impair its investment in those areas.[10] Therefore, as distinguished from agreements which, by their inherent nature, imply the parties intended the power to terminate the agreement at will, the nature of the instant agreement as the settlement of a territorial dispute and the fact that it was incorporated into a PSC order, is evidence that the parties intended the agreement to operate with finality absent an express provision to the contrary.
Finally, in construing a contract, it is well established that "the laws existing at the time and place of the making of the contract and where it is to be performed which may affect its validity, construction, discharge and enforcement, enter into and become a part of the contract as if they *455 were expressly referred to or actually copied or incorporated therein." Shavers v. Duval County,
After considering the surrounding circumstances, the nature of the instant agreement, and the law existing at the time the agreement was executed, we conclude that, absent an express provision in the agreement to the contrary, the law surrounding the modification or termination of a PSC order is applicable to the instant territorial settlement agreement. Therefore, the instant agreement is not terminable at will by the parties and may only be modified or terminated by the PSC in a proper proceeding as set forth in Peoples Gas.[12] Accordingly, we affirm the decision of the PSC in the instant case.
It is so ordered.
SHAW, C.J. and OVERTON and GRIMES, JJ., concur.
BARKETT, J., dissents with an opinion, in which KOGAN and HARDING, JJ., concur.
BARKETT, Justice, dissenting.
The issue to be resolved in this case is whether a territorial agreement approved by the PSC prior to 1974, which did not set forth a specific duration or date for termination, is terminable at will by either party.
The majority concludes that any contract that may have existed between the parties has, in essence, been replaced by the PSC order, which can only be terminated or modified in accordance with principles of regulatory and administrative law. Majority op. at 452. Although, by its terms, PSC approval was a prerequisite to the validity of the contract, there is a vast difference between approving the contract as valid and inferentially declaring, as the majority does, that the contract no longer exists. I cannot accept the majority's theory that the contract and the rights of the parties thereunder disappeared because PSC approval was needed to make the contract enforceable. Contracts are signed every day subject to the approval of a third party or a state agency and no one suggests that the approval requirement makes the contracts void once that approval has been obtained.
More importantly, in 1988 FPL sought and obtained from the PSC a declaratory statement that the 1967 territorial agreement was a valid, binding contract.[13] It is therefore inconsistent for FPL to now argue that the contract was subsumed in the original order.
Furthermore, in 1967 there was no statutory or decisional authority empowering the PSC to deprive a party of its contractual right to terminate a territorial agreement, or to require the party to demonstrate necessity for termination due to changed conditions. Nor can any such authority be derived from the 1974 amendment. The proviso in that amendment specifically provides that "nothing in this chapter shall be construed to alter existing territorial agreements as between the parties to such agreements." Ch. 74-196, § 1, Laws of Fla. Thus, clearly, the legislature did not intend to authorize the deprivation of rights acquired under preexisting contracts.[14]
*456 Finally, the majority's reliance on Fuller[15] is misplaced. Fuller involved a controversy over jurisdiction. The issue there was not whether the City had the right to terminate the agreement, but only whether the proper forum to determine that issue was the circuit court or the PSC. Thus, Fuller is not dispositive of the question in this case because any statements made outside the context of the jurisdictional issue are dicta. Consequently, for the foregoing reasons, the effect of the PSC order was to confirm and validate the terms of the contract, thereby adopting and incorporating those terms into the order, including whatever rights of termination were contained therein.
The only remaining question is whether the contract that existed between the parties was terminable at will. According to Williston:
"The general rule is that when a contract provides that one party shall render service to another, or shall act as his agent, or shall have exclusive sales rights within certain territory, but does not specify a definite time or prescribe conditions which shall determine the duration of the relation, the contract may be terminated by either party at will. It is true that such a result does not follow in every instance, because it is the intention of the parties which is the ultimate guide, and in order to ascertain that intention, the court may take into consideration the surrounding circumstances, the situation of the parties, the objects they apparently have in view, and the nature of the subject-matter of the agreement."
