162 Iowa 695 | Iowa | 1913
The city of Boone by its proper officers let to A. J. Gary a contract for the construction of a sewer. The agreed price of the work was $36,531.11. About the time the work was completed Gary found himself involved in financial difficulties, being largely indebted for labor and materials employed in the construction of the sewer, and for money borrowed by him in prosecuting the enterprise. A judgment in the sum of $1,500 had also been rendered against him for personal injuries sustained by one Seed through the negligence of Gary in carrying on said work. By the terms of the contract it had been agreed that if before final settlement was made between the city and the contractor it should appear that the latter had failed to pay for labor and material used in constructing the sewer, the city was authorized to
But the appellant says that neither the trial court nor the city required the holders of these claims to perfect them under the provisions of Code, section 3102, which provides for preference to subcontractors upon a work of public improvement who properly file and give notice of their claims. But we think the rights of the laborers and materialmen in this case do not depend upon their compliance with that provision, and the city was not required to insist upon compliance with it. The right to make payment of such claims was reserved in the contract. In other words the right is contractual — not statutory. The city in such case is bound only to take care that the debts it thus assumes to pay for the contractor are bona fide claims for labor or material, and if this be done, other creditors who are thus postponed suffer no wrong. Counsel argue this feature of the case on the theory that this provision of the contract was intended solely as a protection to the city against the assertion or enforcement of claims under the statute above cited. "We do not so construe the agreement. It was the right of the city in letting the contract to insure, so far as practicable, that the money which became due to the contractor should be applied to the payment of its
II. It will be observed that Gary had received and put up as collateral with the Boone bank $25,000 in sewer certificates. Gary’s order given to the Denison bank was not an order on the city, but on the Boone bank, and seems to have contemplated that the latter bank would release some of its collateral to the former. The debt to the Boone bank was something over $20,000, and after satisfying this, as we have already noted, it turned the remainder over to the Denison bank. It is not clear just how this transaction puts the Denison bank in position to assert any right to recover from the city. True the Boone bank held something in the nature of an assignment or order from Gary for all his earnings under the contract, and it had accepted Gary’s order for certificates in favor of the Denison bank. But the assignment or order to the Boone bank was confessedly a matter of security only for its advances or loans to Gary. So far as appears, no more than $25,000 in certificates were ever delivered under this order, and this amount proved enough to pay the debt in full, with a remainder of over $4,000, of which the Denison bank got the benefit. The collateral having served its purpose, and the debt it secured having been paid, it is, to say the least, a matter of doubt whether the Boone bank had any legal right to call on the city for additional certificates for no other purpose than to turn them over to the Denison bank in satisfaction of the order which it had accepted. But the defendant being the only appellant, that matter is perhaps not directly involved
III. There is a suggestion in the record that the sum withheld by the city and brought into court does not represent the full amount due and unpaid to Gary, but we find no evidence upon which we would be justified in reaching such a conclusion.
Counsel further seems to think that while as between Gary and the city the latter would be justified in withholding the amount of the Reed judgment, yet that in some way the appellant’s right has “intervened,” and that judgment should have been rendered for this item against the surety company, thus increasing by that amount the sum left to apply bn appellant’s claim. In our judgment this cannot be. The appellant, a general creditor, could not thus acquire any intervening rights which would disturb or change the relation existing between Gary and his surety and the city which was the obligee in the bond. The utmost effect of the order or assignment under which appellant claims would be to place it in Gary’s stead. The stream cannot rise above its source, and if Gary could not successfully object to the payment of the judgment from the funds in the city’s hands, the appellant as his assignee cannot object.
The record is not entirely clear as to some of these details,
The decree of the trial court is Affirmed.