29 Mont. 88 | Mont. | 1903
ME. COMMISSIONER CALLAWAY
In August, 1896, the defendant Cook entered into a contract with the plaintiff respecting the construction of a sewer along one of its streets. The defendant agreed to- erect fences and other obstructions around open trenches, or keepi lights burning at night, or both, to protect the traveling public during the prosecution of the work; and to pay all damages to persons injured by his neglect to give proper warning. As security for the fulfillment of his contract, he executed to- the plaintiff city
Defendants introduced testimony tending to 'sustain their answers, and at tbe conclusion thereof their counsel moved the court to instruct the jury to return a verdict for them. The court sustained tbe motion, and entered judgment thereon. Thereupon the plaintiff moved for a new trial, which motion was by tbe court overruled. From tbe order denying the plaintiff’s motion for a new trial, and from said judgment, tbe plaintiff appealed. Tbe appeal from the judgment has heretofore been dismissed. "The cause stands on appeal from the order only.
The issues presented will be discussed under twe beads, as tbe answer's of tbe defendants present different issues.
Did the court err in sustaining defendants’ motion aforesaid ?
Upon this subject our statute (Section 3586, Civil Code) provides: “In the interpretation of a contract of indemnity, the following rules are to be applied, unless a contrary intention appears: (4) The person indemnifying is bound, on request of the person indemnified, to defend actions or proceedings brought
If in a particular case the indemnitor had been requested to defend the action against his obligee under his contract of indemnity and neglected to do so, the judgment is conclusive against him. If lie had not reasonable notice of the action, or if, having such notice he was not allowed to control the defense, the judgment is only presumptive evidence against him. This' is a question to be decided by the trial court in the first- instance. Aside from his contention that he had no notice of the pendency of the Joyce action defendant insists that it does not appear from the Joyce judgment roll, or from, the p(roof adduced in this case, that the excavation into which Mrs. Joyce fell was one made by him in constructing the sewer. In this we differ from defendant. In her complaint Mrs. Joyce identified the excavation into which she fell as being upon. Main street, about one block; above the intersection of Copper and Main streets. The record shows, that Cook was a witness in the Joyce case; and also that at some time ppfior to tire trial he made an affidavit for a continuance therein on behalf of thp city in which he swore that he was the “contractor under the city of Butte for doing the excavation and putting in a sanitary sewer on Main street, between Quartz and Woolman streets, in the year 1896.” His witnesses in this case all testified concerning the manner in which the work was guarded and lighted, while defendant himself said, “I was the contractor constructing this sewer in 1896, and I remember the night of the accident, when Mrs. Joyce claimed to. have sustained some injuries there.”
Mr. Justice Story, in Miller v. Stewart, 9 Wheat, 703, 6 L. Ed. 189, expresses the general proposition of law in relation to the' liability of sureties as follows»: “Nothing can be clearer, both upon principle and authority, than the doctrine that the liability of a surety is not to be extended by implication beyond the terms of his contract. To the extent, and in the manner, and under the circumstances pointed out in his obligation, he is bound, and no further. It is not sufficient that he may sustain no injury by a change in the contract, or that it may even be for his benefit. He has a right to stand upon the very term®
Under tbe general rule above quoted, however, sureties are not permitted to escape liability by making agreements among themselves, or with their principal, of which the obligee has no notice. Upon this subject this court said, in Ney v. Orr, 2 Mont. 559 : “It may be considered as settled that a bond perfect on its face, and apparently duly executed by all whose names appear thereto, purporting to be signed and delivered, and actually delivered without a stipulation, cannot be avoided by the sureties upon the ground that they signed it on condition that it should not be delivered unless it was executed by other persons who did not execute it, where it appears that the obligee-had no notice of such condition, and there was nothing to put him on inquiry about the manner of its execution, and that he had been induced upon the faith of such bond to act to his own prejudice.”
But when a bond is delivered to the obligee, showing on its face that it is- incomplete, as that one of the persons named as sureties in the body of the bond has not signed, such fact is sufficient to place the obligee upon inquiry, and the obligee then becomes subject to such a defense as the surety asserts in this case. (Ney v. Orr, supra; Thomas v. Bleakie, 136 Mass. 568; Dair v. United States, 16 Wall. 1, 21 L. Ed. 491; State v. Wallis, 57 Ark. 64, 20 S. W. 811; Cutler v. Roberts, 7 Neb. 4, 29 Am. Rep. 371; Fletcher v. Austin, 11 Vt. 449.)
It was the duty of the cityi officers to have inquired concerning the completeness of the bond, and, if the city .must now lose, it is of its own fault. We therefore conclude that the court’s ruling as to the defendant Bray was correct.
It follows that the order as to the defendant Cook should be reversed and the cause remanded for a new trial, while as to the defendant Bray the order should be affirmed.
Eor the reasons given in the foregoing opinion. the order as to the defendant Cook-is reversed, and the