279 F. 57 | 6th Cir. | 1922
The city of Cleveland asks the reversal of a judgment rendered against it in the court below for about $22,000, as the net balance of the counterclaims of the parties.
At the outset, we must observe the subject of our power to review. The Walsh Company (which we shall call plaintiff) sued to recover from the city what was said to be the unpaid balance owing under a contract for the construction of part of a water filtration plant; the city, by counterclaim, asked damages against the Walsh Company and its surety for nonperformance of the contract; the parties stipulated in writing that a- jury be waived and that the issues be referred to a commissioner. The commissioner made a report, containing elaborate findings of fact and of law. Exceptions were taken by each party to the findings of law, as if to a master’s report in equity, and the trial court disposed of these exceptions and entered judgment according to the practice pursued in such cases in equity, and, we assume, in accordance with the state practice.
Under the practice as it existed before 1865, when there was a trial before the court without a.jury, the judge was practically an arbitrator, and ordinarily there could be no effective review; but an agreed statement of facts, signed by counsel and filed in the case, early came to be thought a part of the technical or primary record, equivalent to the special verdict of a jury; and the question whether the judgment lawfully followed on such agreed facts could be raised on error. If the judge made special findings of fact, they were extrajudicial, and not recognized by the appellate court.
common-law practice, or the trial judge may adopt and follow the state practice, indicating such adoption either by express order or by tacitly following such practice after the referee’s report, or the parties may, with the judge’s approval, stipulate to extend or narrow the referee’s functions.
The waterworks system in Cleveland, of which this new structure was to be a part, was maintained by fees charged to the users, and the funds to pay for this improvement were to be obtained from bonds sold or to be sold, and to the payment of which the revenues of the \vater department were to be devoted. The sections of the city charter claimed to be controlling are quoted in the margin.
The court below assumed that if the proceedings had been under the general municipal code of Ohio instead of under the Cleveland charter, and in a case where the certificate was necessary, the contract, as to the excess over $272,000 would be void for lack of the essential
The allowances for extra work amounted to about $7,500 for repairing an injury caused by the city, about $800 for another similar matter, and about $1,100 on account of a change made by the city in the plans and specifications.
“In some cases, whore the structure is a total loss, due to the defective materials or faulty workmanship of the contractor, and the owner elects not to reconstruct according to- the original plans and specifications, but in another location and upon new and different plans, the measure of damages is held to be the amount paid to the contractor for the original structure. See U. S. v. McMullen, 222 U. S. 460, 32 Sup. Ct. 128, 56 L. Ed. 269; U. S. v. U. S. Fidelity & Guaranty Co., 236 U. S. 512, 35 Sup. Ct. 298, 59 L. Ed. 698; Lincoln County v. Coast Bridge Co. (D. C.) 231 Fed. 468. Upon the facts here found, this rule obviously is not applicable, because, if the location and design of the original structure had been sufficient, the loss from faulty workmanship would have been slight and easily remedied.
“The measure of damages properly to bo applied is that applicable to a contract which has been substantially performed but into the performance of which have entered defective materials or faulty workmanship, or departures from the plans and specifications. In cases of this character, two rules have been applied, depending somewhat upon the circumstances of each case. One is that the contractor is entitled to recover the contract price diminished by .the difference between the value of the building to the owner in its defective condition, and its value if perfectly constructed. This rule is applied whenever the structure or building is useful to the owner in its defective condition and it is neither fair nor reasonably practicable to remedy the defects by the making of repairs. In other words, where there is a failure to complete the work, and such failure may reasonably be remedied by the expenditure of*70 additional labor and materials, or where the defects are of such a character that they may be fairly and reasonably remedied by the expenditure of labor 'and materials, the proper rule seems to be to deduct from the contract price s.uch sums as would be reasonably necessary to complete the work according to the contract or to make such repairs. Sutherland on Damages, § 699; Stillwell Mfg. Co. v. Phelps, 130 U. S. 520, 9 Sup. Ct. 601, 32 L. Ed. 1035; Gleason v. Smith, 9 Cush. (Mass.) 484, 57, Am. Dec. 62; Pelatowski v. Black, 213 Mass. 428, 100 N. E. 831. No finding, as has been said, is made by the master as to the difference in value, between the reservoir in its defective condition, and the contract price, nor how much less valuable the reservoir is to the owner by reason of faulty workmanship. No evidence seems to have been offered on this proposition. The burden of proof in that situation is apparently on the owner. Filbert v. Philadelphia, 181 Pa, 530, 547, 37 Atl. 545; District of Columbia v. Clephane, 110 U. S. 212, 3 Sup. Ct. 568, 28 L. Ed. 122. Apparently, the master’s conclusion is that the reservoir, except as to the collapsed portion, was worth as much with the faulty workmanship as it would have been with perfect workmanship, and that by reason of its original defective design, it was worth practically nothing in either condition, except as it served as a basis for the new and different reconstruction work provided for in the Casey contract.
