George Brox, Inc. (Brox), filed a third-party complaint against Gordon Construction Corp. (Gordon) seeking indemnification under the terms of a public works subcontract for payment made on a negligence claim. A Superior Court judge allowed Brox’s motion for summary judgment and denied Gordon’s cross motion for summary judgment. On appeal, Gordon challenges the judge’s rulings (1) that the subcontract became effective before the effective date of G. L. c. 149,
The material facts are not disputed.
Brox began work on the Haverhill project on March 20, 1985. Gordon began its work under the subcontract on November 19, 1985. On November 20, a reserve police officer from the Haverhill police department was working a paid detail at Brox’s request.
1. Central to this case is the meaning of the phrase “effective upon approval” appearing in section 19 of the subcontract. Gordon argues that section 19 created a condition precedent to the formation of the subcontract such that the subcontract did not come into existence until June 5, 1985, when the DPW approved Gordon as a subcontractor on the project. If Gordon is correct, then G. L. c. 149, § 29C, which became effective on April 7, 1985, would operate to nullify the indemnification clause of the subcontract. See Harnois v. Quannapowitt Dev., Inc.,
Contract conditions precedent generally are of two kinds. The first involves issues of offer and acceptance which precede and determine the formation of a contract. See Massachusetts Biographical Soc. v. Howard,
Where the language of a contract is not ambiguous, the words will be given their plain meaning, Freelander v. G. & K. Realty Corp.,
The subcontract at issue has all the components of a valid contract: offer, acceptance, consideration, and terms setting forth the rights and obligations of the parties. It was executed under seal. The parties are content that the subcontract was a complete expression of their agreement and that no other terms were left to negotiate. The condition of the DPW approval was created by express provision of the subcontract, and, upon such condition being met, the rights and obligations of the parties as defined by the subcontract would spring forth without need for any further action by the parties. This could only occur if the subcontract was in existence at the time the condition was met. Contrast Massachusetts Biographical Soc. v. Howard,
Significantly, Gordon concedes that beginning March 8, 1985, the executed subcontract eliminated the risk to Brox that Gordon would refuse to sign
Gordon relies on two decisions, Howland v. Plymouth,
We conclude that the parties intended the subcontract to
Though it will not affect the outcome, there remains the question whether the condition was precedent or subsequent. These terms have been the source of considerable confusion, and this case illustrates the reason for their discontinued use by the American Law Institute. See Restatement (Second) of Contracts § 224, Reporter’s Note at 164. The condition subsequent, like the condition precedent to the formation of a contract, is frequently mistaken for a condition precedent under an existing contract. See Restatement (Second) of Contracts § 230 (1981) (where it is now described as a discharge of obligation); Corbin, Contracts § 628. True conditions subsequent are considered rare. See 5 Williston, Contracts § 667; Calamari and Perillo, Contracts § 11-7 (3d ed. 1987).
The motion judge concluded that the subcontract created a condition subsequent because “the parties intended Section 19 to relieve [them] of their obligations in the event the DPW did not approve Gordon.” See Wood v. Roy Lapidus, Inc.,
2. Gordon contends that since Maine’s interest in the application of its law to this dispute is greater than Massachusetts’s interest in having its law applied, the law of Maine should govern. Maine law prohibits enforcement of an indemnity agreement against an employer with workers’ compensation insurance unless the agreement contains a clear and express waiver of the immunity provided by the Maine Workers’ Compensation Act, Me. Rev. Stat. Ann. tit. 39, § 4 (West 1989). See Diamond Inti. Corp. v. Sullivan & Merritt, Inc.,
Massachusetts has adopted a “functional choice-of-law approach that responds to the interests of the parties, the States involved, and the interstate system as a whole,” where, as here, the parties have failed to agree upon a choice of law. Bushkin Assocs., Inc. v. Raytheon Co.,
We are satisfied that the motion judge considered the relevant factors enumerated in Bushkin, supra, including Maine’s interest in the administration of its workers’ compensation laws. One of the relevant factors, “the protection of justified expectations,” Restatement (Second) of Conflict of Laws § 6(2)(d) (1971), warrants attention. Gordon submitted its bid with knowledge that it would be required to obtain insurance coverage to indemnify Brox against all claims. Presumably Gordon’s bid was calculated with that expense in mind, especially where Brox and Gordon had a history of working together on Massachusetts public construction projects. Gordon entered this transaction with its eyes open, and the result here fell within the negotiated expectations of the parties. Gordon’s contention would not promote that expectation, but rather would topple it and significantly alter the economics of the project. We agree with the motion judge that the Commonwealth’s interest in the application of its laws to a subcontract under a public construction project funded by an agency of the Commonwealth pursu
Judgment affirmed.
Notes
The case was submitted on an “agreed statement of facts.”
“Any provision for or in connection with a contract for construction . . . including without limitation, excavation, backfilling or grading, ... on any real property, including without limitation any road, bridge, tunnel, sewer, water or other utility line, which requires a subcontractor to indemnify any party for injury to persons or damage to property not caused by the subcontractor or its' employees, agents or subcontractors, shall be void.” G. L. c. 149, § 29C, as appearing in St. 1985, c. 228, § 3.
See G. L. c. 149, § 34B.
Gordon invokes the provisions of 301 Code Mass. Regs. § 50.17, Appendix 2 (1996), which declares void any subcontract executed before written approval is obtained from an authorized representative of the applicable State agency that the subcontractor’s certification has been incorporated into the subcontract. Gordon’s claim that this regulation evidences the parties’ intent that the subcontract would have no existence until the DPW approval is undermined by the fact that the parties never reexecuted the subcontract after the DPW approval. Further, Gordon cites no authority for the proposition that an agency has authority to effectuate a forfeiture of contractual rights in the absence of statutory authority. Compare Valley Stream Teachers Fed. Credit Union v. Commissioner of Banks,
Decisions such as Eckstrom, supra, which, apart from issues of escrow, turn on conditional delivery, have been criticized as mistaking a condition precedent to the formation of a contract for a condition that arises, expressly or impliedly, from an existing contract. See Corbin, Contracts § 589; 5 Williston, Contracts § 666. The confusion, it is said, derives from the approval of admission under an exception to the parol evidence rule of testimony that a writing which appears on its face to be a complete expression of the transaction was never intended to be binding unless a condition was met under the terms of a contemporaneous oral agreement. That reasoning is seen as faulty, because the parties indeed would have been bound by the writing, without more, had the condition been met, so the writing necessarily evidenced a valid, existing contract. Rights and duties arise under the contract, the critics maintain, upon the occurrence of the event described in the condition. In the
