155 P. 859 | Okla. | 1916
The defendants in error recovered a judgment in the lower court against the plaintiff in error for damages caused to them by an unreasonable delay in the performance of a certain contract which they had made with the city, which delay was caused by the failure of the city to furnish the material to be used in the performance of the work and was without fault on the part of the defendants in error. The lower court heard the evidence and rendered a judgment against the plaintiff in error for the sum of $295.50, with interest thereon from the 30th day of June, 1910, amounting to $52.19, which judgment was rendered on the 10th day of July, 1913. To reverse this judgment the city has appealed and has asserted two grounds for reversal: (1) That the evidence upon which the court rendered the judgment is insufficient to sustain the judgment; (2) that the rendition of the judgment for interest upon unliquidated damages was improper.
The evidence discloses that the defendants in error, in order to complete their contract which they made with the city, hired expensive machinery at so much per day and also employed skilled men to operate the same, for which they paid daily wages of so much per day to each man. The court found that the city had, without fault of the defendants in error, unreasonably delayed them in the progress of the work, and that the defendants in error *343 had been compelled to pay the rent of the machinery in question and the wages for the men during the time that they were delayed and rendered a judgment in their favor and against the city for the same.
We are of the opinion that this is a proper measure of damages in a case of this character, for if the city delayed the defendants in error in the progress of their work they would be entitled to recover from the city the damages accruing therefrom; that is, such as were proximately caused to them by reason of this delay, and if the defendants in error were compelled to pay the rent of the machinery and the wages of the men for the time they were delayed, that the amount thus paid by them would be recoverable against the city, and the same is the proximate damage flowing from this delay.
The machinery used by the defendants in error was of a very expensive character and required skilled men to operate it, and in the absence of an established rental value upon the market we cannot say that the court committed error in fixing the lease price as the prima facie evidence of its rental value in the absence of other evidence to the contrary. See Burgess etal. v. Felix,
Upon the second proposition of permitting the defendants in error to draw interest upon the damages as stated above, we are of the opinion that the lower court was in error to this extent, and that section 2848, Rev. Laws 1910, *344 does not authorize the recovery of interest upon an unliquidated claim of this character, for in the instant case it required a judgment of the court or a verdict of the jury to establish the claim of the defendants in error, and the general rule that interest upon unliquidated damages is not recoverable until reduced to a judgment must be applied in this case.
In the case of Cox v. McLaughlin, reported in
"The court below allowed interest on the amount recovered, from June 15, 1866. Appellants attack this portion of the judgment as unwarranted by the facts and law. It may be stated as a general principle that interest is not allowed on unliquidated damages or demands. This term 'unliquidated damages' applies equally to cases of tort, as slander, assault, and battery, etc., and to cases upon a quantum meruit, for goods sold and delivered, or services rendered. The reason of such denial of interest is said to be that the person liable does not know what sum he owes, and therefore can be in no default for not paying. The damages in such cases are an uncertain quantity, depending upon no fixed standard, are referred to the wise discretion of a jury, and can never be made certain except by accord or verdict. As to such damages there can be no default, and hence the initial point at which to fix the starting of interest is wanting. To this general rule there are many exceptions; and while it is said 'a demand is unliquidated if one party alone cannot make it certain, when it cannot be made certain by mere calculation' (1 Suth. Dam. 610), yet the same author, in the next sentence, adds: 'The allowance of interest as damages is not dependent on this rigid test.' A review of the cases relied upon in support of this last assertion assert this proposition: 'Whenever a debtor is in default for not paying *345
money, delivering property, or rendering services in pursuance of his contract, justice requires that he should indemnify the creditor for the wrong which he has done him.' Van Rensselaerv. Jewett,
"The case at bar is not an action upon an express contract between the parties. Such a contract, it is true, existed; and, had plaintiff recovered under it, he would have been entitled to interest upon the several payments provided for therein from the dates at which they fell due; but for reasons not now necessary to be enumerated a recovery upon the contract has been abandoned, and plaintiff counts upon a quantum meruit for the performance of labor and services, precisely as he might have done had there been no contract. His services, and the material furnished by him, were uncertain as to amount, character, value, and time of payment, until fixed by a verdict or findings of the court. They were not of a character to have a fixed or ascertainable market value. They could not be ascertained by computation, either in extent or value. Defendant was not in default for not ascertaining that which, outside of the abandoned contract, he could not ascertain except by an accord or by verdict or its equivalent. In Bank v.Northam,
We are therefore of the opinion that the judgment in this case should be modified and reduced to $288, with interest from the 10th day of July, 1913, the day of the judgment, until paid, and costs herein expended, and this cause is in all other things affirmed.
By the Court: It is so ordered.