“The sum of $56,350, found by the master to be necessary to remedy the faulty workmanship, would undoubtedly be the true measure of the city’s damages, if the structure had otherwise been adequate. Such expenditure would have been a reasonable and practical way of making repairs within the rules of law stated in the cases above cited. Moreover, it is the method of making repairs and the measure of damages provided in the contract for defects in material and workmanship, whether the necessity therefor arises before acceptance or afterwards and within the guaranteed period of one year from date of such acceptance. The difficulty of applying this rule is that the repairs were not made, for reasons for which the city alone was responsible. It would have been useless and unnecessary to make them in view of the method of reconstruction adopted by the city, and it is likewise true, upon the master’s finding, that it would have been useless to have made them if some such plan of reconstruction had not been adopted, for a reservoir would not thereby have been produced fit for the purposes for which this one had been designed and built. The original structure, with these defects, was just as valuable under the plan of reconstruction as would the original structure have been with perfect workmanship. In view of all these circumstances, the master was right in holding that the cost of repairs which were not made, and the making of which” would have served no useful purpose* is not to be taken as the true measure of the city’s damage.
“In this situation and in the absence of any finding of how much less the original reservoir in the defective condition was worth to the owner than the original contract price, or if perfectly built, the city is not entitled to complain of the measure of damages actually adopted by the master. The plaintiff does not complain. This measure, as already stated, is to deduct from the contract price,' all that was paid by the city to the contractor for that portion of the concrete work which was found to be defective by reason of faulty workmanship. The contractor ought not in equity to have or retain money paid to him for work done that was not good, but was faulty or defective. If the contractor is required to surrender all compensation for that part of the work which was thus found to be defective, it would seem to me that substantial justice is done.”
The plaintiff .has claimed that it should not have been charged with the $14,600 offset, and the city has insisted that it should recover the entire cost of its new structure, but neither claim has been saved for ruling here.
The judgment is affirmed.
Kearney v. Case, 12 Wall. (79 U. S.) 275, 20 L. Ed. 395; Gilman v. Illinois, 91 U. S. 603, 614, 23 L. Ed. 405; Dundee Co. v. Hughes, 124 U. S. 157, 160, 8 Sup. Ct. 377, 31 L. Ed. 357; Perego v. Dodge, 163 U. S. 160; 166, 16 Sup. Ct. 971, 41 L. Ed. 113.
Flanders v. Tweed, 9 Wall. (76 U. S.) 425, 428, 19 L. Ed. 678; Kearney v. Case, 12 Wall. (79 U. S.) 275, 283, 20 L. Ed. 395; Boogher v. Ins. Co., 103 U. S. 90, 95, 26 L. Ed. 310; Hodges v. Easton, 106 U. S. 408, 412, 1 Sup. Ct. 307, 27 L. Ed. 169; Madison County v. Warren, 106 U. S. 622, 2 Sup. Ct. 86, 27 L. Ed. 311; Bond v. Dustin, 112 U. S. 604. 607, 5 Sup. Ct. 296, 28 L. Ed. 835; Dundee Co. v. Hughes, 124 U. S. 157, 159. 8 Sup. Ct. 377, 31 L. Ed. 357; Andes v. Slauson, 130 U. S. 435, 438, 9 Sup. Ct. 573, 32 L. Ed. 989; Spalding v. Manasse, 131 U. S. 65, 66, 9 Sup. Ct 649, 33 L. Ed. 86. The Kearney Case specifies the different ways in which the record may show the existence of the written stipulation. In the Boogher Case certain facts outside the record were thought sufficient to raise an inference of such existence; but in the Dundee Caso the same facts were thought insufficient for the same purpose; and though tile Boogher Case has been very often cited, we find no case in which it has been followed on this isoint. As to what is a sufficient record, see Cudahy Co. v. Sioux Nat. Bank (C. C. A. 8) 69 Fed. 782, 16 C. C. A. 409.