9 Samuel Williston, A Treatise on the Law of Contracts, § 1017A, at 150 n. 11 (3d ed. 1967 & Supp. 1991) (quoting Lubrecht v. Laurel Stripping Co.,
In this case I am not persuaded by the majority's conclusion that the parties' intent with regard to duration can be divined. The majority's primary explanation of the parties' supposed intentions is derived from the "nature" of the agreement. Although the majority's arguments have some merit, I do not think that this Court can ascribe an intention to the parties in the absence of any evidence whatsoever of their true intentions. The Fourth District's reasoning in Gulf Cities Gas Corp. v. Tangelo Park Service Co. is instructive on this point:
Where the language of a contract is ambiguous or unclear as to a particular right or duty, the court may receive evidence extrinsic to the contract for the purpose of determining the intent of the parties at the time of the contract. However, where a contract is simply silent as to a particular matter, that is, its language neither expressly nor by reasonable implication indicates that the parties intended to contract with respect to the matter, the court should not, under the guise of construction, impose contractual rights and duties on the parties which they themselves omitted. In our opinion the contract before the court was "silent" as to the duration of the defendant's duty to provide gas to Tangelo Park Subdivision. In that circumstance the normal rule is that the duty is terminable at will. And this rule should have been applied. *457253 So.2d 744 , 748 (Fla. 4th DCA 1971) (citations omitted) (emphasis added); see, e.g., BMW of N. Am., Inc. v. Krathen,471 So.2d 585 , 587 (Fla. 4th DCA 1985), review denied,484 So.2d 7 (Fla. 1986); 17A C.J.S. Contracts § 328 (1963) ("A term which the parties have not expressed is not to be implied merely because the court thinks it is a reasonable term, or because the contract is advantageous to one party or unjust to the other....") (footnote omitted)). Here, because the intention of the parties cannot be determined from the evidence, the contract must be terminable at will.
Admittedly, it may be better policy to find that the contract is not terminable at will. However, that is a separate question from whether the parties to the contract intended for the contract to be enforced indefinitely absent PSC approval. In the absence of some tangible proof of the parties intention, I would give them the benefit of their bargain as set forth in the plain wording of the contract. In this case, because the contract is silent as to duration, I would follow the rule as stated in Gulf Cities and find that the contract is terminable at will.
KOGAN and HARDING, JJ., concur.
NOTES
Notes
[1] § 366.11, Fla. Stat. (1967). In 1974 the legislature amended chapter 366 to confer upon the PSC limited jurisdiction over municipally owned electric utilities for certain purposes. Ch. 74-196, § 1, Laws of Fla. Among the powers granted was the authority "[t]o approve territorial agreements between and among rural electric cooperatives, municipal electric utilities, and other electric utilities under its jurisdiction or any of them; provided, nothing in this chapter shall be construed to alter existing territorial agreements as between the parties to such agreements." Id.
[2] The pertinent portion of the Commission's order read:
When a territorial agreement is approved by the Commission, it becomes embodied in the approving order which may only be modified or terminated in accordance with the Commission's express statutory purpose. See Fuller at 1212. Therefore, in order to withdraw or modify Order No. 4285, Homestead must make a showing that, "such modification or withdrawal of approval is necessary in the public interest because of changed conditions or circumstance not present in the proceedings which led to the order being modified." Peoples Gas System, Inc. v. Mason,
[3] We have jurisdiction. Art. V, § 3(b)(2), Fla. Const.
[4] If the agreement had provided for termination after a certain period of years, it would have terminated at the end of that period. In such case, general case law governing the modification and termination of PSC orders would have given way to the express terms of the order.
[5] The law at the time of the agreement set forth that PSC orders could be withdrawn or modified at the initiation of the PSC, a party to the agreement, or an interested member of the public "after proper notice and hearing, and upon a specific finding based on adequate proof that such modification or withdrawal of approval is necessary in the public interest because of changed conditions or other circumstances not present in the proceedings which led to the order being modified." Peoples Gas Sys., Inc. v. Mason,
[6] See Southern Bell Tel. & Tel. Co. v. Florida E. Coast Ry. Co.,
[7] Florida-Georgia Chem. Co. v. National Labs. Inc.,
[8] FPL transferred 35 commercial and 363 residential customers to the City, and the City transferred 12 commercial and 66 residential customers to FPL. Storey v. Mayo,
[9] In City of Gainesville v. Board of Control,
[10] FPL, as a regulated utility, cannot terminate the agreement without PSC approval regardless of our construction of the agreement. Thus, the City is, in effect, claiming a unilateral right to terminate the agreement. See Southern Crane Rentals, Inc. v. City of Gainesville,
[11] The agreement provides that "[t]he parties acknowledge that the Company is regulated by the Florida Public Service Commission and that it will have to apply to the Commission for approval of this agreement." The agreement further states that "[i]f an order of the Commission is entered approving the agreement and the order becomes final, then as promptly as possible, each party shall transfer" facilities and customers located in the other's service area.
[12] See supra note 5.
[13] In re Petition of Florida Power and Light Company for a Declaratory Statement Regarding Territorial Agreement with the City of Homestead, 88 F.P.S.C 12:15 (1988). The Declaratory Statement uses the phrase "valid, binding agreement."
[14] Indeed, to construe the 1974 amendment as authorizing the PSC to alter the City's termination rights under the contract by conditioning their exercise on a showing of good cause would constitute an impermissible impairment of contract under article 1, section 10 of the Florida Constitution. See Park Benziger & Co., Inc. v. Southern Wine & Spirits, Inc.,
[15] Public Serv. Comm'n v. Fuller,