OPINION
The City of Corpus Christi (City) appeals from a judgment rendered against it and in favor of Heldenfels Brothers, Inc. (Helden-fels), on a claim for the value of materials and services furnished by Heldenfels under a subcontract for use in a City recreation center building. After a bench trial, based on theories of quantum meruit, unjust enrichment and negligent failure of the City to require its general contractor to provide a proper payment bond, the trial court rendered judgment for Heldenfels for the reasonable value of its materials and services in the amount of $23,250, plus interest and attorney’s fees. The City appeals by nineteen points of error, while Heldenfels brings one cross-point. We reverse the judgment of the trial court and render judgment that Heldenfels take nothing.
On May 18, 1983, the City hired La-Man Constructors, Inc., (La-Man) as general contractor to build improvements on City park land for the Meadow Park Recreation Center. The general contract provided for a lump-sum payment to La-Man of $267,-748.00, and La-Man agreed to provide the standard performance and payment bonds by corporate sureties duly authorized to do business in Texas, as required by the City on all such contracts in accordance with the MacGregor Act. Tex.Rev.Civ.Stat.Ann. art. 5160 (Vernon Supp.1990). La-Man provided documents which facially appeared to be the required bonds. Although the City accepted these purported bonds after only a cursory review procedure, it later discovered after La-Man abandoned the project, that the bonding company did not exist and that the bonds were fraudulent.
La-Man hired Heldenfels as subcontractor for $26,000.00 to provide concrete T-beams to support the roof covering the recreation center. Heldenfels constructed the T-beams, delivered them to the project, and completed all of its responsibilities under the subcontract before the end of October 1983. During the course of the project, the City made monthly payments to La-Man for the work completed, while retaining 10% until final completion of the project. La-Man’s own estimates as provided to the City listed $32,500.00 as the amount of its general contract price allocated for the T-beams. On October 5, 1983, the City authorized a payment to La-Man for the T-beams of $29,250.00 (not including $3,250.00 for retainage).
Meanwhile, on December 1, 1983, La-Man unexpectedly abandoned the project and is now in bankruptcy proceedings, leaving Heldenfels and other subcontractors unpaid. In February 1984, the City hired a new general contractor, Black Brothers (B & B), to complete the project for $83,-000.00. During the interim period between general contractors, the City did little to advance the project aside from maintaining the structure and hiring one of the subcontractors under separate agreement to complete minor repair work on the roof for $300.00. B & B substantially completed the project on June 22, 1984. The City claimed a number of incidental expenses associated with La-Man’s walkout and liquidated damages for delay in completion, leaving only $2,184.00 in excess funds which the City acknowledges may be due to La-Man.
The present suit is one of several to reach this court brought by subcontractors on the Meadow Park Recreation Center project seeking payment from the City. See
City of Corpus Christi v. Acme Mechanical Contractors, Inc.,
Because the City had no direct contractual obligation with Heldenfels to pay for the T-beams, nor was the City’s property encumbered by a mechanic’s lien, Heldenfels, in order to recover, had to rely on some other theory of liability. Heldenfels chose the theories of implied contract and negligence against the City. The trial court returned numerous findings and conclusions against the City on grounds of quantum meruit, unjust enrichment and negligent failure to require La-Man to provide a proper payment bond. By its nineteen points of error the City challenges each of the three grounds upon which the trial court granted judgment for Heldenfels. Heldenfels complains by its cross-point that the trial court erred in failing to award it the full $26,000 amount of its subcontract with La-Man.
By points of error one through five the City challenges recovery based on the theory of quantum meruit. Specifically, by points one and two the City challenges the legal and factual sufficiency of the evidence to show that the circumstances reasonably notified the City that Heldenfels was expecting to be paid by it. The trial court’s findings of fact are reviewable for legal and factual sufficiency of the evidence by the same standards applied in reviewing sufficiency of the evidence to support a jury answer.
Okon v. Levy,
The City contends that there was no evidence to show that Heldenfels reasonably notified it at the time Heldenfels provided the T-beams and they were incorporated into the project that Heldenfels would look to the City for payment if La-Man defaulted. Heldenfels never actually informed the City that it expected to be paid by it before La-Man abandoned the project. Helden-fels relies upon the testimony of two of its employees to show that the City knew before Heldenfels provided the T-beams that it would look to the City for payment.
Kurt Schriefer, who prepared Helden-fels’ cost and price estimate for the Meadow Park project, testified that the City accepted, used and enjoyed the T-beams in question “under such circumstances as Hel-denfels Brothers reasonably notified the City that they expected the City to pay for that work.” Schriefer, however, never reveals what those circumstances were that supposedly notified that City that Helden-fels would look to it for payment. In addition, attorney H.C. Heldenfels testified that it is normal to approach the owner for payment when neither the contractor nor the bonding company make payment, and that he would be greatly surprised if the City was not aware of Heldenfels’ expectations before it began work on the project.