See note 8.
To extend this challenge of the special findings to a case of non written waiver is seemingly inconsistent with the doctrine of Campbell v. Boyreau, 21 How. (62 U. S.) 223, 16 L. Ed. 96, and Rogers v. United States, 141 U. S. 548, 12 Sup. Ct. 91, 85 L. Ed. 853, that findings of fact in the old District Court were unauthorized — a doctrine affirmed as late as Campbell v. United States, 224 U. S. 99, 105, 32 Sup. Ct. 398, 56 L. Ed. 684 — when supplemented by the common holdings that as to the Circuit Courts, section 700, which recognizes findings of fact and enlarges the power of review, does not become effective unless the waiver is in writing. However, we think there is a substantial distinction. In the old District Court, findings of fact could not become a part of the record because they were wholly unknown to the practice; but in the Circuit Courts, since 1865. they might have been an authorized incident in every nonjury trial. The lack of a written stipulation pertains only to the matter of regularity, and when they are once made and filed, with the
In Shipman v. Straitsville, 158 U. S. 356, 361, 15 Sup. Ct. 886, 39 L. Ed. 1015, there had been no written stipulation, but a referee’s findings were thought to have become those of the judge, and for that reason it was concluded that the question was open whether they supported the judgment. This case clearly modifies the broad language of Bond v. Dustin, but, unless the court inadvertently gave a wrong reason, its effect cannot be confined to situations where there was a referee, as was done by Judge Thayer (Cudahy Co. v. Sioux Nat. Bank [C. C. A. 8] 75 Fed. 473, 474, 21 C. C. A. 428). The reason why no exception is necessary as a basis for review of the sufficiency of special findings is that they become a part of the record, instead of being proceedings on the trial to be brought in by bill of exceptions (Webb v. National Bank [C. C. A. 8] 146 Fed. 717, 719, 77 C. C. A. 143; Chicago, R. I. & P. Ry. Co. v. Barrett [C. C. A. 6] 190 Fed. 118, 123, 111 C. C. A. 158), and, for the same reason, once concede that special findings in a nonwritten waiver case become a part of the record, no resort to section 700 is necessary to give the right to review; the analogy to an agreed statement or a special verdict becomes perfect. This court has adopted and repeated the broad rule of Bond v. Dustin (City of Defiance v. Schmidt, 123 Fed. 1, 3, 59 C. C. A. 159), but neither in that case, nor in any other here authoritative, were there special findings and an effort to get this review. Our conclusion in the text is supported by inference from Paine v. Central Vermont R. Co., 118 U. S. 152, 158, 6 Sup. Ct. 1019, 30 L. Ed. 193, where findings were deemed part of the record, though not pursuant to section 700. It is opposed by Merrill v. Floyd (C. C. A. 1) 53 Fed. 172, 3 C. C. A. 494; Branch v. Texas Co. (C. C. A. 5) 53 Fed. 849, 4 C. C. A. 52; Rush v. Newman (C. C. A. 8) 58 Fed. 158, 7 C. C. A. 136.
Humphreys v. Third Nat. Bank (C. C. A. 6) 75 Fed. 852, 853, 21 C. C. A. 538; Wright v. Bragg (C. C. A. 7) 96 Fed. 729, 732, 37 C. C. A. 574; Philadelphia Co. v. Fechheimer (C. C. A. 6) 220 Fed. 401, 407, 136 C. C. A. 25, Ann. Cas. 1917D, 64. Dickinson v. Bank, 16 Wall. (83 U. S.) 250, 258, 21 L. Ed. 278, is not inconsistent with the existence of cases where the duty to make or refuse a particular finding of fact depends upon a question of law. In St. Louis v. Rutz, 138 U. S. 226, 241, 11 Sup. Ct. 337, 34 L. Ed. 941, the requested findings of fact may have involved conflicting evidence.
