delivered the opinion of the Court.
Exceptions to the import were taken by both parties, all of which were overruled, with the exception of the reduction of the city’s claim for liquidated damages to the sum of $2,000; the report was in all things confirmed by the chancellor, and a decree in conformity thereto was entered.
In the case of the Kingsport Improvement Corporation v. W. H. Bostwick and United States Fidelity & Guaranty Co. et al., a number of the questions here made have been adjudicated, and any discussion other than their enumeration is deemed unnecessary. The refusal of the chancellor to stay proceedings on account of military service of the defendant Bostwick, the payment of earned estimates to Bostwick, and his assignees, as well as the authority of the chancellor to order an advisory reference, upon questions of law and fact, and the authority to fix compensation for the special master, were passed upon, and need not here be further considered. Also the decision of this court upon the former appeal in this case is the law applicable, and is conclusive of certain other questions here made. That the defendant Bostwick Avas in default upon his contract and the city warranted in giving notice and subsequently assuming charge of the work is clearly shown in the proof. The dual obligation of the surety has been heretofore determined, and the record does not disclose any proof warranting the conclusion that, in the execution of the bond, the surety was in any wise deceived or misled; certainly to one engaged in the business of professional suretyship the insistence of the building commission that the bond be made to comply with the statutory requirements and the citation of authority for the necessity therefor was an unambiguous request, the effect of compliance with which could not have been misunderstood.
The allegations of the bill as to the delay and default of the contractor in the performance of his contract are fully
It was the opinion of the learned chancellor that notice given within thirty days after abandonment by the prin
The bond has been determined one in compliance with the provisions of both the Act of 1915 (Priv. Acts 1915, chapter 192), under the authority of which the- contract was entered into, and the Act of 1899, for the protection of laborers and furnishers of material. The provision for notice by the terms of the instrument is applicable to the same in its character first mentioned. The Acts 1899, chapter 182, section 1, specifies that the contractor “shall first execute a good and solvent bond to the effect that he will pay for all the materials and labor used in said contract, in lawful money of the United States.” Notice of claims to the contractor’s surety is neither required nor provided for in the act, and by no construction will- the bond be held to impose requirements in addition to those designated in the statute, the effect of which in the case here would be to destroy the very protection which the act was intended to afford. The insistence of the defendant surety that it is released from all liability on its bond' because of unauthorized payments to the contractor or his assignees cannot be maintained. There is ample evidence in the record sustaining the finding of the master and the chancellor on this question. Under article 8 of the contract payment on earned estimates were to be made to the contractor; his right of assignment was in no wise restricted by the terms of the bond or the contract, and it is shown that all payments made were upon estimates for labor and material actually employed in the construction of the building — in fact, it is shown by the testimony of the contractor — that all moneys paid him on the contract
Error is assigned by the city to the action of the chancellor reducing the amount of its claim for damages on account of delay from $4,125, as found by the master, to the sum of $2,000. While it is true that interest upon the amount invested by the city, as held by the chancellor, may not be the measure of damage, being but an element to be considered, yet the amount fixed is, in our opinion, an equitable adjustment between the parties, and will therefore not be disturbed. Computing the time for' which the stated amount should be allowed upon the number of working school days of which the city was deprived, exclusive of holidays, and the extension granted on account of unavoidable delays, together with the period in which the receivership proceedings were pending and that of notice given by the city of its intention to take over the work, the amount fixed by the chancellor is a reasonable approximation of the amount the city is entitled to recover.
It is contended that the chancellor erred in not sustaining the award to the city for delay as a liability for which the surety should be held upon its bond. The stipulation for notice, accompanied by a statement of the principal facts showing the claim for indemnity, is a reasonable one, with reference to which the parties were at full liberty to contract, and is binding upon the city in its demand against the surety. There is no proof in the record showing compliance Avith this provision, and it cannot be held that the institution of suit was effectual for this purpose for
It is contended by the surety that the decree is erroneous in so far as it authorizes the city to apply the funds of the contractor in its hands to the satisfaction of its damages awarded for delay. We are unable to see upon what principle this insistence can be sustained. That the surety is entitled to be subrogated to any rights available to its principal is not to be questioned, and, were the funds in the possession of the city without claim of right or the principal entitled thereto, there could be no doubt of the surety’s right to obtain and apply the same in diminution of its losses on the bond; but it must be manifest that any right or equity of the surety must arise through, and is only coextensive with, that of the principal; here the city completed the work and is found entitled to damages on account of the default of the contractor; the latter is entitled to funds retained by the city only to the extent that the sarnie exceed the amount of the city’s award; the rights of the surety are no greater.
We do not find the case here presented one for the application of chapter 141 of the Acts of 1901, providing for additional liability in cases where the- refusal of the insurer or indemnitor to make settlement after demand is not made in good faith; the proof does not warrant the finding that the surety company was prompted by improper motives in its refusal to settle upon the bond, or that its defense of the suit instituted by the city was not in good faith. This must appear before the discretion of the court can be invoked. Silliman v. Life Ins Co., 135 Tenn., 646, 188 S. W., 273.
For the purpose of ascertaining enforceable claims in accordance with our findings herein, the case is remanded, and a reference therefor may be had in the discretion of the chancellor. Save as modified, the decree is affirmed.