When the evidence offered to prove a vital fact is so weak as to do no more than create a mere surmise or suspicion of its existence, the evidence is no more than a scintilla and, in legal effect, is no evidence.
Kindred v. Con/Chem, Inc.,
Heldenfels additionally relies on the City’s subsequent actions as evidence that it assumed the responsibility to pay Hel-denfels directly for the T-beams. There is some authority for the proposition that a city’s actions in taking over the responsibilities of its general contractor may subject it to liability from the subcontractors. In
City of Ingleside v. Stewart,
In the present case, during the interim period after La-Man abandoned the project and before the City contracted with B & B to complete the project, no signifi
Nevertheless, Heldenfels attempted to show that the City later would have held it responsible for faults in the T-beams, and that the City thereby assumed responsibility to pay Heldenfels directly for the T-beams. However, though there was a great deal of examination and testimony about what the City might have done if it had found Heldenfels’ work to be defective, it is uncontradicted that the City ultimately found that Heldenfels’ product was sound and that the City never did assert any claims against Heldenfels or request it to do anything more on the project after La-Man abandoned it. We sustain the City’s first and second points of error.
By points of error six through twelve the City challenges the theory of unjust enrichment as the basis for Heldenfels’ recovery. Specifically, by points of error eight and ten the City argues that as a matter of law it has not been Unjustly enriched, because the City had no legal obligation to pay retained or withheld funds to a subcontractor, and Heldenfels as subcontractor had no lien against funds withheld by the City from the prime contractor.
It has been said that an action for unjust enrichment will lie where one person has obtained a benefit from another by fraud, duress or taking an undue advantage.
City of Corpus Christi v. S.S. Smith & Sons Masonry, Inc.,
Unjust enrichment is probably not an independent cause of action but merely characterizes the result whereby one fails to make restitution of benefits under circumstances which give rise to an implied or quasi-contractual obligation to return such benefits.
S.S. Smith,
However, we see no need to equate or distinguish the two causes of action in the present case, since we hold that Hel-denfels’ novel theory of unjust enrichment could be supported neither under quantum meruit nor under any separate and independent theory of unjust enrichment. Helden-fels recovered in the trial court under a theory of unjust enrichment based on the retention of certain funds by the City from La-Man under the general contract. Since the City retained these funds specifically because of its concern about possible defects in the T-beams, Heldenfels claimed a right to trace the retained funds to its own entitlement to payment from La-Man for these T-beams under the subcontract.
Under Tex.Prop.Code Ann. § 53.231 (Vernon 1984), a subcontractor may claim a
Regardless of the fact that the City may have gained an incidental benefit by Hel-denfels’ provision of the T-beams and the City’s retainage of certain funds from La-Man, and Heldenfels may have suffered a loss by La-Man’s failure to make payment under the subcontract, we hold that unjust enrichment may not be used to impose the equivalent of an equitable lien on the funds due under the separate general contract between the City and La-Man. The City’s eighth and tenth points of error are sustained.
By points of error thirteen through sixteen the City challenges the theory of negligent failure to require La-Man to secure a proper bond as the basis for Helden-fels’ recovery. Specifically, by points of error thirteen and fourteen the City argues that as a matter of law it cannot be held liable for its failure to assure proper bonding because it had no duty other than to approve the form of the bond.
The present dispute concerning the City’s failure to secure a proper payment bond from La-Man is governed by Tex.Rev.Civ. Stat.Ann. art. 5160 (Vernon 1987) (repealed) (former article 5160). Former article 5160 provided merely that the prime contractor on contracts in excess of $25,000 entered into with a governmental authority shall be required to execute statutory performance and payment bonds by corporate sureties duly authorized to do business in Texas, and that such bonds shall be approved as to form by the governmental authority. 1
In
City of Corpus Christi v. Acme Mechanical Contractors, Inc.,
By points of error seventeen through nineteen the City complains that Heldenfels is not entitled to attorney’s fees or prejudgment interest because it is not entitled to recover under any of its theories of liability. In view of our disposition of the City’s other points of error denying recovery, we sustain points seventeen through nineteen.
By a single cross-point Heldenfels complains that the trial court erred in failing to award it the full amount of $26,000. In view of our disposition of the City’s points of error and our determination that Helden-fels was not entitled to recover under any of its theories, we overrule Heldenfels’ sole cross-point of error.
We REVERSE the judgment of the trial court and here RENDER judgment that
Notes
. Article 5160 was subsequently amended to provide specifically for liability against a governmental authority which fails to secure a proper payment bond on contracts entered into after the effective date of September 1, 1989. See Tex.Rev.Civ.Stat.Ann. art. 5160 (Vernon Supp.1990).
