207 Ky. 289 | Ky. Ct. App. | 1925
Opinion of the Court by
Affirming.
The appellant and defendant below, city of Frankfort, acquired by deed from the appellee and defendant,
This action was brought by plaintiff against the city to recover various items of damages for alleged violations of the terms of the contract, aggregating $977.50. The answer of the defendant was a denial, with the addiditional plea in a separate paragraph that the work of constructing the sewer was let to an independent contractor and that defendant was not liable for the violations of the terms of the contract by such contractor. Without demurring to that paragraph plaintiff denied it, and upon trial by a jury it returned a verdict in favor of plaintiff in the sum of $527.50, which the court declined to set aside on defendant’s motion for a new trial, and from the judgment pronounced thereon the city prosecutes this appeal.
1. The defense of independent contractor, relied on in ground (1), if available at all in this case, would not apply to. any of the damages sought to be recovered re-' suiting from a failure to maintain the open ditch or the dam at its mouth and consequent overflows resulting therefrom, since such injuries were not produced by anything done by the independent contractor but resulted entirely since the work was completed because of defendant’s failure to observe its contract to maintain those-parts of the structure and which it agreed to maintain in its contract. Eliminating such portions of the damage sued for, there remains, only the injuries to crops, roads and fences produced by the contractor in the construction work, none of which is it shown was the result of his negligence but only as a natural consequence of doing the work.
If it should be conceded that the defense of independent contractor is available in an action based upon the violation of contractual rights, a question which we do not determine, then the defense must fail in this case as to the later damagesi (growing out of the construction of the work) because they were the result of doing the work as contemplated, i. e., the construction of the sewer, including the use of the roads, the removal of the fences and necessary travel over plaintiff’s fields whereby the damages sought to be recovered were sustained.
. But the cases and citations referred to deal with actions sounding in tort, and none of them had under consideration the violation of contractual obligations. Here the defendant, city of Frankfort, expressly agreed to pay all damages, to plaintiff’s roads, crops and fences resulting from the doing of the work it had under contemplation and, clearly, it could not relieve itself from those contractual obligations by delegating the performance of the work to another. We, therefore, conclude that the court properly disallowed this defense.
2. In disposing of ground (2) but little need be said. In the first place no such defense as therein urged was relied on in the trial court, but if it had been interposed it could not be sustained, even if the work undertaken by defendant could be classified as one in the exercise of its governmental function (a question not decided), since such defenses apply to actions ex delicto and not to those ex contractu. Here the defendant expressly agreed to pay the character of damages now under consideration as well as those arising from its failure to maintain after completion the structures it had undertaken, and if it had the right to so, contract, it cannot avoid its obligations so assumed by urging that in entering into the contract it was engaged in exercising a governmental function. No, question is raised as to the authority of defendant to make the contract sued on or any part of it, and if it possessed such authority the conclusions hereinbefore expressed are so elementary as to require no extended discussion or the citation of supporting authorities.
We, therefore, conclude that the court properly overruled the motion for a new trial and the judgment is affirmed.