Dundee Co. v. Hughes, 124 U. S. 157, 160, 8 Sup. Ct. 377, 31 L. Ed. 357; Hecker v. Fowler, 2 Wall. (69 U. S.) 123, 131, 17 L. Ed. 759; Tiernan v. Chicago Co. (C. C. A. 8) 214 Fed. 238, 242, 131 C. C. A. 284.
Boogher v. Ins. Co., 103 U. S. 90, 26 L. Ed. 310.
Boogher v. Ins. Co., 103 U. S. 90, 98, 26 L. Ed. 310; Lupton v. Auto Club, 225 U. S. 489, 491, 495, 32 Sup Ct. 711, 56 L. Ed. 1177, Ann. Cas. 1914A, 690; Philadelphia Co. v. Fechheimer (C. C. A. 6) 220 Fed. 401, 136 C. C. A. 25, Ann. Cas. 19171), 64.
We find no express holding that whore the findings of fact aro those of a referee as such, there can be review of their sufficiency; the effort often has been to find them transformed into the judge’s findings; but we see no way to give them less standing ¡han those of a judge in oral waiver oases; indeed, they are of higher standing, because they have always become part of the record. See note 5 and Paine v. Central Co., 118 U. S. 352, 158, 6 Sup. Ct. 1019, 30 L. Ed. 393 (which held the trial not to be under sections 649 and 700); Roberts v. Benjamin, 124 U. S. 64, 71, 8 Sup. Ct. 393, 31 L. Ed. 334; Shipman v. Straitsville Co., 158 U. S. 336, 15 Sup. Ct 886, 39 L. Ed. 1015; Chicago, etc., Co. v. Clark, 178 U. S. 353, 364, 20 Sup. Ct. 924, 44 L. Ed. 1099; Steel v. Lord (C. C. A. 2) 93 Fed. 728, 35 C. C. A. 555; Shipman v. Ohio Coal Exchange (C. C. A. 6) 70 Fed. 652, 17 C. C. A. 313; Steger v. Orth (C. C. A. 2), 258 Fed. 619, 620, 170 C. C. A. 73; Demotte v. Whybrow (C. C. A. 2) 263 Fed. 366.
“Sec. 122. No contract, agreement or other obligation, involving the expenditure of money shall be entered into, nor shall any ordinance, resolution, or order for the expenditure of money be passed by the council or be authorized by any officer of the city, unless the director of finance first certify to the council or to the proper officer, as the case may be, that the money re
“Sec. 123. All moneys actually in the treasury to the credit of the fund from which they are to be drawn, and all moneys applicable to the payment of the obligation or appropriation, involved, that are anticipated to come into the treasury before the maturity of such contract, agreement or obligation, from taxes or assessments, or from sales of services, products or by-products or from any city undertakings, fees, charges, accounts and bills receivable or other credits in process of collection; • and all moneys applicable to the payment of such obligation or appropriation, which are to be paid into the treasury prior to the maturity thereof, arising from the sale or lease of lands or other property, and moneys to he derived from lawfully authorized bonds sold and a process of delivery shall, for the purposes of such certificate, be deemed in the treasury to the credit of the appropriate fund and subject to such certification.”
“Sec. 125. All contracts, agreements or other obligations entered into and all ordinances passed, resolutions and orders adopted, contrary to the provision of the preceding sections, shall be void, and no person whatever shall have any claim or demand against the city thereunder, nor shall the council, or any officer of the city, waive or qualify the limits fixed by any ordinance, resolution or order, as provided in section 122, or fasten upon the city any liability whatever, in excess of such limits, or release any party from an exact compliance with his contract under such ordinance, resolution or order.”
Kerr v. Bellefontaine, 59 Ohio St 446, 52 N. E. 1024; Comstock v. Nelsonville, 61 Ohio St. 288, 56 N. E. 15; Emmert v. Elyria, 74 Ohio St. 185, 78 N. E. 269; Akron v. Dobson, 81 Ohio St 66, 90 N. E. 123; Frisbie Co. v. East Cleveland, 98 Ohio St. 266, 120 N. E. 309.